640 likes | 805 Views
Microsoft Project Association. March 7, 2007. About Me. Jim Aksel, PMP Director of Project Management Celeris Systems, Inc http://www.celeris-systems.com Jim.aksel@celeris-systems.com Telephone: 714-813-4025. You get Credit!. You may claim 1 hour of CE (or PDUs) PMI References:.
E N D
Microsoft Project Association March 7, 2007
About Me Jim Aksel, PMP Director of Project Management Celeris Systems, Inc http://www.celeris-systems.com Jim.aksel@celeris-systems.com Telephone: 714-813-4025
You get Credit! • You may claim 1 hour of CE (or PDUs) • PMI References:
Backward Compatibility to 2003 Examples in Project 2007
1 Task Types 2 Resource Issues & Leveling AGENDA 3 Custom Sorting 4 EVMS in Project Conclusion
Custom Sorts EVMS Sorting Tasks Leveling Resources
Fixed Units Not Effort Driven Fixed Work TASKS Title Fixed Duration Not Effort Driven Fixed Units Effort Driven Fixed Duration Effort Driven
Task Type Definitions • Fixed Units • The allocations of resource units is held constant • Fixed Work • Total of all work hours assigned to a task is held constant • Fixed Duration • Task Duration is held constant
Effort Driven • Total task work remains at its current value, regardless of how many resources are assigned to the task. • When new resources are assigned, remaining work is distributed amongst all assigned resources, proportionately.
Added Resources Additional resources just increase total work with no change to duration
Adding Resources After %Complete Status Date: 15 FEB 2007 On Schedule
Progress Shown Status Date: 15 FEB 2007 On Schedule
New Resources Create Remaining Work Status Date: 15 FEB 2007 On Schedule
Adding Effort Driven Labor No Work Change Added to Basic Task, after making it Effort Driven Adding Resources reduces duration while keeping total work and units constant
Status Date: 15 FEB 2007 On Schedule Effort Driven Labor Added after %Complete Adding Effort Driven Labor keeps finish date and work constant, creates split
Adding Effort Driven Labor creates splits Status Date: 15 FEB 2007 On Schedule
Fixed Units Tasks • Not Effort Driven • Duration fixed • Adding Resources • adds remaining work • Increasing Work • increases Duration • New resources • add work after • Status Date • Effort Driven • Add Resources • Total Work Constant • Duration Changes • Add Work • Changes Duration • New resources • Add work after • Status Date
Not Effort Driven behaves as before Fixed Duration Tasks Adding resources divides remaining work among all resources
Status Date: 15 FEB 2007 On Schedule Fixed Duration w/%Complete Additional Resources share the remaining work
Fixed Work Task • Always effort driven Additional Work alters duration while respecting finish date
What Project Recalculates Task Type Fixed: ED: Effort Driven
EVMS Tasks Custom Sorts Resources Sorting Leveling
Resources • Individual names • Skill set grouping
Resource Types • Skill Set List • Department Wide • Easier to Assign • Interchangeable • Named Person • Unique Calendars • Retains Grouping • Skill Specific Advantages
Resource Types Disadvantages • Skill Set List • Department Wide • Homogeneous • Calendaring • Exact Costs TBD • Named Person • Wage/Privacy • Harder to swap • Skill Specific
Tasks Resources EVMS Leveling Custom Sorts Sorting
Leveling Order • Standard Project looks at predecessor, slack (a task with more total slack time is delayed first), dates (a task with a later start date is delayed first), priorities, and constraints • Priority, Standard Project looks first at priorities and then at predecessors, slack, dates, and constraints to determine whether and how tasks should be leveled
Leveling Parameters: • Day by Day Level resources when there is at least one day more work scheduled for a resource than can be completed within the resource's normal availability for that day. • Week by Week Level resources when there is at least one week more work scheduled for a resource than can be completed within the resource's normal availability for that week. • Month by Month Level resources when there is at least one month more work scheduled for a resource than can be completed within the resource's normal availability for that month. This is the default setting.
Leveling Example: • Ringo assigned to two 8 hour tasks in 1 day. • Leveling: • Day By Day: Problem • Week By Week: No Problem, work <40 • Month By Month: No Problem, work<160
Other Leveling Settings • Level only within available slack • Finish Dates are respected. • Leveling can adjust individual assignments on a task • Adjusts when a resource works on a task independent of the other resources working on the same task. • Leveling can create splits in remaining work • Any remaining work can be split for leveling. Unchecked will not delay a task with an Actual Start Date.
General Guidance • IMHO • Project does a pretty good job of leveling since it takes a methodical approach • However, it does level in resource order
Resources Leveling Tasks Sorting Custom Sorts EVMS
Standard Sorting Obvious Just Like Excel
Leveling Sorting Resources Custom Sorts Tasks EVMS
Some Grouping Ideas • Place custom text field in Resource Usage View • Group by CLIN, Job Number, other accounting information • Assign Control Account Managers • Supplier ID’s • WBS Field • Sort by defined code (such as first three levels)
Leveling Custom Sorts Sorting EVMS Resources Tasks EVMS is my personal opinion
EVMS in MS Project BCWS = Budgeted Cost of Work Scheduled BCWP = Budgeted Cost of Work Performed ACWP = Actual Cost of Work Performed
EVMS Comments • BCWS & BCWP only register in the Baseline Date Period • If you start/finish on different dates you must enter an Actual Date in the [Actual Start] or [Actual Finish] columns
MS Project uses %Complete Method • Think about it – Milestones, Incremental, 80/20, Formula, Apportionment are all subsets of %Complete • The trick is accurate definition of %Complete
Example: Concert • 6 Roadies take 2 days to setup • Fab Four sing some songs for 1 day • 3 Roadies tear down for 1 day
Resources • Singers make $500/hr • Roadies make $25/hr • Let’s assume everyone is paid cash at the end of each phase (setup, sing, teardown)
Baseline Schedule and Costs • We have a $19K EAC and 4 Days
%Complete Example • After Setup is complete, we claim 50% EV = $9,500 • We pay the roadies $2400