Scientific highlights of ISIBHI G. Ciavola For the ISIBHI collaboration INFN- GSI- GANIL- JYFL- KVI - TSL- CERN– LPSC - NIPNE EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 1
Aims to: Improve the knowledge of intense beams production and transport Fulfil all the needs of the major EU accelerator facilities Maintain the EU leadership in the field of ECR ion sources EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 2
GOALS To design, build and test prototypes of ECRIS with a magnetic field still never reached and frequency ≥ 28 GHz • A Multi-purpose totally Superconducting ECRIS (MS-ECRIS, inspired from the GyroSerse project), with an adjustable magnetic configuration : Bmax = 4 T; Brad = 2.7 T; large ECR zone, f = 28 GHz according to our scaling laws • A more compact source, with a lower magnetic field and an higher power density (A-PHOENIX source) with a technology based on HTS coils and permanent magnets • Bmax=3 T; Brad~ 1.7 T to 2.2 T EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 3
A-PHOENIX • CAD Design achieved (05/2006) • Mechanical parts ordered to industry & to LPSC workshop (10/06) EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 4
HTS Coils 3 T axial field 20°K LHe free 2004 HTS Coils Specifications At LPSC 2005 HTS Coils builded at SpaceCryomagnetics LTD 2006 Coils quench protection electronics designed and builded at LPSC, delivered to SpaceCryomagnetics LTD • Final Reception Tests at Culham (UK) in December 18th-20th 2006 • Delivery at LPSC : January 2007 EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 5
Highlight : Large Permanent magnet hexapole 3 mm-2.3 T 5 mm-2.1 T 6 mm-2.05 T 2005 Hexapole final design LPSC Iron plates in the plasma chamber wall Iron plates width influence on Br • The strongest permanent hexapole in the world so far (2T on the magnets) 1.6 T in the plasma chamber (without iron plates) • 1.8 to 2.3 T in the plasma chamber using different iron plates geometries EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 6
A-PHOENIX hexapole assembly status • Last permanent magnets FeNdB received end of July 2006 • Lateral hexapoles builded successfully • Main hexapole assembly to start in late december 2006 Up to now, global planning has drifted of ~3 to 4 months Full program completion by the end of 2008 EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 7
SERSE MS-ECRIS f 18 GHz 28-37 GHz Bradial 1.55 T 2.7 T Binj 2.7 T 4.5 T Bext 1.6 T 3.2 T chamber 130 mm 180 mm L chamber 550 mm 650 mm cryostat 1000 mm 1200 mm L cryostat 1310 mm 1347 mm Au4 5+ Vextr 20-25 kV 40 to 60 kV LHe consumption ~4 l/h 0 O8+ ~7 pA ~ 20 to 50 pA Ar12+ 15 pµA 100 pA ~1 pnA ~0.1 pA Xe20+ ---- ~50 pA Pb27+ ---- 40 pA MS- ECRIS Multipurpose Fully Superconducting Magnets adapted to all accelerators EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 8
Cryostat & Magnetic System EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 9
One of the 6 Hexapolar coils Coils cos 3 windings Maximum field on conductor~ 7 T EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 10
Sextupole winding 4 months delay EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 11
MS-ECRIS assembly EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 12
Plasma chamber EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 13
waveguides 28 GHz and 14-18 GHz) estimated plasma flux oven feedthrough biased disk plasma diagnostics gas inlets Injection flange EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 14
60 kV DC Break 60 kV DC Break MS-ECRIS MS ECRIS Microwave transmission setup The refurbishment of the Gyrotron has drifted of 9 months, but will be ready still on time. EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 15
Movable cooled electrodes Extraction system UHV vacuum chamber EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 16
Inductively heated Resistively heated foil: 2000°C 2000˙C has been reached Space for high size ovens High performances ovens EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 17
Test bench layout at GSI EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 18
Planning • Magnetic system and cryostat are expected for the spring 2007 • Mechanics will be available at GSI at beginning of 2007 • Microwave generator and ancillary equipment at same time • First beam July 2007 • Test with gaseous beams in DC mode: 2nd half 2007 • Test with metallic beams in DC mode: 1st half 2008 • Test in pulsed mode: 2nd half 2008 EURONS PCC Meeting, Groningen, Holland, 11-12 December 2006 19