An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FiT Solar Auctions in IndonesiaLessons Learned from Participation of a Local EPC CompanyGerman-Indonesia Business Forum on Grid-Connected PV Systems Intercontinental Jakarta MidPlaza Hotel Erik C. Sentosa – Director PT. Suntech Solar System www.suntechsolarsystem.com

  2. List of Contents • Brief Company Introduction • Conditions of Solar Auctions • Auctions Progress • Lessons Learned • Summary & Recommendations Lessons Learned from Participation of FiT Solar Auctions in Indonesia – PT Suntech Solar System

  3. Brief Company Introduction • PT. Suntech Solar System established in 2007 • EPC Company for RE, specializing in PV (On-Grid, Off-Grid and Hybrid Systems) • Authorized Distributor & Partner in Indonesia for SMA and Suntech Power • Emphasis on technical expertise, detailed engineering, know-how, quality components and good installation Lessons Learned from Participation of FiT Solar Auctions in Indonesia – PT Suntech Solar System

  4. Conditions of Solar Auctions • Regions and system sizes defined by Ministry of Energy and Mineral Resources (ESDM) • Auctions held by Directorate General of New & Renewable Energy and Energy Conservation (EBTKE) • Total quota 140MW for 80 locations (regions) with sizes 1 to 6 MW • Ceiling Tariff : USD0.25/kWh for imported modules, USD0.30 for modules with local content >= 40% • PPA with PT. Perusahaan Listrik Negara (PLN) for 20 years without price adjustments • Bid language: Bahasa Indonesia • Auction open for state-owned enterprises , local goverment-owned enterprises, private Indonesian enterprises and bidding consortia • International companies via Project Joint Operation (KSO), JV or Consortium with private or state-owned enterprises in Indonesia Lessons Learned from Participation of FiT Solar Auctions in Indonesia – PT Suntech Solar System

  5. Conditions of Solar Auctions (Cont’d) • Online auction: register to http://lelang.ebtke.esdm.go.id • Download tender documents, Q&A sessions, upload of bid documents, evaluation progress & reasons • Tender documents: 120+ pages, fortunately most are identical for all locations • Contents: Administrative, Technical, Financial, Draft of PPA • Bid evaluation (elimination): Administrative -> Technical -> Financial -> Bid Price • Bid Bond 2% and Escrow Account 20% of overall project price Lessons Learned from Participation of FiT Solar Auctions in Indonesia – PT Suntech Solar System

  6. Conditions of Solar Auctions (Cont’d) • Tender Download – Upload of Bid: 14 days preparation • Bid Evaluation – Winner Announcement: 2-3 weeks • Make Escrow Account: 15 days after announcement • PPA Signing – Grid Interconnection Study: 60 days after announcement • Financial Close: within 3 months after PPA • Installation - COD: latest 18 months after PPA Lessons Learned from Participation of FiT Solar Auctions in Indonesia – PT Suntech Solar System

  7. Conditions of Solar Auctions (Cont’d) • Purchase price includes all cost of generation to point of grid interconnection • Purchase price are including VAT (PPN) 10% • Payment in IDR with exchange rate valid on the time of payment Lessons Learned from Participation of FiT Solar Auctions in Indonesia – PT Suntech Solar System

  8. Auction Progress • First tender started beginning November 2013 • So far total of 11 locations (19.5MW) tendered • 4 locations (4.5MW) out of 11 failed due to tender conditions are not met by participants • Lowest Bid Price: 18.36 cents US per kWh with imported modules • Last tender announced on March 2014, currently FiT solar auction program is under evaluation before more locations are to be tendered • No information when more locations are to be tendered • 70 (+4) locations with volume of 120.5(+4.5)MW are still to be tendered Lessons Learned from Participation of FiT Solar Auctions in Indonesia – PT Suntech Solar System

  9. Lessons Learned • Exact locations are not defined by ESDM • Insufficient coordination between ESDM-PLN-Local Government • GPS coordinates are required in bid document, no alternate location • Bid document requires land availability • Limited preparation time for complete bid documentations • Slightest error in bid documents will result in elimination • Insufficient or no data for grid conditions • Grid capacity only based on computer model simulation, different from actual at site survey • Grid connected PV capacity >20% of grid capacity -> prone to grid failure • Therefore, advanced region choosing - site survey - bid preparation needs to be done prior to tender announcement Lessons Learned from Participation of FiT Solar Auctions in Indonesia – PT Suntech Solar System

  10. Summary Site Survey after region choosing: • Coordinate with local ESDM – PLN – Local Govt – Local Land Authority for suitable sites • Make sure of land ownership (certificate) & price, not part of protected forest or conflicting with land allocation • Close distance to PLN Grid or Substation • Site is disaster-free (flooding, tsunami, landslides, etc.) • Site survey for grid conditions (load, capacity, future grid expansions) • Transport facility, access to site, handling facility, closest seaport & airport to site Continue to bid preparation before tender announcement Lessons Learned from Participation of FiT Solar Auctions in Indonesia – PT Suntech Solar System

  11. Reccomendations • Improve coordination between ESDM – PLN – Local Goverment – Local Land Authority to define suitable or “perfect” sites and set the land prices at a reasonable predetermined prices for the auction winners to reimburse • This would avoid a lot of uncertainties and unnecessary efforts, save time and money Lessons Learned from Participation of FiT Solar Auctions in Indonesia – PT Suntech Solar System

  12. Thank You • Vice-Minister of ESDM and Director General of EBTKE once said “..IPP investors are like heroes and pioneers..” • Let’s become heroes together and for each other.. Dipl.-Ing. Erik Chandra Sentosa Director – PT. Suntech Solar System Email: erik@suntechsolarsystem.com Lessons Learned from Participation of FiT Solar Auctions in Indonesia – PT Suntech Solar System