1 / 17

Availability Working Group: Accelerator Fault Tracker Status & Plans for 2017

This document provides an update on the status and plans of the LHC Availability Working Group's Accelerator Fault Tracker for the year 2017. It highlights the importance of availability as a key performance indicator and discusses the challenges faced by the group. The document also outlines the objectives and achievements of the Accelerator Fault Tracker tool and its integration with other data services at CERN.

elon
Download Presentation

Availability Working Group: Accelerator Fault Tracker Status & Plans for 2017

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Availability Working Group & Accelerator Fault Tracker Status & Plans 2017 B. Todd, L. Ponce, A. Apollonio, benjamin.todd@cern.ch v1

  2. Introduction • Availability is the only means to increase integrated luminosity once a machine is levelled. • LHC Availability Working Group (AWG) launched in 2012 • 2010-2012: objective view of availability not possible = weaknesses in data captured • 2012-2013: AWG proposed the Accelerator Fault Tracker to solve data issues • 2014: Accelerator Fault Tracker launched by BE/CO, BE/OP and TE/MPE • 2015: Accelerator Fault Tracker was extensivelyused for availability data analysis • 2016: Availability Working Group periodic reporting Started Where do we go from here?

  3. Availability Working Group integratedluminosity is the real Key Performance Indicator coherent & objective information capture is primary concern – biggest challenge of AWG

  4. Important Concepts from AWG Coherent & objective = viewpoint from both operations & equipment Operations & Equipment = “Hybrid Pareto” “Cardiogram” “Availability Matrix”

  5. Cardiogram = Operations Viewpoint KPI = inversefemtobarn • Increase physics performance in stablebeams • Increase stable beams duration • Decrease turnaround time • Decrease faulttime

  6. Availability Matrix = Equipment Viewpoint Typical KPI optimised by equipment groups = Mean Time Between Failures • Remove or mitigate the failure mode entirely • Make the failure lesslikely (increase reliability, …) • Make the failure have a lowerimpact (decrease repair time, decrease diagnostics time, …)

  7. Hybrid Pareto = Both Viewpoints operations unavailable time equipment fault time shadow / parallel faults, … • Combined Viewpoint: • equipment fault time longer than operational unavailability • equipment fault time shorter than operational unavailability • equipment fault time zero pre-cycles, … beam events, operational errors, … Correlation of all of these is the only way to really see “availability” Equipment Group optimisation of MTBF does not mean LHC optimises inverse femtobarn

  8. 2010  2012 • Manual report creation • carried out once per year • Subjective approach • Opaque process • no correlation operations vs equipment • strategic conclusions impossible to make • lag data capture to report generation • ≈0.2 FTE data processing (3 x STAFF & DOCT) = proposal for the Accelerator Fault Tracker tool (AFT)

  9. Accelerator Fault Tracker LS1 = AFT launched as BE/CO, BE/OP and TE/MPE initiative Led by C. Roderick, proposed in three releases: • AFT 1.0 (2015-2016) • infrastructure to collect operations view-point data • produce cardiogram • structure foreseen to fold in equipment data • AFT 2.0 (2016-2017) • Capture data from equipment groups • Produce combined equipment and operations viewpoints • AFT 3.0 (2018+) • Connect to otherdataservices at CERN (INFOR EAM, IMPACT, LAYOUT) • fully integrated transverse view

  10. 2015 • direct eLogbook extraction • One-click cardiogram • Before AFT = 2 months to cardiogram 2010 data • few seconds to get it now • correlation operations vs equipment • operations viewpoint =weekly review • equipment viewpoint = annual review • objective view possible • no lag data capture to report generation • 0830 meetings using previous day’s cardiograms • transparent approach • ≈1.5 FTE tool (BE/CO) • ≈0.25 FTE tool feedback (AWG) • ≈0.5 FTE data entry (AWG) March  November 2015 – possibility for automation of parts of this feedback

  11. One-Click (ish)

  12. 2016 – Periodic Reporting Technical Stop report 1 x restart & ramp up 2 x proton physics production 1 x ion physics production Process: * draft at start of TS * AWG meeting to discuss duringTS * finalised and approved by AWG after meeting annualreport * compilation of previous reports…

  13. Reports So Far • create uniform means to see availability in the LHC context • propose template always followed • easy to complete • data from AFT statistics structure • AFT reproduce large parts of the report on-the-fly • simple to compile for annual report • create a permanentrecord of LHC availability • template ATS Note Restart – TS1: TS1 – TS2: TS2 – TS3: Proton Run: https://cds.cern.ch/record/2195706 https://cds.cern.ch/record/2235082 https://cds.cern.ch/record/2235079 https://cds.cern.ch/record/2237325

  14. 2017 [1/2] • AFT 1.0  AFT 2.0 • Numerous open issues & tickets with BE/CO – slow progress • Attempt equipment group information integration • Attempt integration for the TIOC • AWG and BE/CO already started work • Turnaround • Often discussed metric without coherent approach or analysis • Organisedata for this, make and publish analyses as part of reporting • Improve turnaround data and analysis • AFT & AWG in the Injectors • It is possible to propagate the AFT tool • Let’s make some first attempts. • We need to define some core members for injectors who take ownership … • Andrea + Verena et al. set things in motion • Help from others is vital….

  15. 2017 [2/2] • Day to Day • data validation and continuous improvement of the AFT remains a core aspect of the AWG • effort to maintain fault data increased x3 – used to be a part-time job… • dedicated resources are needed • Strategic View • information created for the LHC can be exploited for HL-LHC, FCC, … • newand existingmachines are being designed facing availability as a primary deliverable. • AFT information should be able to be used to create genericmodels • Modellingand strategic aspects are becoming more detailed and heavier to manage, with several parties involved. • The mandate of the AWG only covered the LHC. • centralised modelling & strategy elsewhere than AWG

  16. Thank you!Questions? 2012 – Availability Working Group Established

More Related