Group Members: Gilliland, John Goodell, Christopher Jemison, Jennifer Longden, Katherine Oliveira, Nickolas. Cost Estimating Phase II. Alternative A Estimated at $1,898,106.78. Included in Estimate:. Not Included in Estimate:. 11,048 S.F. of Heated Walkways 2 Pedestrian Bridges
E N D
Group Members: Gilliland, John Goodell, Christopher Jemison, Jennifer Longden, Katherine Oliveira, Nickolas Cost Estimating Phase II
Alternative AEstimated at $1,898,106.78 Included in Estimate: Not Included in Estimate: • 11,048 S.F. of Heated Walkways • 2 Pedestrian Bridges • 2762 L.F. of 24” retaining wall • 4 tons of Class 2A Fill & Back Fill • 1390 L.F. of Railings • Pods • Band Stand • Permitting • Landscaping • Utilities & Trenching • Storm water
Alternative BEstimated at $2,302,739.71 Included in Estimate: Not Included in Estimate: • 15,200 S.F. of Heated Walkways • 1 Pedestrian Bridge • 3750 L.F. of 24” retaining wall • 1914 tons of Class 2A Fill & Back Fill • 1875 L.F. of Railings • Pods • Band Stand • Permitting • Landscaping • Utilities & Trenching • Storm water
Pod DesignEstimated at $635,168.70 Included in Estimate: Not Included in Estimate: • 7,800 S.F. of Heated Walkways • 390 L.F. of 24” retaining wall • 390 L.F. of 36” retaining wall • 390 L.F. of Railings • 26 Park Benches (2 & 3 seat) • Permitting • Landscaping • Utilities & Trenching • Storm water
Band Stand DesignEstimated at: $411,017.55 Included in Estimate: Not Included in Estimate: • 1 Structure • 20 L.F. of Mechanical Compaction • 20 L.F. of Grading the Existing Surface • Seeding • Permitting • Landscaping • Utilities & Trenching • Storm water
Environmental & Permitting To Be Determined