An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ATLAS MDT ElectronicsResponsibilities,Costs & Schedule Mezz HedgeHog CSM ROD MDT ASD AMT George Brandenburg – Page 1

  2. Design Responsibilities • HedgeHog Boards • Barrel: Pavia (HV), Rome III (signal) • EndCap: MIT (HV), Boston U (signal) • ASD Chip - Boston U and Harvard • AMT TDC Chip - KEK • Mezzanine Boards - Harvard and Boston U • Chamber Service Module - Michigan • ROD - NIKHEF George Brandenburg – Page 2

  3. Production Responsibilities • HedgeHogs (common production by CERN) • HV - INFN (all types) • Signal - Boston (EndCaps), Chamber-Builders (Barrel) • ASD - Boston U and Harvard • AMT-TDC - KEK • Mezzanine Boards - Harvard and Boston U • Chamber Service Module -To Be Determined! • ROD - (Freiburg, Munich LMU, Munich MPI) 20%, Nijmegen 41%, Saclay 33%, JINR 6% George Brandenburg – Page 3

  4. “Core” Cost Estimate • HedgeHogs (32,000 HV+signal): 1,892 kCHF • (assumes common CERN production) • AMT-TDC (16,000): 1,330 kCHF • Mezz Boards (16,000): 2,433 kCHF • (includes 45K ASD chips) • Patch Panels 382 kCHF • (replaced by Mezz -> CSM cable assemblies) • Off Chamber Electronics 1,682 kCHF • (does NOT include CSM) George Brandenburg – Page 4

  5. Cost Estimate Issues • HedgeHogs: Common production at CERN of all types now being planned to reduce costs. • ASD: Current HP quote is $375K ≈ 600 kCHF, but production must be finished before HP phases out process. • Mezz Boards: Quote for US production is $1,875K ≈ 3,000 kCHF –> CERN prod. is being investigated. • Patch Panels: No longer needed, but individual Mezz -> CSM cables (16,000) may cost more. • CSM: estimate for 1,320 modules is $1,221K ≈ 1,950 kCHF, however, funding source NOT yet determined! George Brandenburg – Page 5

  6. Production Schedule George Brandenburg – Page 6

  7. Mod-0 (10k) Test Schedule George Brandenburg – Page 7