1 / 7

Project HCl - Wastegas

Project HCl - Wastegas. W aste gas conditioning from hydrochloric acid synthesis units Haimburger Rudolf 06/2010. The idea. Project: HCl - wastegas. page 2. H2. H2. H2. HCL ( ppm ). CL2 ( ppm ). HCL. Cl2. H2.

eavan
Download Presentation

Project HCl - Wastegas

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project HCl - Wastegas Waste gas conditioning from hydrochloric acid synthesis units Haimburger Rudolf 06/2010

  2. The idea Project: HCl - wastegas page 2 H2 H2 H2 HCL ( ppm ) CL2 ( ppm ) HCL Cl2 H2 aCollecting the wastegas and thermally reutilizing in an internal process.

  3. CO2 The facts Project: HCl - wastegas page 3 H2 HCL II HCL III HCL IV boiler ano waste gas in the atmosphere aHCl-units running in a closed system ano more HCl and ÖL ano more Cl2-issues iH2 as fuel in steam production iless oil consumption gless CO2-issues

  4. Concept Project: HCl - wastegas page 4 Kamin H2 HCL II HCL III HCL IV Targets: asafety boiler ano influence to the HCl-units ano corrosion in the steam-production. ÖL Safety analyse

  5. cleaning Implementation Project: HCl - wastegas page 5 PIC Druck- Messung H2 NaOH CL2 – Messung CL2 – analyse HCL II HCL III HCL IV boiler NaOH for Hypo ÖL H2 Online a chlorine-measurement a wastegas cleaning with 20 % NaOH aRPM-controlled booster pump a 17 parameters for monitoring the unit

  6. Profitability Project: HCl - wastegas page 6 ca. 1400 t/a CO2 weniger H2 HCL II HCL III HCL IV boiler aproduced HCl in year 2009: 313 t/d aoil-reduction: 70 kg/h ÖL ioil-savings in 2009 : 600 t/a iin euro(375 €/t):225.000€/a Project-costs:200.000 € ROI: less than 1 year

  7. The unit Project: HCl - wastegas page 8 First unit in europe