Regional Organics Processing Facilities Study Summary and Next Steps Jennifer Morlock, CRWRP Chuck Smith, CH2M HILL
Presentation Outline • Background • Study process summary • Business Case Results • Recommendations & Next Steps
Background: 2003 Regional Waste Study 29% 36 % 25% 26%
Kick-off Meeting 11 municipalities represented • Organics = defined broadly • Objective defined • Success defined
No “Big Box Concept” at a single location • Calgary goal for waste diversion is 80/20 by 2020 – this is an opportunity that shouldn’t be missed • Take diversion to next level. Lead. Look to a progressive, sustainable future
Update of current facilities and processes • Questionnaires distributed to members • Facilities identified • Movement of materials (paper and organics) identified • Regional quantities determined
Compost Facility Capacities • 11,000 tpy green waste facilities • 8,000 tpy biosolids • 55,000 tpy ag waste
Series of Workshops • Tools and Stand Alone Reports Presented • Best Management Practices • Organics • Paper • Maps of Suitable Land Inventories presented
Series of Workshops Cont’d • Determination that • Recycling is the best practices for handling waste paper in the region • Composting makes the most sense for organics in the Calgary region • Ag wastes should be viewed as opportunities not impacts
Series of Workshops Cont’d • Options Explored • Policies • Sharing equipment / staff • Joint marketing • Harmonizing collection methods
Series of Workshops Cont’d • Triple Bottom Line • Decision Making Analysis applied to Facility Options
Social and Environmental Factors • Public Trust • Sustainable end-product • Build upon existing programs • Diversion from landfill • Flexible future • Regional unity • Environmental impacts • Air quality • Localized facility impacts
Workshop Conclusion • Proceed with developing a business case for this multi-site option • Potential for partnering with local Ag waste processing operations to reduce the overall peak design capacity (for Airdrie and Foothills)
Series of Workshops Cont’d 4. Presentation of business case
Capital and Operating Cost Size Cap Cost Unit Cost Facility (tpy) ($MM) ($/t) East Calgary* 162,000 55 44 FRSC landfill** 7,200 3.2 77 Canmore/Banff** 5,800 2.6 80 Airdrie** 4,200 2.0 76 Notes: * 50 day enclosed facility ** 21 day enclosed facility
Organic Processing Assumptions • Phase facility design • Expansion every 5 years over 20 year build-out • Initial processing capacity design at 60% of the projected 10th year peak month capacity • Residential organics recovery 72% • Biosolids included • IC&I Organic waste Capture 20% • Project growth at 1.6% per annum
Ownership Structure • Airdrie and FRSC currently public • Calgary and Canmore potential private, public or combination (P3) • Airdrie & FRSC could include agreements with Ag waste facilities
Ownership Structure Cont’d City of Calgary – Organics Facility RFP • Design/Build/Finance and Operate • Residential waste organics @ 55,000 tpy • 10 year operating contract w/ option for up to 5 year additional (one year renewable contracts) • City will provide land. Proponent has option to propose it’s own facility site
Financing • Self-financing by the host • User fees / disposal taxes • Provincial and Federal grants and funds (Initial FCM funding received)
Marketing Plan Initial elements include: • Benefit statement • Standards, quality, and reliable end product • Branding • Policies to promote purchase of organic waste products • An office, providing compost products, locations, and services • Educational information
Recommendations • That CRP Executive Committee approve the establishment of a Regional Composting Committee of staff made up of practitioners and elected officials from the four facility-owned members (Foothills (FRSC), Airdrie, Canmore/Banff and Calgary) and at least one non-facility member (MD of Rocky View) • That this CRP Regional Composting Committee, do the following: • develop workable plans and written agreement to technology, resources, equipment, • agree on composting standards that will be adopted for regional saleable end products, • refine the initial marketing plan for the CRP products and services, • review and agree on ownership/operating/financing structure, and • work with the City of Calgary and its RFP process to ensure an integrated regional organic waste facilities system
Recommendations (Cont’d) • That the Committee prepare a report which includes a more comprehensive go forward plan to CRP Executive Committee after the results of the City of Calgary’s Organics collection and processing facility RFP’s are analyzed and the City’s plans are better understood. This will likely be in March /April 2007, based on the City’s current project milestone schedule. • That CRP continue to pursue funding and allocate total funding to this project as follows: • FCM - up to $42,133 • CRP - up to $49,133 Up to $91,000 • That funding of up to a maximum of $20,000 only be budgeted for work up to the above noted March/April 2007 Report.
Thank you… Questions & Discussion