120 likes | 337 Views
Planning with Microsoft Project. Ivan Lloyd Corporate Project Solutions Ltd. Ivan_lloyd@cps.co.uk 07710 132013. Agenda. Do’s and Don’ts Key Issues MSP 2007 Stand Alone Highlights. Do’s & Don’ts. Do’s Use a template Display the Project Summary
E N D
Planning with Microsoft Project Ivan Lloyd Corporate Project Solutions Ltd Ivan_lloyd@cps.co.uk 07710 132013
Agenda Do’s and Don’ts Key Issues MSP 2007 Stand Alone Highlights
Do’s & Don’ts • Do’s • Use a template • Display the Project Summary • Set the working time & calendar to be equal if possible • Use one calendar • Use milestones for key events • Link all tasks • Baseline the project • Update the Project regularly • Assign resources to all tasks • Use target dates sparingly • Don’ts • Link summaries • Assign resource to summary tasks • Assign more than one resource
The Global.mpt • Stores Personal Standards e.g. • Views • Fields • Tables • Calendars • Maintained using Organiser
Calendars • Tools – Options – Calendar • Saved 1 per project and in the Global.mpt • Tools – Change Working Time • Defines Individual Working Calendars – available on the project on tasks & on resources • Start Time • End Time • Breaks • Non Working Days • Saved in the project (can be copied to global.mpt) • Can have many calendars • Ideally set both to be the same
Task Types • Fixed Duration • Changing the Duration changes the Work • Changing the Units changes the Work • Changing the Work changes the Units • Fixed Units • Changing the Duration changes the Work • Changing the Units changes the Duration • Changing the Work changes the Duration • Fixed Work • Changing the Duration changes the Units • Changing the Units changes the Duration • Changing the Work changes the Duration
Task Types • MS Default is Fixed Units, Effort Driven • Default setting is saved in the Global.mpt • Projects & Tasks can be different • Effort Driven • Only available for Fixed Work (Mandatory) & Fixed Units • Changes to units or work drive the assignment duration
Progress Update • Set Status Date • Save an Interim Baseline • Update Task Progress • % Complete (Task related) • % Work Complete (Assignment related) • % Physical Complete • Reschedule uncompleted work • Re-plan
2007 Highlights Multi–level undo Change Highlights Task Drivers Cost Resources Visual Reporting
Next StepsAttend A Corporate Project Solutions Microsoft Project Training Course (CPS 300, 301 & 302)Book within the next 30days and receive a 15% discount Ivan_lloyd@cps.co.uk 07710 132013