Migration Strategies. Presented by: University of Southern California University of Arizona VivanTech. From Legacy to KFS Wednesday, November 19th, 1:00 — 2:00pm. VivanTech Summary. Software Development and Consulting Services US company — HQ in San Diego, CA
E N D
Migration Strategies Presented by: University of Southern California University of Arizona VivanTech From Legacy to KFS Wednesday, November 19th, 1:00 — 2:00pm
VivanTech Summary Software Development and Consulting Services US company — HQ in San Diego, CA Onshore developers and project managers Offshore Development Center — India Core Strengths: Financial system development & migrations General Java programming Kuali Commercial Affiliate
Migration Strategy Project Planning and Scheduling Java development (new KFS 3.0 feature) Augmentation of the USC KFS team VivanTech’s KFS Work Project Planning & Scheduling Consultation
USC & UA Summary USCUA • Private; Research 1 • Statistics • 33K students • $430 M research • $1.8 B expenditures • Kuali Involvement • Kuali Financial — Spring ’07 • Founding partner • Kuali Student • Land Grant, Research I • Statistics • 35K students • $500 M research • 1.5 B expenditures • Kuali Involvement • Founding Partner • Kuali Financial • Kuali Research
Migration from … USCUA • 26-year old in-house developed financial system • Technology/PlatformInfobasic - Universe • Financial Record System (FRS) - Information Associates • Technology/PlatformMainframe – Cobol & IDMS
Gap Analysis USCUA 525 Functions Analyzed • 458 Meet Requirements • 23 Need Further Testing • 39 Minor KFS Modifications • 5 Extensive KFS modifications 200 Central Business Processes • ID’d for documentation & design • Reporting vs. System • 6 – 10 KFS mods • Extended attributes • 2 new eDocs
Feeder Systems USCUA 47 Modules / Systems • 84 Interfaces — • 12 Large effort - 1,200 hrs • 17 Medium effort - 350 hrs • 55 Small effort - 75 hrs • Estimated effort - 24,475 hrs 6-10 KFS Modules / Systems • 41 Interfaces - Inbound • 1 large effort (Payroll) • 7 medium effort • 26 small effort • 7 to be absorbed • Estimated effort – 2500 hrs
Skill Sets USCUA Team Size at Peak: 88 Details — • 57 technical • 14 management - pm - lead • 17 non-technical Team Size at Peak: 30 • Details — • 10 technical (including BI) • 4 management – pm - lead • 16 functional • 60 testers - supplemental
Budget USCUA Assumptions — • Freezing of existing systems • Staff augmentation • Project structuring & automation • Data migration • Interfaces • QA & Testing • Assumptions — • Freezing of existing systems • Vanilla implementation • Staff augmentation • Project management • Data migration
Conversion USCUA Phased Migration • Existing system is complex • Cannot freeze immediately • Many feeder systems • Team is implementing KFS • CAMS and KEW • Long-term objective: Kuali as standard development platform Light Switch Migration • Primarily paper processes • FRS data similar to KFS • FRS frozen • Sandbox proof of concept • 3 years Kuali Involvement
Schedule USCUA 900+ Activities in MS Project • Duration: 35 Months • Official kick-off: 01/ 2009 500+ Activities in MS Project • Duration: 12 months • Official kick-off: 10/22/2008
Community USCUA Community Involvement& Responsibilities • Kuali Financial Steering Committee • Numerous community forums, briefings and demonstrations • Functional work groups with multiple input/feedback channels Community Involvement & Responsibilities • Business process owners • Business process advisors • Testing team (60+) • Training Director • Communication Director
Summary Limited Experience = Get Help • Limited Experience = Get Help Start Your Planning Activities Early • Start Your Planning Activities Early • Form a Kuali Planning Team Form a Kuali Planning Team • Get Your User Community Involved in Planning Activities Get Your User Community Involved in Planning Activities