Fanning Outdoor Recreation Facility. Conceptual Plan Final report (draft) Presented by Stan Kochanoff & Tracey Tomlik. Stakeholders The Strait Regional School Board The NS Department of Health & Protection The Municipality of Guysborough Preliminary ‘shopping list’ 8km trail loop
E N D
Fanning Outdoor Recreation Facility Conceptual Plan Final report (draft) Presented by Stan Kochanoff & Tracey Tomlik
Stakeholders • The Strait Regional School Board • The NS Department of Health & Protection • The Municipality of Guysborough • Preliminary ‘shopping list’ • 8km trail loop • Campsites • Outdoor classroom & shelter • Low ropes initiative course • Bird Blind • Interpretive signage • Access route to Lake & Canoe launch area
Final Report • Conceptual Plan • Showing in plan view where design elements are located • Three Phased developmental approach • Organizing design elements into four separate projects • Cost Estimates • Presenting expected cost associated with each design element
Bird Observation • 8km Trail • Group Campsites • Tree-Go • Outdoor Classroom • Teaching Garden • Soccer Field • Walking Track • Green Gym • Access Road • Canoe Launch
Phase One • Establishing a Trail system • Two group campsites • Interpretive signage • Regulation Soccer Field • Access Road/ Turning circle & parking • Canoe launch site • Total Cost • $82,374 - 95,824
Establishing a Trail System • 8kms of trail • Yellow route (1km) • Blue route (2km) • Red route (5km) • 8kms of trail • $2,500/km • Total • $20,000
Group Campsites (2) • (1) family camping • Trail ($625) • Picnic tables (2@$150) • Fire pit (2@$100) • Waste bins (2@$125) • (2) Wilderness camping • Trail ($750) • Fire pit ($100) • Total • $ 2,225 1 2 1
Interpretive Signage • Wooden signs • Describing local ecology • Showing direction • Cost Estimate • 3 Large ($1,500) • 15 Small ($50 - 100) • Total • $5,250 - 6,000
Soccer Field (300 x 180ft) Extension $15 - 20,000 Bleachers ($4,800) Benches ($600) Nets ($5,300) Fencing (behind nets) $14,400 Total $32,900 - 45,100 Annual Maintenance Lime (20lb/1000sqft) $135 Fertilizer (10lbs/1000sqft) $259 Aeration $480 Total $874
Lake Access Road • Expanding the current path to 11ft wide • Cost Estimate • Excavating • $810 • Class A Gravel • $6,480 • Ditching • $4,500 • Total • $11,790
Turning point & temporary parking • 35ft Radius • 2@20x10 parking spots • Cost Estimate • Fill • $1,180 • Excavating • $295 • Class A Gravel • $2,360 • Total • $3,835
Canoe Launch Site • Clearing rocks to create a launching site • Constructing a dry dock • Cost Estimate • Lake dragging ($3,000) • Dock ($2,500-3,000) • Total • $ 5,500 - 6,000
Phase Two • Bird Observation • Outdoor classroom shelter • Teaching garden • Tree Plantings • Total Cost • $40,524 - $45,524
Bird Observation Tower • An offshoot of the yellow hiking trail • 0.3km ($750) • Observation platform • 256sqft footprint • $12 - 15,000 • Total • $ 12,750 - 15,750
Outdoor classroom • Shelter with no walls • 1,600sqft • Long table with benches • Location is flexible right now • Cost Estimate • Excavating ($90) • Class A gravel ($720) • Materials • $8 - 10,000 • Total • $8,810 - 10,810
Teaching garden (900sqft) • Food production • Wildlife habitat • Cost Estimate • Excavating ($50) • Soil ($200) • Compost ($250) • Gravel ($120) • Fence ($9,100) • Total • $9,720 * Excluding the cost of plant material
Tree Plantings • Soccer Field (10) • Playground (3) • Grassed slope (9) • Cost Estimate • 5ft Evergreen • $368 (8) • 60mm Deciduous • $450 (14) • Total • $9,244
Phase Three • Walking Track • Green Gym Outdoor Fitness Centre • Aerial Adventure Course (Tree-Go) • Total Cost • $74,235 - $84,235
Walking Track • Located on the perimeter of the soccer field • Walking & jogging for all ages • Cost Estimate • Excavation • $335 • Track base (67cuyd) • Crusher dust ($3,900) • Total • $4,235
Outdoor Gym system • Green Gym (5units) • Stations placed along walking track • One designated area • Total • $20,000
Aerial adventure course • Tree-Go unit • Demo Area • Kids Area • Main Course • >10” Trees or use poles • Total • $50,000 - 60,000
Phase 1 $82,374 - 95,824 Phase 2 $40,524 - 45,524 Phase 3 $74,325 - 84,325 Total Cost Estimate $197,223 - 225,583 Summary Presentation Final Plan (draft) Cost Estimate Public Feedback Questions or concerns Discussions
We Thank You for your Feedback