260 likes | 401 Views
LCLS Undulator Systems Beam Loss Monitor. William Berg ANL/APS Diagnostics Group. Introduction. Physics Requirements Document: Heinz-Dieter Nuhn 9-28-07 (prd: 1.4-005-r0 undulator beam loss monitor). Scope Reduction : diagnostic to mps detector. Purpose and Requirements.
E N D
LCLS Undulator SystemsBeam Loss Monitor William Berg ANL/APS Diagnostics Group
Introduction • Physics Requirements Document: Heinz-Dieter Nuhn 9-28-07 (prd: 1.4-005-r0 undulator beam loss monitor). • Scope Reduction: diagnostic to mps detector. • Purpose and Requirements. • Budget: M&S 500k (325k detector, ctls/mps 175k). • Schedule: (design: nov-mar, test: feb-mar, fab: mar-jun, inst: july). • Organization: 4 groups. • Group Definition: controls, detector, simulation, test & calibration. • Design Highlights and System Overview (detectors: dynamic 33, static: 2, r&d fiber:1). • Detector design details and focus topics. • Funds are limited and efforts need to be focused to minimize costs (h-dn). • Simulation of losses and damage in the undulator will proceed in parallel with the present effort (pk).
BLM Purposeh-dn • The BLM will be used for two purposes: • A: Inhibit bunches following an “above-threshold” radiation event. • B: Keep track of the accumulated exposure of the magnets in each undulator. • Purpose A is of highest priority. It will be integrated into the Machine Protection System (MPS) and requires only limited dynamic range from the detectors. • Purpose B is also desirable for understanding long-term magnet damage in combination with the undulator exchange program but requires a large dynamic range for the radiation detector (order 106 ?) and much more sophisticated diagnostics hard and software.
BLM requirements pk • Primary function of the BLM is to indicate to the MPS if losses exceed preset thresholds. • MPS processor will rate limit the beam according to which threshold was exceeded and what the current beam rate is. • The thresholds will be empirically determined by inserting a thin obstruction upstream of the undulator. • Simulation of losses and damage in the undulator will proceed in parallel with the present effort.
Draft Budget Breakdown • 500kM&S Total • 325k Detector Development • 25k Interface Box • 150k Control and MPS integration • 25k link node chassis • 25k long haul cables • 50k davis bacon labor • 15k ctl modules and signal conditioning electronics • 25k clean power distribution • 10k racks
LCLS MPS Beam Loss Monitor System Engineer: W. Berg Cost Account Manager: G. Pile Technical Manager: D. Walters Scientific advisor: P. Krejcik* FEL Physics: H. Nuhn* Scientific advisor: B. Yang FEL Physics: P. Emma* Controls/MPS Group Lead (ctls) : J. Stein Lead (mps): A. Alacron* Testing and Calibration Group Lead: B. Yang Detector Group Lead: W. Berg Simulations and analysis Group Lead: M. White M. Brown * R. Diviero E. Norum S. Norum * B. Laird J. Dusatko* A. Brill L. Erwin R. Keithley J. Morgan J. Dooling B. Yang W. Berg J. Bailey J. Dooling L. Moog E. Norum M. White * Slac employee
MPS Beam Loss Monitor Group Functions • Controls Group:J stein, A. Alacron Develop BLM control and mps system: • Interface Box and Control. • PMT Signal Conditioning. • Control and MPS Integration and User Displays. • Detector Group: W. Berg Develop Detector and Interface. • Simulations and Analysis Group: M. White Provide collaborative blm simulation support and test analysis. • Test and Calibration Group: B. Yang Provide beam based hardware testing programs and calibration plan.
Design Highlights • 33 distributed detectors (one preceding each undulator segment), two static units (up and downstream of undulator hall). • One additional channel reserved for r&d fiber based system. • Dynamic detector (tracks with undulator) 100mm stroke. Undulator position (in/out) detection will be used to set the corresponding mps threshold levels. • Large area sensor (coverage of the full horizontal width of top and bottom magnet blocks). • Manual insertion option via detachable arm for special calibration and monitoring. • Fiber Out for low gain upgrade (full integration and dyn range diagnostic), system expandable to 80 channels. • MPS threshold detection and beam rate limiting. • Single pulse detection and mps action up to max 120Hz beam rep rate via dedicated mps link. • Monitoring of real time shot to shot signal levels and record integrated values up to one second. • Heart beat led pulser for system validation before each pulse up to full rep rate (pseudo calibration). • Remote sensitivity adjust (dynamic range) by epics controlled PMT dc power supply (600-1200V). • Calibrated using upstream reference foil (initial use cal will be determined from simulation studies). • Radiation hard detector (materials and electronics).
BLM Controls Architecture pk • The BLM PMT interfaces to the MPS link node chassis. • The IO board of the MPS link node chassis provides the ADC & DAC for the PMT. • A detector interface box (pmt, led pulser, sig con?) is the treaty point between the MPS and the undulator BLM. • There are 5 link node chasses serving up to 8 BLMs along the undulator (expandable from 8 to16 channels).
Beam Loss Monitors with Link Nodes • Use Link Node to • support analog I/O IndustryPack modules • provide analog readouts to control system • set threshold levels • control HV power supplies • control LED Pulser
BLM System Support Focus Topics • 1. Assignment of Eric Norum to controls design oversight and testing. • 2. Funding of beam based prototyping and test program. • 3. Group Leaders to significantly step up direct involvement in system oversight, program implementation, and schedule tracking (controls: n. arnold, diag: g. decker, lcls: g. pile, ops/analysis: m. borland). • Active participation in simulations and simulation priority from slac. • Implementation of upstream profile monitor (halo or at min. cal foil). • Adequate analysis and shielding of upstream beam dump. • Develop long term collaboration plan for the pursuit of determining magnet damage mechanisms and thresholds via empirical methods. • Determine need and priority of BLM signal integration (diagnostic).
Summary • Undulator magnets protection is critical for machine commissioning period. • Schedule for development of the blm program is very aggressive and Funding is limited. • System design and fabrication must go in parallel with simulation and testing program. • Consider Minimum requirements for first level implementation. Taking advantage of existing mps infrastructure. • BLM system is now defined as a component of the mps with an upgrade path to a diagnostic (low gain detector). • 36 distributed channels (2 static devices) capable of single pulse detection and rate limiting reaction. • Detectors track with undulator position with detach option for manual operation. • Calibration plan and hardware is vital to proper system operation (threshold detection will use empirically derived levels).