In Progress: PPL Center arena parking garage (yellow circle), January 2 16, 2014. January 2: First deck is in place. January 9: Second deck is in place and an exterior wall is added. January 9: Thin brick veneer finishes are applied in the factory. January 9: An interior wall is placed.
E N D
In Progress: PPL Center arena parking garage (yellow circle), January 216, 2014.
January 9: Second deck is in place and an exterior wall is added.
January 9: Thin brick veneer finishes are applied in the factory.
January 13: Third deck is added; exterior walls and spandrels visible.