AMERICAN SAMOA AIP PROJECTS IN HAND. ARFF STATION PAGO PAGO HOT FIRE TRAINING FACILITY FOR PAGO PAGO ARFF STATIONS FITIUTA AND OFU RAPID INTERVENTION VEHICLE PROVISIONING FOR PAGO PAGO ,FITIUTA AND OFU APRON PAVEMENT CONSULTANCY FOR PAGO PAGO ENVIRONMENTAL ASSESSMENT STUDY FOR OFU.
E N D
AMERICAN SAMOAAIP PROJECTS IN HAND • ARFF STATION PAGO PAGO • HOT FIRE TRAINING FACILITY FOR PAGO PAGO • ARFF STATIONS FITIUTA AND OFU • RAPID INTERVENTION VEHICLE PROVISIONING FOR PAGO PAGO ,FITIUTA AND OFU • APRON PAVEMENT CONSULTANCY FOR PAGO PAGO • ENVIRONMENTAL ASSESSMENT STUDY FOR OFU
ARFF STATION PROGRESS AT 4/1/05 • Overall project 68% complete • Main vehicle room and floor drains complete • Concrete roof to courtyard complete • Mechanical and electrical installation continuing • Painting of main vehicle room continuing
POURING OF ROOF SLAB ARFF PROJECT PAGO PAGO INTERNATIONAL AIRPORT Pouring of Final Roof Slab
ARFF PROJECT PAGO PAGO INTERNATIONAL AIRPORT AccommodationArea
ARFF PROJECT PAGO PAGO INTERNATIONAL AIRPORT FRONT OF STATION HIGHLIGHTING THE OFFICE AREAS
ARFF PROJECT PAGO PAGO INTERNATIONAL AIRPORT EASTERN END OF THE STATION SHOWING THE ENTRY TO THE RECEPTION AREA
ENGINE BAY ARFF PROJECT PAGO PAGO INTERNATIONAL AIRPORT Engine Bay
ARFF PROJECT PAGO PAGO INTERNATIONAL AIRPORT • STATION REAR Rear of Station
ARFF PROJECT PAGO PAGO INTERNATIONAL AIRPORT STATION DISPATCH AND ENGINE BAYS NOTE THE SHUTTERS IN THE ENGINE BAY DESIGNED FOR VENTILATION AND TO DEFLECT HURRICANE FORCE WINDS
NOAA WEATHER STATION State of the Art Hurricane Proofed Weather Facility