1 / 13

Example

Example. A company purchases air filters at a rate of 800 per year $10 to place an order Unit cost is $25 per filter Inventory carry cost is $2/unit per year Shortage cost is $5 Lead time is 2 weeks Assume demand during lead time follows a uniform distribution from 0 to 200 Find (Q,R).

dorian-chan
Download Presentation

Example

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Example • A company purchases air filters at a rate of 800 per year • $10 to place an order • Unit cost is $25 per filter • Inventory carry cost is $2/unit per year • Shortage cost is $5 • Lead time is 2 weeks • Assume demand during lead time follows a uniform distribution from 0 to 200 • Find (Q,R)

  2. Solution • Partial derivative outcomes:

  3. Solution • From Uniform U(0,200) distribution:

  4. 0 200 R Solution • Iteration 1: F(R)

  5. Solution • Iteration 2:

  6. Solution • Iteration 3:

  7. Solution • R didn’t change => CONVERGENCE • (Q*,R*) = (94,190) I(t) 253 Slope -800 190 159 With lead time equal to 2 weeks: SS = R – lt =190-800(2/52)=159

  8. Example • Demand is Normally distributed with mean of 40 per week and a weekly variance of 8 • The ordering cost is $50 • Lead time is two weeks • Shortages cost an estimated $5 per unit short to expedite orders to appease customers • The holding cost is $0.0225 per week • Find (Q,R)

  9. Solution • Demand is per week. • Lead time is two weeks long. Thus, during the lead time: • Mean demand is 2(40) = 80 • Variance is (2*8) = 16 • Demand observed in one week is independent from demand observed in any other week: • E(demand over 2 weeks) = E (2*demand over week 1) = 2 E(demand in a single week) = 2 μ = 80 Standard deviation over 2 weeks is σ = (2*8)0.5 = 4

  10. Finding Q and R, iteratively • 1. Compute Q = EOQ. • 2. Substitute Q in to Equation (2) and compute R. • Use R to compute average backorder level, n(R) to use in Equation (1). • 4. Solve for Q using Equation (1). • 5. Go to Step 2 until convergence.

  11. Solution • Iteration 1: • From the standard normal table:

  12. Solution • Iteration 2: This is the unit normal loss expression. Table A - 4 gives values.

  13. Solution • Iteration 2:

More Related