580 likes | 759 Views
CEQA Roles for CUPA's Regarding Hazardous Waste . Not Tiered Permitting, This is MinisterialNot Inspections, These are Not Projects Not Shut Downs or Denials, These are Not Projects Therefore:Mostly Corrective Action Cleanups Also Commenting on Brownfields Development Projects that Need Cleanup
E N D
1. Cal CUPA Conference, San Francisco February 2010Eric Maher, DTSC INTRODUCTION to the CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA)
2. CEQA Roles for CUPA’s Regarding Hazardous Waste Not Tiered Permitting, This is Ministerial
Not Inspections, These are Not Projects
Not Shut Downs or Denials, These are Not Projects
Therefore:
Mostly Corrective Action Cleanups
Also Commenting on Brownfields Development Projects that Need Cleanup
3. CEQA’s Basic Statutory Premises
3 One Sentence Nutshells:
Decision Makers Must Consider the Impacts of a Project on the Environment Prior to Approving It
If Significant Impacts Exist, Attempts Must be Made to Mitigate or Alternatives to the Project Considered
Inform the Public and Allow Comment on this Evaluation
4. CEQA Law Sources Statute – now included in:
Public Resources Code 21000 et seq.
Regulation “CEQA Guidelines”
Title 14 Cal. Code Regs. 15000 et seq.
(regulations of the Resources Agency)
Legal Decisions (largely in guidelines as well)
Agency Guidance and Policy
Thresholds, procedures, forms, manuals
5. Are You the Lead Agency ? Prepares the CEQA Document
Defined as the First Permitting Agency or
the Agency with the Primary Overall Authority
Must consult with Responsible Agencies to Avoid Multiple CEQA Documents for one Project
Must consider Trustee Agency Authority
Address Comment of Other Agencies
6. Responsible vs. Commenting Agency Roles A Responsible Agency is one that will use the Proposed CEQA Document of Another Agency to make a Discretionary Decision
Process is Laid Out in Title 14. CCR Section 15096
Commenting Agencies May have Expertise or Authority but will not be approving the Project or Using the CEQA Document
7. Trustee Agencies Must be consulted when projects impact their jurisdiction of resources held in trust for the people of California.
Fish and Game: fish and wildlife, rare or endangered species, game refuges, ecological reserves
State Lands Commission: state owned “sovereign” lands
Parks and Recreation: units of state park system
University of California: natural land and water reserves system
8. The Procedural Hierarchy Is it project that triggers CEQA? (discretionary)
Is Subject to an Exemption?
Categorical
General Rule
Statutory
9. The Procedural Hierarchy Are there Significant Impacts based on Analysis? (typical tool is an Initial Study)
Can they be Mitigated?
Does Remaining Impact Require an Environment Impact Report for: Further Analysis, Alternatives, or Overriding Findings
10. What is a Notice of Exemption (NOE) ? Not a CEQA Get Out of Jail Free Card
NOE Serves as a Surrogate for Both:
The Initial Study and
The Notice of Determination
Not Technically a CEQA Document,
It is Both:
An Environmental Analysis Summary
and
A Legal Defense of Your Conclusions
11. CEQA Exemptions PREMISE:
No Environmental Impact is not Implicit for Hazardous Waste Projects
But
Hazardous Waste Projects Typically Already Have Considerable Operational Controls on Their Activities by Lead and Other Agencies
QUESTION:
With These Controls in Place,
is the Potential Impact Controlled?
12. Benefits of an Exemption Process Requires Careful Description of Controls for Relevant Potential Impacts
but
Avoids the Least Relevant Parts of the Initial Study Checklist
Also Avoids:
Mitigation Measures Where Controls Are Already in Place and Monitored through the Permit or the Corrective Action Work Plan
13. Benefits of an Exemption Process Also Avoids:
Separate CEQA Comment Period, CEQA Public Notice and Response to Comments
(Draft NOE Documents are Supporting Evidence During Comment Period Instead)
Fish and Game Code De Minimus Impact
Finding or Fees
Discussion of Cumulative Effects
14. Risks of an Exemption
Must Meet Higher Standard
Limited Opportunity for Impact Assessment:
Conclusions Must be Readily Explainable Without New Lengthy or Detailed Analysis
Supporting Evidence Must Preclude:
A Fair Argument of Significant Effect or
Need for Additional Mitigation Measures
15. Risks of an Exemption Exemptions are One Agency, One Use
They are not a CEQA Document
that Other Agencies Can Use
No Comment Period May Mean Greater Potential for Legal Challenge
(partially ameliorated by DTSC’s NOE placement in public notice and repository during the project comment period)
16. CEQA Exemptions When Filed, the Notice of Exemption is
Your Statute of Limitations Notice
Starts a 35 Day Legal Challenge Period
So Treat Them As:
Freestanding
A Chance to Convince People not to Review
the Full Project File
Your First Line of Legal Defense
Draft it as You Will File It
Content Should not Change Substantially Following Project Comment Period
17. CEQA Exemptions Three Key Parts of the
Notice of Exemption
Project Description
Exempt Status and Title
Reasons Why Exempt
18. Project Description Content Who, What, When, Where, Why and How
Including Levels, Standards, Controls
State Project Objectives
Indicate Results of the Project and its Control Measures
Needs to be Written as Freestanding Document
Your Challenge: A Lay Person’s Level of Technical Knowledge, but Sufficient Detail
19. CEQA Exemptions For Corrective Measures:
Remedy Selection Is Part of the Decision
Basis for No Further Action Can Be An Important Part of the Decision and
Project Description
Especially If Health Risk Standards Are the Remedy Basis
So Can Land Use Covenants/ Restrictions
20. CEQA Exemptions The Basis for Your Exemption
and What You Must Justify
Four Types:
A. Statutory - Limited in Scope and Targeted
B. Regulatory Categories - from the Title 14
CEQA Regulations
33 Categories Available - We Use Only 3 or 4
Others Don’t Fit or Have Additional Restrictions
C. Emergency (Title 14) - Narrow Under CEQA
D. General Rule (Title 14) - Broad Scope - High Standard
21. Categorical Exemptions
in the CEQA Guidelines
(Title 14)
Minor Modifications to Existing Facilities (15301)
Investigative Activities (15306)
Regulatory Actions to Protect the Environment (15308)
Small Site Cleanups (15330)
22. Small and Medium CleanupsClass 30 (15330 ) DTSC Defined and Uses Frequently
Remediation of Hazardous Waste or Substances
Project Less Than $1 Million
Sites Cannot be on the Cortese List
Limits on Thermal Treatment
Limits on Relocation
Other Section 15300.2 limits apply
23. Title 14, section 15061 (b) (3)
Known as General Rule
Mostly Used for Sites on the Cortese List
or ”Misfits”
A Higher Hurdle:
With Certainty No Possibility
of a Significant Effect
24. CEQA Exemptions Emergency Exemption
(Title 14, Cal. Code Regs., section 15269)
Narrow Emergency Definition in CEQA
(Title 14, Cal. Code Regs., section 15359)
25. CEQA Exemptions Reasons Why Exempt
Use the Initial Study Checklist as Guidance for Relevant Questions
Consider Offsite Impact Issues as Well as
On-Site Controls
(Receptors, Land Use, Transportation, Upset)
For the Categoricals, Describe How
the 15300.2 Limits Don’t Apply
(Rule out Biological and Cultural Resource Areas, Scenic Highways and Cortese List)
26. Reasons Why Exempt Writing Style Tips
Treat as your First Line of Legal Defense
Be Assertive and Don’t Equivocate
Make Your Strongest Argument
Use Existing Controls
Don’t Assume Public Knowledge of the Permit
or Work Plan
Reasons Can Be Brief, If Concise
Lists and Bullets Are Good Tools
27. CEQA Exemptions If you Point to Another Supporting Document, Tell Them What Is In It, What It Does,
and How It Protects
Examples:
Health Risk Assessment
Transportation Plan
Health and Safety Plan
Dust Control Plan
Air Permit
28. CEQA Exemptions DTSC’s PROCESS:
Draft NOE Serves In Lieu Of Initial Study During Comment Period
NOE Is Draft, Unsigned in Repository and the Public Notice During Comment Period
NOE Is Signed When Permit or Work Plan
Is Approved, Filed Thereafter
29. Preparing CEQA Documents “CEQA is not an Independent Process, but
rather Must be Integrated into Project
Planning and Decision Making“
(Title 14 Cal Code Regs., Section15004 (c))
30. Preparing CEQA Documents An Initial Study will help determine the Appropriate CEQA Document:
- A Negative Declaration where either no significant environmental effects
- A Mitigated Negative Declaration where they can be mitigated or
- An Environmental Impact Report
31. Negative Declarations What’s An Initial Study?
Definition: A Preliminary Analysis Prepared by the Lead Agency to Determine if the Project may have a Significant Effect on the Environment
32. Initial Study Purpose (s) Facilitate environmental assessment early in the design of a project.
Provide information to use as the basis for deciding whether to prepare:
ND, MND, or EIR
Document the Factual Basis for Findings in a Negative Declaration that:
The project will not have a
significant effect on the environment.
33. Contents of Initial Study Project description
Environmental setting
Potential environmental impacts
Mitigation measures for any significant effect
34. The Initial Study Checklist Evaluation of Potential Impacts
OPR Checklist has 17 Categories
Is Development Project Oriented
Most HW Projects only AFFECT:
AIR QUALITY
WATER QUALITY
TRANPORTATION
HUMAN HEALTH
35. The Initial Study Checklist MUST ALSO RULE OUT:
Biological
Cultural Resources
HAZARDS (Earthquake, Flood) if long term or construction
Land Use Conflicts ( if Residual Health Risk is not Unrestricted Use)
36. The Initial Study Checklist If Redevelopment Project:
Consider Whether the Brownfield Cleanup is Separable from the Construction or Land Use Permits
Usually the Cleanup itself is not a cause of Population Growth, Utility Demand, Facility
Public Services Needs or Construction Impacts
37. State CEQA Comment Periods Negative Declaration 30-days (PRC 21092.3)
Environmental Impact Report
Notice of Preparation - 30 days
Draft Environmental Impact Report - 45 days
If Applicable, File 15 Copies with
Governor’s Office of Planning and Research, State Clearinghouse, for Circulation to State Agencies
38. CEQA Comment Periods Local Government Process Varies if Project is not Sent to State Clearinghouse
(e.g. 20 days for Negative Declaration)
Local Governments Can Have their Own CEQA Guidance, Processes and Forms as long as consistent with Title 14.
39. OPR Contact Information Governor’s Office of Planning and Research State Clearinghouse
1400 Tenth Street, Room 212
Sacramento, CA 95814
Scott Morgan, Acting Director
(916) 445-0613
40. Initial Study Tips Accurately Describe the Project
What Are You Being Asked to Approve?
Describe the discretionary action
Permit, permit modification, corrective action
Describe all proposed activities
Operation
Construction
Modifications
Cleanup goal
Forms the basis for determining potential impacts
Prepare a summary list in bullet form
Easy to transfer to affected area in Initial Study
41. Initial Study Identify Activities Likely to Create an Impact
Based on activities listed in the
Project Description
Narrows the scope of analysis to affected areas
List in bullet form within each affected section before conducting analysis
42. Initial Study Identify Activities Not Likely To Create an Impact
Declare “NONE”
Provide a brief explanation that supports the finding
“For these reasons, no further analysis of impacts to this resource category is deemed necessary”
Proceed to the next environmental resource category
43. Initial Study Describe Baseline Environmental Conditions
Existing Physical Characteristics Resources at and near the project site
Conditions as they exist at the time of the decision
Helps to establish what will be impacted
e.g., Air Quality - Level of Attainment/ Non-Attainment with Criteria Pollutants (PM 10, PM 2.5, ozone precursors, etc.)
e.g., Traffic/ Circulation - Level of service (LOS), preferred routes
44. Initial Study Describe Existing Ordinances, Regulations, or Standards that Apply to Project
Establishes Mitigation or Controls Already in Place
e.g., Hydrology/ Water Quality-allowable discharge levels, frequency of monitoring
e.g., Land Use/ Planning – zoning, allowed uses, restrictions
Defines Potential Exceedances that may
Create an Impact
45. Initial Study Thoroughly Analyze All Potential Impacts
Bullet items under each category must be examined to determine if potential impacts are “significant”.
They establish minimum threshold levels of significance
Look for physical changes (e.g., dust, noise, and traffic of heavy equipment)
46. Initial Study Provide evidence to substantiate findings
Must be based on substantial evidence in the record
Must be based to the extent possible on scientific & factual data
Speculation and hearsay are no substitute Not:
“I’ve been to the site, and didn’t see squirrels”
47. Initial Study Properly Document References
Identify the source document (person) used in the analysis of impacts for each bullet item
Allow Sufficient Amount of Time for Preparation and Approval
Don’t wait until just before decision has to be made
Avoid the Naked Checklist –
A checklist with out explanation or reference
is a target for comment and challenge
48. Other CEQA Forms Draft Negative Declaration
Notice of Completion
County Clerk Notice
DFG Code Finding of Deminimus
or fee ($2,010.25)
Decision Document (ND MND or
EIR Certification)
Notice of Determination following Public Comment and Approval
49. Negative Declaration vs. Mitigated Negative Declaration If Mitigation can be built into the Project prior to Public Notice, DTSC would use a Negative Declaration
Avoids a separate Mitigation Monitoring Plan
Other Factors to Consider:
Third Party Enforcing/ Implementing Agency?
Jurisdiction (e.g., endangered species)
Result
Mitigation Monitoring Plan - benefit?
50. Notice of Determination (NOD) Filing (NOD) with County Clerk or State Clearinghouse Triggers the 30 day Statute of Limitations
on Legal Challenges via
Superior Court Civil Suit
51. EIR Content Index & summary
Project description, location
Environmental setting
Significant environmental impacts
Alternatives (no-project, environmentally superior)
Areas of known controversy
Mitigation measures
Growth inducing impacts
Significant irreversible changes (plans, policies, joint NEPA documents)
52. Notice of Preparation Description of Project
List of Potential Impacts
If Focused EIR, “Expanded” Analysis of Those Impacts Not Significant and will not be Carried Forward to Focused EIR
30 day Comment Period
(Local or State Circulation)
Scoping Meetings ( Public, Agency )
53. Environmental Impact Report More Detailed Analysis of Significant Subjects
Consideration of Alternatives to Avoid Impacts
Allows Findings to Approve Project
if Mitigation or Alternatives Are Not Feasible or Benefit Exceeds Burden
“Statement of Overriding Findings”
54. Environmental Impact Report Contract for EIR preparation
Agency and Public scoping meetings
Public hearings on Draft EIR
EIR Certification that final EIR reflects Lead Agency’s
Independent Judgment/Analysis
55. Environmental Impact Report Draft Comment Period:
30 days if local only
45 days if State Clearinghouse
Review of Administrative Final EIR
10 days by Responsible Agencies
56. Environmental Impact Report Certification (approval)
Findings of Fact
Mitigation Monitoring Plan
NOD (30 days)
Fish and Game finding or fee
(currently $2,792.25)
57. EIR Findings Project changed to avoid or substantially reduce magnitude of impact
Changes needed to project to avoid impact are in another agency’s jurisdiction and have been or should be adopted
Specific economic, social, legal, technical or other considerations make alternative measure or alternative infeasible (Statement of Overriding Considerations)
58. Types of Environmental Impact Reports Focused
Supplemental
Subsequent
Addendum
Program
Master
General Plan Combined