140 likes | 267 Views
Golden Triangle Blvd. Progress Report. March 27, 2007. Funding. City ……………… $7.3 Million County…………… $7.3 Million Federal…………… $11.0 Million $25.6 Million . Current. 2004. 2007. Proposed Urban Design Median/Left Turn Lanes Curb & Gutter Sidewalks Drainage Improvement
E N D
Golden Triangle Blvd.Progress Report March 27, 2007
Funding • City ……………… $7.3 Million • County…………… $7.3 Million • Federal…………… $11.0 Million $25.6 Million
2004 2007
Proposed Urban Design Median/Left Turn Lanes Curb & Gutter Sidewalks Drainage Improvement $18.3 Million 50+ Year (permanent fix) Alternative Rural Road Barrow Ditches Federal Strings (6-8 months) 5-10 Year (Band-Aid) Re-prioritization +-
Current Maintenance/Improvements • Constructing Beach St. at Alta Vista • Left Turn Lanes • Re-timing Traffic Signals • Major Surface Repair (500 tons) • Re-stripe Roadway • Drainage west of SH 377 • Keller-Hicks at Alta Vista
http//www.fortworthgov.org/tpw Project Status Link
$7.3M PLAN Rehabilitate Existing Roadway(Approx. Life 5 Years) Two New Lanes (Approx. Life 10 Years) Ditch Ditch Ditch
$25.6M PLAN • 4-Lane Divided Arterial with Curb and Gutter • Raised Median • Underground Drainage • Traffic Signals • Left & Right Turn Lanes
FEDERAL FUNDING REQUIREMENTS • Environmental Assessment • Coordination with multiple agencies • Public Involvement • TxDOT / FHWA Review and Approval Processes • 30%, 60%, 90%, 100% Reviews • Bridge Design Review in Austin • Plan Review in Austin (6 months)
CONCLUSION - Councilman Espino Is 8 months worth $18.3 million?