200 likes | 285 Views
US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab FNAL Oversight Panel October 24, 2000. CMS planning at LHCC review October 2000. US CMS S&C schedule adapted to LHC. Constraints for updated S&C schedule: Working CMS detector by mid-2005
E N D
US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab FNAL Oversight Panel October 24, 2000 Milestones, Funding of USCMS S&C Matthias Kasemann
CMS planning at LHCC review October 2000 Milestones, Funding of USCMS S&C Matthias Kasemann
US CMS S&C schedule adapted to LHC • Constraints for updated S&C schedule: • Working CMS detector by mid-2005 • LHC pilot run in Fall 2005, few weeks of luminosity running • Complete detector and start LHC running in Spring 2006 • Lessons learned from other experiments: • Pilot running: for detector as well as for computing and analysis Fall 2005 • Finish facilities before physics data early FY06 • CMS Software schedule not changed • Adapt schedule: delay start of implementation of facilities by 12 months (03->04) • 9 month delay in startup of LHC luminosity running • 3 month: US FY05 ends in 9/2005 Milestones, Funding of USCMS S&C Matthias Kasemann
US CMS S&C funding profile • Received draft funding profile from DOE: 5/30/2000 • Assume NSF funding profile after discussion • This is a BIG step for S&C projects: • guidance to allow detailed and solid planning • We want to continue to work with funding agencies to make S&C for CMS a success • profit for science from investment into LHC program Milestones, Funding of USCMS S&C Matthias Kasemann
CAS Project: Scope + Funding • US CMS CAS personnel contributions to CMS Core software: • determined by canonical scaling from CMS top-level resource-loaded WBS for Software • Add ~25% for additional US-specific software support • Proposal for CAS personnel contingency: • add a fixed percentage to base cost as management reserve e.g. • 10% for FY 2001 and 2002 • 25% for FY 2003 and beyond • All this is unchanged due to the updated schedule. Milestones, Funding of USCMS S&C Matthias Kasemann
US CMS S&C profile: January 00 version now USCMS S&C expected: 40%-25% of UF people contribution from FNAL, not shown here Milestones, Funding of USCMS S&C Matthias Kasemann
Schedule for US-CMS S&C Project • In order to match the proposed funding profile from DOE/NSF more closely as well as the LHC schedule, we have stretched out the CMS Software and Computing Project Schedule. • User facilities: • Now – end FY2003: R&D phase • FY2004-FY2006: Implementation Phase • FY2007 and onwards: Operations Phase • This required a new hardware cost estimate and resource loaded WBS. Milestones, Funding of USCMS S&C Matthias Kasemann
UF: Updated schedule • Modified: • Stretch hardware installation on UF and Tier2 • Reevaluate UF facility manpower needs • Very similar results • Tier 1 and Tier 2 center scope are: • proposed by MONARC, • defined by CMS Computing Model • Reviewed by CERN Hoffmann Review • Hardware requirements need to remain flexible to respond to • advances in technology • in storage: capacity, cost, => disk vs. tape, store vs. recalculate • in networking: bandwidth, latency, => local vs. remote data storage and access, replication • in computing: speed, cost, => servers vs. commodity type computing • results of review and planning process at CERN • results of Grid R&D, availability of integrated ‘middleware’ software • => Serious planning requires contingency here! Milestones, Funding of USCMS S&C Matthias Kasemann
Hardware Costing For UF w/o T2 Hardware costing for User Facilities, excluding Tier 2 Milestones, Funding of USCMS S&C Matthias Kasemann
Hardware Costing For UF Hardware costing for User Facilities, INCLUDING Tier 2 from GriPhyN Milestones, Funding of USCMS S&C Matthias Kasemann
User Facility Personnel Costs Milestones, Funding of USCMS S&C Matthias Kasemann
Total User Facility Costs Milestones, Funding of USCMS S&C Matthias Kasemann
Total S&C Project cost Management reserve: 10% on manpower Milestones, Funding of USCMS S&C Matthias Kasemann
DOE funding vs. UF(Tier 1) + 2/3 CAS Management reserve: 10% on manpower Milestones, Funding of USCMS S&C Matthias Kasemann
From “Bottoms Up” Approach 2001 2002 2003 2004 2005 2006 2007 • 1.1 Tier 1 Regional Center 13 17 20 18 • 1.2 System and User Support 1.3 2.25 3 3 5 4.5 4.5 • 1.3 Operations and Infrastructure 1 1.25 1.25 3 5 4.5 4.5 • 1.4 Tier 2 RCs 2.5 3.5 4 5 6.5 7.5 7.5 • 1.5 Networking 0.5 1 2 2.5 3 3 3 • 1.6 Computing and Software R&D 3 4 4.5 1.4 0.6 0.6 0.6 • 1.7 Construction Phase2 2 2 0.25 Computing • 1.8 Support of FNAL0.4 1.4 1 2.6 2.25 2 2based Computing • User Facilities (total) 10 15 18 30 37 43 41 • (Without T2 Personnel) 7.5 11.5 14 25 30 36 34 • Full time staff working on User Facilities tasks: (technicians, support staff, computing professionals) Milestones, Funding of USCMS S&C Matthias Kasemann
NSF funding vs. UF(Tier 2) + 1/3 CAS • Tier 2 center cost: • start of Prototype centers spread over FY01-04 • final implementation stretched over 2-3 years (FY04-06) • dominated by potential networking cost Milestones, Funding of USCMS S&C Matthias Kasemann
Funding - Request Milestones, Funding of USCMS S&C Matthias Kasemann
Evaluation of Profiles • The US CMS S&C project is managed and coordinated by the L1 PM, who carries budget authority • Funding shared differently for the two subprojects: • Tier1 center funded by DOE • Tier2 centers expected to be funded by NSF • CAS traditionally funded 2/3 DOE + 1/3 NSF • NSF part: under-funded by ~$1M/year • Tier 2 center cost dominated by networking cost • Uncertainty in networking cost for Tier 2 sites • Site Networking connectivity must be argument in selection process • Leveraging from University sites must contribute to cost of Tier2 centers • DOE part: • Dominated by Tier 1 personnel cost • Leveraging from FNAL infrastructure? • Part of WBS 1.3: Operations & Infrastructure • Part of WBS 1.5: Networking: LAN, WAN, monitoring, security • Part of WBS 1.8: Desktop systems, Support, Remote Control Room Milestones, Funding of USCMS S&C Matthias Kasemann
Conclusion (1) • The project needs to have a project office with: • Two project engineers supporting the L1 PM • coordinating the activities at all levels • Overseeing purchases • Establishing MoU’s, SOW’s • Preparing for Reviews • Tracking budget • Tracking the project progress • Not yet added to the previous numbers • Need to have management reserve / contingency for manpower (10% proposed, shown in the graphs) • The back loaded funding profile creates big problems now, additional help needed. • It is essential that we keep flexibility to use funds where needed most; only in this way are we able to take advantage of matching funds. Milestones, Funding of USCMS S&C Matthias Kasemann
Summary • Profile recognizes needs for operating S&C • Profiles heavily back-loaded towards 2005 • Result: • Funding does not allow to finish R&D and implementation for 2006 • Very hard to reach milestones: • Deliverables for Core Application Software • Contributions of US share to • Mock Data Challenges, • production exercises for trigger and physics studies • Test beam analyses for detector optimization • Preliminary analysis: implementation ready by 2007 • Severe impact for US based CMS data analysis: • Will not be able to fully contribute to CMS analysis • Will compromise readiness of CMS and US CMS for Physics • Disadvantage can only slowly be corrected because of operational needs Milestones, Funding of USCMS S&C Matthias Kasemann