An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update: 30-Minute Emergency Response Service (ERS) Pilot Project Mark Patterson, ERCOT Technical Advisory Committee July 2, 2013

  2. Background • ERCOT Board approved 30-Minute ERS Pilot Project in June 2012 to test an ERS product with a 30-minute ramp capability. • 30-Minute ERS Features: • Dispatched as early as EEA Level 1 • Procured via market clearing price mechanism • Fleet-wide testing of Pilot Resources • Maximum of 8 hours of obligation • Only financial consequences for non-compliance; no suspensions • Procured through 4 Contract Periods • July15, 2012 through September 2012 (1st CP) • October 2012 through January 2013 (2nd CP) • February 2013 through May 2013 (3rd CP) • June 2013 through September 2013 (4th CP) ERCOT Public

  3. Growth in Participation • 937 unique sites offered in to 30-Minute ERS • 718 sites with no previous ERS-10 participation • 118 sites with more than12 months since last ERS-10 participation • Some sites that were unable to comply with ramp requirement of standard 10-Minute ERS product have migrated to 30-Minute ERS Pilot. • First ever ERS Residential Aggregations • QSEs have indicated that more sites would be willing to participate if 30-minute product was made permanent. ERCOT Public

  4. Performance and Testing • No EEA events during pilot period to-date • 7 fleet-wide test deployments: • 3 test deployments during 1st Contract Period • 2 test deployments during 2nd Contract Period • 2 test deployments during 3rd Contract Period • Generally, fleet-wide performance exceeds obligation: ERCOT Public

  5. Costs • 30-Minute ERS cost range: $7.80/MW/hr - $16.00/MW/hr • Comparisons to other services (see appendix for more detail): • Non-Spinning Reserve Service • BH1 & NBH ranged from $1.03 - $3.99 • BH2 & BH3 ranged from $2.34 -$21.41 • TDSP Load Management Program • $79.36/MW/hr • applies to BH2 and BH3 during Jun-Sep Contract Period only • Actual Pilot cost (through January 2013) - $2,038,052 • Estimated cost February –May 2013 CP: $1,167,837 • Estimated cost June – September 2013 CP: $2,983,493 ERCOT Public

  6. Next Steps • ERCOT will present updated report to Board of Directors at July 2013 meeting. • Pilot Project will end on September 30, 2013 if Board does not extend. • ERCOT intends to ask Board to extend Pilot by one Contract Period (October 2013 through January 2014) to allow development and discussion of NPRR integrating 30-Minute product. • NPRR could be in place for February through May 2014 ERS Standard Contract Term. ERCOT Public