An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. How to Build a School in CaliforniaManaging the State Agency Requirements Moderator: Kathleen Moore, Director School Facilities Planning Division California Department of Education Small School Districts’ Association 28th Annual Conference April 14, 2011, 9:45-10:45 AM

  2. California Department of Education School Facilities Planning Division Presenter: Kathleen Moore

  3. Agenda Summary • Role of the California Department of Education (CDE) • Overview of the CDE site and plan approval processes • Top 10 Tips for getting your Projects Approved • Resources

  4. Role of the CDE • California Education Code Section 17251 • CDE to develop standards for school sites and plans to ensure educational appropriateness and promote school safety • Upon LEA request, CDE reviews proposed school sites and plans • Standards in California Code of Regulations (CCR), Title 5 • Advisory and Best Practices

  5. Role of the CDE (cont.) • All public school sites and plans, regardless of funding source, must meet Title 5 standards: • Section 14010, site standards • Section 14030, plan standards • Sections 14011 and 14032, state funded procedures • Sections 14012 and 14033, locally funded procedures • If state funds are to be requested, CDE approval is required (Education Code Section 17070.50)

  6. SFPD – Who are we? • Director - Kathleen Moore • Supervising Field Representative - Fred Yeager • Education Administrator - Kathleen Seabourne (policy) • Staff Manager – Diane Works (supervises Analysts) • Senior Architect – Diane Waters • 12 Field Representatives - (Geographic and topical assignments, 8 based in Sacramento Office) • Office of School Transportation

  7. Vision and Guiding Principles The California Department of Education envisions school facilities that enhance the achievement of all students and are learner-centered, safe, sustainable, and centers of community.

  8. Vision and Guiding Principles The siting and design of educational facilities will: • Reflect the Local Educational Agency’s board-adopted facilities master plan and educational specifications. • Result from an open, community-based, and comprehensive planning process including all stakeholders and early dialogue with all involved planning agencies.

  9. Vision and Guiding Principles • Accommodate a complete facility supporting the delivery of the adopted educational program, be accessible to all, and adaptable to future demographic, educational, and community needs. • Support students, parents, teachers and staff in closing achievement gaps, and preparing students for the workforce, post-secondary education, and lifelong learning.

  10. Vision and Guiding Principles • Consider the full spectrum of community facilities and support opportunities for joint-use and educational partnerships. • Ensure safety from existing and potential hazards and incompatible land uses. • Provide a secure environment with a focus on supervision.

  11. Vision and Guiding Principles • Create comfortable, attractive, and stimulating environments that support collaboration and diverse learning styles and opportunities. • Promote sustainable practices that conserve natural resources, limit greenhouse gas emissions, optimize construction and life cycle costs, and encourage walking and bicycling.

  12. Vision and Guiding Principles • Incorporate superior acoustics, indoor-air quality, and natural lighting. • Respond to current and future information, communication, and technology needs. • Support student health, nutrition, and physical fitness

  13. FACILITY MASTER PLAN Local Educational Agency (LEA) evaluates short and long term facility needs OPSC SUBMITTAL LEA submits CDE site & plan approval letters as part of their Office of Public School Construction (OPSC) funding application POTENTIAL SITES LEA identifies and evaluates potential sites CDE SITE APPROVAL LEA submits site package, Analyst reviews, Field Rep. and Asst. Dir. approves if Code & Title 5standards and procedures are met CDE EVALUATION CDE evaluates/ranks three or more of the potential sites identified by the LEA, and notes any required special studies per Title 5 (SFPD 4.0) PREFERRED SITE LEA selects preferred site and prepares CDE required documents, completes procedures per Codes and Title 5, including CEQA & DTSC (SFPD 4.01) Site Approval Process Overview

  14. EDUCATIONAL SPECIFICATIONS LEA develops/adopts Educational Specifications DEVELOPING THE PLANS LEA develops and submits preliminary plans to CDE (design development with SFPD form 4.07 / 4.08) OPSC SUBMITTAL LEA submits CDE plan approval letter as part of their OPSC funding application CDE PRELIMINARY PLAN REVIEW Analyst reviews plans per Title 5, Field Rep. may require or recommend changes. LEA resolves CDE concerns, makes plan changes CDE FINAL PLAN APPROVAL LEA submits final plans, Field Rep. & Asst. Dir. approves if Code & Title 5 standards are met, and CEQA & DTSC (if applicable) are Complete Plan Approval Process Overview

  15. CDE Top 10 Tips • Develop and Use Educational Specifications • Links function / educational program to design • Required by Title 5 • Involve all stakeholders in development • Teachers • Classified • Parents • Community • Students • Board-adopted • Consider new trends / post-occupancy evaluation

  16. CDE Top 10 Tips • Develop / Update a Facilities Master Plan • Recommend 5+ year timeframe, update at least every 3-5 years • CDE reviews Master Plan with site approval package to justify site size acquisition, master plan capacity • Identify need to acquire land, build or consolidate • Where to build • What to build • What to modernize • Budget estimates • Funding sources

  17. CDE Top 10 Tips • Ensure that LEA staff, your architects and consultants understand and use CCR Title 5, e.g.: • Minimum classroom sizes • Parking lot, drop-off, bus separations/safety • Mitigations noted in site approval, such as: power line setbacks, pipeline mitigations, demonstration of adequate physical education on smaller sites • Know how to request & document standard exemptions

  18. CDE Top 10 Tips • Use most current forms/guidance from CDE Web • Latest requirements and certifications on forms • Small school site policy / maximum student density • Physical education – guidance for smaller sites • Guidance for power lines, pipelines, etc.

  19. CDE Top 10 Tips • Early and frequent contact with CDE Field Representative • Review of requirements, processes • New laws, regulations, policies, recommended guidance • Scheduling of review times • Consider attending County Office of Ed. Facilities Planners Meetings

  20. CDE Top 10 Tips • Plan sites for future growth (acreage, access, supervision, interaction, support for expand capacity) Support and other facilities such as: • Additional toilets • Cafeteria/outdoor seating, satellite food services • Lockers • Physical education teaching stations • New construction / relocatable classrooms • Special Education • District and County Office of Education • Parking and other interaction on campus • Preschool / day care • Joint-Use

  21. CDE Top 10 Tips • Understand the role / timelines of CDE, City/County and any other approval agencies • Are there any other agency approvals or overrides needed? (e.g.,Coastal Commission, Regional Planning Agency, Army Corp of Engineers, Airport Land Use Commission, Dept. of Conservation-Williamson Act Contracts, Air Quality Mgmt. Dist, CalTrans-Airports, Cities/Counties, etc.) • Need for utility and road access, connections • Off-site improvements, mitigations • Grading / drainage permits • New air impact assessment fee / indirect source review

  22. CDE Top 10 Tips • Ensure your documents / studies are consistentinternally and with each other same location, acreage, project scope, master plan capacity,conclusions / findings in all submitted to CDE, such as: • California Environment Quality Act (CEQA) – EIRs, Neg. Decs. • Department of Toxic Substances Control (DTSC) – Phase I • Geohazards Reports • Safety Studies (pipelines, powerlines, railroads, etc.) • CDE forms (SFPD 4.0, 4.02) • Legal description and matching maps

  23. CDE Top 10 Tips • Clear Definition of Project Scope Upfront • What level of CEQA analysis is needed? • Is DTSC approval needed? If so, be prepared for Phase 1 Environmental Site Assessment, Preliminary Endangerment Assessment, or Removal Actions, etc. • Other safety studies as required / noted on the SFPD 4.0 Initial Site Evaluation • All joint use acreage included/covered by reports?

  24. CDE Top 10 Tips • Submit Preliminary Plans to CDE • Schematic/Design development docs. (20-50%) • Saves time for CDE final plan approval • Saves money (fewer unexpected changes later) • Better final product • Insist your design professional submit early (before DSA submittal) • Respond to preliminary plan required changes and comments in final plan approval request

  25. CDE Top 10 Tips Bonus tips: • Be aware of funding deadlines, don’t wait and file at the last minute • Read consultant / architect prepared forms/reports before submitting to CDE • Submit drawings / plans that are readable and call out uses, dimensions, safety equipment etc. • Submit only complete packages with forms completely filled out • Use the Env. Hazards Checklist form for site packages, consider electronic/interactive disk submittal

  26. Sample CDE Web Site Resources • CaliforniaCode of Regulations, Title 5 • Hazard evaluation guidance (pipelines, power lines, etc.) • Project application forms • Staff and County assignments • Physical Education Planning Guidelines • Small School Site Guidelines • Advisories / Memos / Reports / Presentations • Guidance / Best Practices Publications (e.g., School Site Selection & Approval, School Site Analysis and Development, Educational Specifications, Healthy Children Ready to Learn) • What’s new , list serve

  27. Other Agency Resources • Collaborative for High Performance Schools (CHPS) http://www.chps.net/ • The Council for Educational Facility Planners International (CEFPI) http:/www.cefpi.org/ • National Clearinghouse for Educational Facilities http://www.edfacilities.org/

  28. CDE Contact Information California Department of Education School Facilities Planning Division 1430 N Street, Suite 1201 Sacramento, CA 95814 (916) 322-2470 http://www.cde.ca.gov/ls/fa/

  29. Division of the StateArchitect “The Building Department for Public Schools” Presenter: Howard “Chip” Smith

  30. DSA Organization DSA Headquarters located in Sacramento Four DSA Regional Offices Oakland Sacramento Los Angeles San Diego

  31. Sacramento Regional Office DSA HEADQUARTERS San Francisco Basin REGIONAL OFFICE Los Angeles Basin REGIONAL OFFICE San Diego REGIONAL OFFICE

  32. DSA Organization DSA Headquarters Code Development Statewide programs: inspector certification & training, laboratory approvals (LEA) Interpretations of Regulations (IRs), Bulletins, Policies, Procedures DSA Academy (learning resource for staff/clients) DSA Advisory Board and Committees

  33. DSA Organization DSA Regional Offices Project plan review and approval Construction oversight Project inspector approval Project close-out & certification TIP – know the DSA contacts for your project:- Intake Architect- Supervisors- Regional Manager

  34. Scope of DSA’s Review DSA reviews design for compliance with building regulations: Structural Safety (SS) Fire and Life Safety (FLS) Accessibility (AC) High Performance Incentive (HPI) Construction documents must show ALL work (electrical, mechanical, plumbing, site)

  35. Projects for which DSA Review is Required New school buildings Alterations to existing school buildings if project cost exceeds $36,908 (IR A-10) Site replacement of relocatable classrooms Reconstruction – the repair of damage to an existing certified school building such as fire damage Rehabilitation – comprehensive evaluation and retrofit of an existing non-conforming building Miscellaneous structures & facilities (ex.: light poles, scoreboards)

  36. DSA Review is Not Required for: Off-campus administrative buildings Maintenance projects – reroof and repair – Title 24, Part 1, Section 4-314 Alteration projects, if estimated construction cost of less than $36,908 (refer to IR A-10) Questions ? Contact your Regional Office

  37. Applicable Laws and Regulations Statutes Education Code Section 17280 (Field Act – K-12) Education Code Section 81130 (Field Act – Community College) Government Code Sections 14963 & 14964 (FLS) Government Code Section 4450 (Accessibility) Regulations – Title 24, Parts 1 – 12: Part 1 – Administrative Part 2 – Building Code Parts 3, 4, 5, 6, 9, 11 – Electrical, Mechanical, Plumbing, Energy, Fire Codes and Green Codes

  38. Project Development Tips Prior to design, conduct adequate surveys for accessibility, fire-safety and structural aspects of existing facilities Preliminary meeting with DSA recommended for large or complex projects:- Project scheduling constraints & funding deadlines- Verify deferred approval items (e.g. fire sprinkler design)

  39. 1: Submitting Plans to DSA Complete plans and specifications: 3 sets (4 if requesting HPI review); use Form DSA-3, Project Submittal Checklist Geological Hazards Report and Soils Report, if required (refer to IR A-4) Site drawing signed by local fire authority approving fire access, gates, fire flow, and hydrants Site plan to show “Path of Travel” for site and building accessibility

  40. 1: Submitting Plans to DSA (cont.) • Energy compliance documentation • 2008 Energy Code Compliance Checklist (DSA-403) • DSA Application Form (DSA-1) • Project tracking (PTN) number • Testing and Inspection Form (DSA-103) • Fees - based on estimated construction cost • Structural calculations

  41. 2: Plan Review Plans reviewed by next available plan reviewer (for each of four disciplines) Plans reviewed in order received (exception - “shovel ready” project prioritization) Four concurrent reviews are conducted: Structural – structural engineer Fire and Life Safety – fire and life-safety officer Accessibility – access compliance review HPI – High Performance Incentive review

  42. 3: Reviewed Plans Returned to Architect Each of four “check sets” (SS, FLS, AC, HPI) returned to Architect when completed DSA Web site “TRACKER” also indicates status of each review (SS, FLS, AC, HPI)

  43. 4: “Back check” and Approval of Plans Architect schedules “back check” appointment at DSA (SS, FLS, AC, HPI) Architect and consultants bring amended tracings and check sets to back check Architect and consultants must provide experienced staff at the back check

  44. Approval of Plans and Specs DSA staff review tracings and three check sets with the architect and engineers When back check is done, SS, FLS, AC initial and date DSA Identification Stamp

  45. Approval of Plans and Specs:DSA Approval Letter DSA scans all stamped drawings and specifications, and then returns documents- DSA Policy 06-01 Approval Letter is issued via emailDSA Bulletin 06-02 Construction contract may be awarded upon approval (DSA Approval Letter)

  46. Construction Oversight & Certification • DSA Certified Project Inspectors • Design Professional • DSA Field Staff • Contractors • Testing Labs

  47. DSA Web Sitehttp://www.dsa.dgs.ca.gov Project Status – “TRACKER” Project Submittal / Plan Review Process DSA Publications and Forms DSA Inspector and Lab Programs Contact Information for HQ and Regional Offices

  48. Office of Public School Construction “Tips for Receiving State Funding” Presenters: Lisa Silverman Brian LaPask

  49. Tips for Active Apportionments • Keep your $$ • Be aware of your Time Limit on Fund Release (TLOFR)