Agenda. https://indico.cern.ch/conferenceDisplay.py?confId=181008. End 12:00 . Workpackage overview – R. Folch (25’ + 5’) Functional requirements of the BIDs – R. Folch (5’ + 5’) FLUKA simulations - A. Christov (15’ + 5’) Thermo-mechanical analysis – M. Delonca (25’ + 5’)
E N D
Agenda https://indico.cern.ch/conferenceDisplay.py?confId=181008 End 12:00 Workpackage overview – R. Folch (25’ + 5’) Functional requirements of the BIDs – R. Folch (5’ + 5’) FLUKA simulations - A. Christov (15’ + 5’) Thermo-mechanical analysis – M. Delonca (25’ + 5’) BREAK (15’) Conceptual and detailed design – M. Fürtinger (25’ + 5’) Controls for movable BIDs – R. Folch (10’ + 5’) Manufacturing strategy – R. Folch (15’) Discussion – All (15’) R. Folch EN/STI - BID Workpackage Review - March 2012
BID WP - Quality Assurance Scheme Ready for detailed design Ready for Manufacturing Functional requirements Conceptual Design 3D Detailed Design 2D OK Design office PTR, WRU Beam parameters - AFA Functionality- AFA Layout - UDO Power deposition Maximum temperature Mechanical stresses Material selection Mechanical pre-study EN/STI OK Integration – PTR, WRU Beam Diagnostics - FOS Vacuum Systems – PCR, THA, GHU, JWA Controls - JGU Alignment – AFA, WRU, Survey Optics & Operation – UDO Project Planning and Tracking - AFA Procurement Manufacturing Assembly Test Ready for Installation OK R. Folch EN/STI 10.08.11 R. Folch EN/STI - BID Workpackage Review - March 2012
Proposed strategy • The 3D conceptual design of all the BIDs is done by the WP • Once the 3D design is approved, the detailed design (2D) can be done by • The mechanical designer in the WP (BDM) • The MA Design Office (surrounding elements) • A subcontractor • Once the detailed design (2D) is approved, the procurement of the raw materials and standards components can start, under the responsibility of the WP • Manufacturing of the components: 2 options • By EN/MME (possibly subcontracted) • By a subcontractor according to the MA procurement procedure • Metrology of the mechanical components: by EN/MME • Assembly of the BIDs: EN/STI mechanical workshop • Final test at CERN: procedure and tooling to be discussed R. Folch EN/STI - BID Workpackage Review - March 2012
Support from EN/MME • The support expected from EN/MME has been roughly estimated to • 12 p.m of mechanical components, involving machining, welding, and sheet metal forming • 6 p.mof metrology This shall be refined based on the manufacturing strategy and the according tothe detailed design (2D) • In parallel, ad-hoc technical meetings are held with EN/MME experts to optimize the feasibility and the tolerances of the components R. Folch EN/STI - BID Workpackage Review - March 2012
Manufacturing plan R. Folch EN/STI - BID Workpackage Review - March 2012
Many thanks to… The Harley Chopper Dump You (attendees) Speakers: M. Delonca, M. Fürtinger, A. Christov Contributors: K. Asvestas, O. Aberle, D. Grenier, C. Maglioni, A. Masi, J. Lendaro, C. Mitifiot, V. Vlachoudis, M. Calviani, G. Jean, M. Benedikt, A. Fabich, U. Dorda, H. Pavetits, J. Gutleber, P. Trilhe, W. Rupprecht, T. Hauser, A. Maillot, S. Bailly, P. Landrot, JP. Brachet, A. Cherif, M. Polini, S. Pelletier, E. Feldbaumer, F. Osmic, M. Repovz, G. Hulla,… + all those I forgot to mention! R. Folch EN/STI - BID Workpackage Review - March 2012