Get the latest updates on the construction progress of the Anschutz Health Sciences Building, including excavation, concrete foundations, and tower crane installation. Learn about R2 impacts and mitigation efforts, air intake monitoring, and equipment requirements. Contact Doug Wilson for more information.
E N D
The Anschutz Health Sciences Building Construction Update 8 April 2019
Current and Upcoming Activities • R2 Impacts and Mitigation Efforts Agenda
Lagging and Excavation, including S Tunnel: Complete by April 17 North Tunnel: Excavation, East 3rd week of June, West 2nd week of October Drilled Cassion’s: Complete By May 24 Concrete foundations, Walls, etc.: Start April 26th Tower Crane Install: End of April
Research 2 Impacts • Air Intake • Mitigation Efforts • Equipment Requirements: Tier 4 • Intake Filters: Completed on March 12 • Air Diffuser Filters: Installed at areas of concentrated concern • R1 and R2 Intake Monitoring: Reports available starting on March 13. • AHSB Project has purchase forty (40) Charcoal filter air cleaners, which will be installed throughout R2. • Review of alternate entry points, i.e. R2 loading dock • Information can be found on the Facilities Active Projects website • http://www.ucdenver.edu/about/departments/FacilitiesManagement/FacilitiesProjects/ActiveProjects/Pages/AnschutzHealthSciencesBldg.aspx • Contact Information • Doug Wilson, doug.wilson@caaicon.com