1 / 10

Status Report on 2007–2016 Long-Term Reliability Assessment

Status Report on 2007–2016 Long-Term Reliability Assessment. Mark Lauby August 16, 2007. 2007 LTRA Schedule. Drafting LTRA Open Meeting Goals: Increased Transparency Identify Enhancements Finalize Draft PC Review Board Approval Release. Ongoing August 16 August 31 Sept. 11-12

eliza
Download Presentation

Status Report on 2007–2016 Long-Term Reliability Assessment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status Report on 2007–2016 Long-Term Reliability Assessment Mark Lauby August 16, 2007

  2. 2007 LTRA Schedule • Drafting LTRA • Open Meeting • Goals: • Increased Transparency • Identify Enhancements • Finalize Draft • PC Review • Board Approval • Release • Ongoing • August 16 • August 31 • Sept. 11-12 • Mid-October • October 15

  3. 2007 LTRA Emerging Issues

  4. Key Observations ? ? Firm Commitments? ? ? ? ? Transmission? CapacityMargin Target Level ? Fuel Supply? ? Regulatory? ? ? Time

  5. General Observations • Difficulty evaluating resource adequacy, especially in organized markets • Reluctance to commit to long-term resource plans • Difficulty judging impact/effectiveness of renewables and demand-side programs • Dependence on gas still high; interruptible transportation contracts a big issue • More transmission projects announced, but concerns whether they will be built

  6. Specific Observations • Margins tight in: • New England • MRO-US • ERCOT • A significant increase in wind farms, • Only 1,800 MW in 2007-2016 peak generation • The remainder is considered energy-only • 11,621 MW of new nuclear power capacity: • ERCOT (6,176 MW) • FRCC (1,125 MW) • SERC (4,320MW) • WECC – RMPA • WECC – CA-MX • WECC – AZ-NM-SNV

  7. Key Observations • The U.S. DOE has identified two draft National Interest Electric Transmission Corridors (NIETC) • Some States have expressed objections • More Transmission Projects proposed (2007–2011) • Transmission/ancillary services to accommodate wind energy • Investments in Connecticut improving reliability

  8. Key Findings & Conclusions • Continued Dependency on Natural Gas in New England, Florida & California • Bulk Power System Expansion Plan Uncertainty makes Long-Term Reliability Assessment Opaque • Grid Investment Needed to Integrate Intermittent Resources • Regulatory Action impact Reliability Projects

  9. High-Level Scenarios Reliability Impacts of … • Significant penetration of wind energy • High integration of demand response • Natural gas unavailability due to supply or delivery limitations • Possible reductions in capacity as a result of emissions restrictions

  10. Questions and Suggestions • Any issues or concerns not being addressed? • Additional scenarios to be considered? • Other suggestions?

More Related