An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CERC Terms & Conditions of Tariff 2009-14 System Operators’ Course

  2. Background • Till March 2001, Tariff of ISGS was fixed by GoI through a notification. • First Tariff regulations issued by CERC on 31-03-01 for the control period April’2001-March’2004 • Tariff regulations for April2004-March 2009 issued in March 2004 • Tariff regulations for April2009-March 2014 issued in Jan 2009 Cost Plus Approach adopted in Tariff fixation

  3. What are Terms and Conditions of Tariff? • Rules for determining the Tariff of ISGS and Transmission licensees. • Applicable to • a) Generating Stations supplying to more than one beneficiary (Thermal, Hydro, CCGT) • (NTPC, NLC, NHPC, DVC, NEEPCO) • b) Inter State Transmission System • Tariff of Nuclear power stations is fixed by DAE.

  4. Some Imp Definitions and terminology • Control Period : Period for which tariff is specified (April 2009-March 2014) • MYT : Multi Year Tariff: The tariff spread over useful life of the equipment • Beneficiary : Person purchasing power from the ISGS • Cut off date :Last day of FY after 2 years from the CoD. • Date of Commercial Operation: date from which Tariff recovery starts • ‘Infirm power’ : Power injected before CoD. • ‘Inter-State generating station’ or ‘ISGS’ : Gen Stns supplying power to more than one state. • ‘Useful life’: Life of the system from CoD used for computing Depreciation and determination of Tariff norms. • ( Coal/Gas based/ Substation=25 yrs, Hydro/Line 35 yrs) • ‘Design energy' means the quantum of energy which can be generated in a 90% dependable year with 95% installed capacity of the hydro generating station;

  5. Steps in Tariff and Collection Audited Costs Apply for Tariff fixation (6 months before) Bench mark norms of Project Cost Tariff fixation CoD Accounting in REA Billing by the ISGS/ ISTS Cut off Date Audited Costs Audited Costs Filing of AddCap+ deferred Liabilities +actual Expenditure Truing up by CERC Beneficiaries Interest Rates Adjustment of Excess or Deficit collection For every Control period for existing Projects also Tariff fixation to be done

  6. High lights Regulation 39 Income from UI, Incentive & non-core business –Not a pass through Regulation 26 (ii)B Min Boiler efficiency, Max. Design unit Heat Rate etc. are defined for different type of boilers and coals defined for new Thermal Gen stations to discourage procurement of inefficient Boilers.

  7. Rs. Total Project Cost considered for Tariff fixation Project Exp. Asstets not in Use IDC Profit in Sale of Infirm power FERV Capital Cost Initial Spares Addl Cap Debt:Equity Ratio Rehab & Resettle (hydro) Equity Loan RGGYY (hydro)

  8. Components of Tariff Tariff Capacity Charges Energy Charges Primary Fuel Interest on Loan Maint. Spares Depreciation O&M expenses Normative Seconday Oil Cost Lime Stone (if applicable) Return on Equity R&M Allowence

  9. Computation of Capacity Charges Rate of RoE Equity Return Equity Rate of Interest Loan Interest on Loan Rate of Depreciation Loan +Equity Depreciation Type/Size of Unit/ / Tr. system O&M Exp Normative O&M Exp Normative % Spares Maint. spares O&M Exp Interest rates Working Capital Interest on Working Capital Sec. Oilrates Seondary Oil rate Sec Oil

  10. working Capital Computation Cost of 1.5* month primary fuel Stock * 2 months for non-pit head stns. O&M Exp Cost of 2 months Sec oil Stock Working Capital O&M Exp for 1 month Interest rates Cost of Maint. Spares (as a % of O&M ch.) Interest on Working Capital 2 months receivables

  11. Time Lines in Tariff Period Project schedule to determine addl. RoE Construction Period Control Period 5 Control Period 1 Control Period 2 Control Period 4 2-3 months Tariff after Renovation and Modernisation 10-12 yrs 2-3 months 2+ years 2-4 years Eligibility for R&M Depreciation in straight Line method (12 years) 1st Trial synchronisation Drawl of Start up power (2-3 months) CoD Cut-Off Date for addl . Capitalisation Apply for True I Up of Tarriff Project Start date (2- 4 years) End of Loan repayment End of Useful Life

  12. Bench marking Model for Generating Stations Benchmarking by CERC Developed as per National Tariff policy, for facilitatting prudence checks in line with Clause 7(2) of the TCT regulations Fuel /Technology Green Field/ Exisitng Size of Unit No. of Units Evacuation Voltage Level • Bill of Quantities • Boiler Efficiency • Steam Generator • Turbine Generator Island • Turbine Heat Rate • Fuel Oil Handling & Storage system • Coal Handling System • Chimney • Ash Handling System • C & I Package • Civil Works • Cooling Tower • Switchyard Package • Initial Spares • Mode of Unloading Fuel Oil Fuel Linkage Plant Location (Pit Head/ Non Pit Head) Month/Year of Award Boiler Configuration Total Unit cost Distance of Water Source (River) Calorific Value Ash Content Moisture Content in Coal Indeces for Steel, Cement, Labour Generous set of assumptions Source: CERC Explanatory Memorandum ( 8th Dec.’09)

  13. Bench marking Model for Transmission lines Benchmarking by CERC Voltage class No. of circuits Conductor type No. of Conductors Insulator type • Bill of Quantities • Conductor length • Earthwire length • No. of insulators • Qty. of Hardware • Tower Weights • Foundation Volume Line length Wind zones & Terrain No. of Towers Types of Terrains No. of River crossings Total cost / Cost per ckm Unit cost based on historical data and Application of PV Formula and indices Generous set of assumptions Source: CERC Explanatory Memorandum ( 8th Dec.’09)

  14. Plant Availability Factor DCi = Average declared capacity (in ex-bus MW), N= No. of Days in the period IC = Installed Capacity Aux = Normative auxiliary energy consumption in percentage. For Thermal Plants, DCi is the Max Pk hour MW schedule given by RLDC For Hydro Plants DCi is the MW delivered for atleast 3 hours certified by RLDC

  15. Availability Calculation of Transmission System Availability = (100-100*NAFM) Where NAFM= Non-availability factor in per unit for the month 1) For AC system [ Σ ( OHL x CktkmL x NSCL ) + Σ ( OHT x MVA T x 2.5 ) +Σ ( OHR x MVAR R x 4 ) ] THM x [ Σ (Cktkml xNSCL ) + Σ (MVAT x 2.5 ) + Σ (MVARR x 4 ) ] Where OHL, OHT & OHR = Outage hours for Line or Transformer or Reactor Cktkm = Length of a transmission line circuit in km NSC = Number of sub-conductors per phase MVA = MVA rating of a transformer / ICT MVAR = MVAR rating of a bus reactor, THM = Total hours in the month 2) NAFM for each HVDC system NAFM = [ Σ (TCR x hours) ] ÷ [ THM x RC ] • TCR = Transmission capability reduction of the system in MW • RC = Rated capacity of the system in MW.

  16. Computation of monthly Capacity charges payable AFC = Annual fixed cost specified for the year, in Rupees. NAPAF = Normative annual plant availability factor in percentage NDM = Number of days in the month NDY = Number of days in the year PAFM = Plant availability factor achieved during the month, in percent: PAFY = Plant availability factor achieved during the year, in percent For Thermal Gen. Stns. less than ten (10) years old: Monthly capacity Charges = AFC x ( NDM / NDY ) x ( 0.5 + 0.5 x PAFM / NAPAF ) For Thermal Gen. Stns. Older than ten (10) years: Monthly capacity Charges = AFC x ( NDM / NDY ) x ( PAFM / NAPAF ) For Hydel Plants Monthly capacity Charges = AFC x 0.5 x NDM / NDY x ( PAFM / NAPAF ) For Transmission charges of ISTS : Monthly transmission Charges = AFC x ( NDM / NDY ) x ( TAFM / NATAF )

  17. Energy Charges Rate Aux = Normative auxiliary energy consumption in percentage. CVPF = Gross calorific value of primary fuel as fired, in kCal per unit CVSF = Calorific value of secondary fuel, in kCal per ml. ECR = Energy charge rate, in Rupees per kWh sent out. GHR = Gross station heat rate, in kCal per kWh. LC = Normative limestone consumption in kg per kWh. LPL = Weighted average landed price of limestone in Rupees per kg. LPPF = Weighted average landed price of primary fuel, in Rupees per unit SFC = Specific fuel oil consumption, in ml per kWh. For Coal based and Lignite fired stations ECR = { (GHR – SFC x CVSF) x LPPF / CVPF + LC x LPL } x 100 / (100 – Aux) For gas and Liquid fuel based stations ECR = GHR x LPPF x 100 / {CVPF x (100 – Aux) } For Hydel Plants ECR = AFC x 0.5 x 10 / { DE x ( 100 – Aux ) x ( 100 – FEHS )}

  18. Secondary Oil Regulation 20 • Secondary fuel charges de-linked from Energy Charges and put in Fixed charges • Sec Oil Exp.= SFC x LPSFi x NAPAF x 24 x NDY x IC x 10 • Secondary oil consumption halved to 1ml/u • Actual Expenses based on landed cost to be adjusted at the FY end. • Savings in Sec. oil consumption to be shared with Beneficiaries 50:50

  19. Depreciation Regulation 17 • Allowed up to maximum of 90% of the capital cost and salvage value is 10% • 5.28% for 1st 12 years Balance depreciable value spread over the balance useful life • IT eqpt.=15% ; PLCC=6.33 ; Motor vehicles=9.5% ; AC=9.5% • Bldgs= 3.34% • Land under lease=3.34% • Temp erections=100% • Advance Against Depreciation removed

  20. Sample Calculation of Tariff – CERC Norms 2009-14 Case Study : A Project Consisting 1 No. 400KV D/C Transmission Line of 75 km line length and 4 Nos of 400KV Bays. Capital Cost of the Project : Rs 100 Cr Adopting Debt : Equity Ratio of 70 : 30 Loan (Debt) Amount : Rs 70 Cr Equity Amount : Rs 30 Cr CALCULATION OF TARIFF for 2009-10 (For illustration purpose only) Interest on Loan : 70 x 0.095 = 6.65 Cr ( IOL @ 9.5%) Return on Equity : 30 x 0.17481 = 5.24 Cr (ROE @ 17.481% {15.5%/ 16% before MAT}) Depreciation : 100 x 0.0528 = 5.28 Cr (Depreciation @ 5.28% {Building : 3.34%, TL/SS : 5.28% , PLCC : 6.33 % and balance spread over after 12 Years}) O&M Expenses = 2.57 Cr 4 No * 52.40 Lakh/Bay (400KV) 75 Km * 0.627 Lakh/Km (400KV D/c Twin) Interest on Working Capital @ 12.25% = 0.41 Cr ( WC=2 Month Receivables + 1 Month O&M + 15% O&M for spares) TOTAL TARIFF = Rs. 20.15 Cr / year

  21. Will Tariff be paid after ‘Useful life’? • Yes. Tariff is receivable by the Owner • ‘Depreciation’ component will not be receivable • Eligible for Renovation and Moderation • Asset can be written off and new project can be constructed or R&M can be taken up • Allowance for R&M Rs.5Lac/MW/yr as Fixed Ch. • R&M as a separate project ‘useful life’ in relation to a unit of a generating station and transmission system from the COD shall mean the following, namely:- (a) Coal/Lignite based station :25 years (b) Gas/Liquid fuel based station :25 years (c) AC and DC sub-station: 25 years (d) Hydro generating station : 35 years (e) Transmission line : 35 years

  22. Some TCT clauses relevant to System Operation

  23. Commercial Declaration ‘Date of commercial operation’ or ‘COD’ means • in relation to a unit or block of the thermal generating station, the date declared by the generating company after demonstrating the maximum continuous rating (MCR) or the installed capacity (IC) through a successful trial run after notice to the beneficiaries, from 0000 hour of which scheduling process as per the Indian Electricity Grid Code (IEGC) is fully implemented, and in relation to thegenerating station as a whole, the date of commercial operation of the last unit or block of the generating station; (b) in relation to a unit of hydro generating station, the date declared by the generating company from 0000 hour of which, after notice to the beneficiaries, scheduling process in accordance with the Indian Electricity Grid Code is fully implemented, and in relation to the generating station as a whole, the date declared by the generating company after demonstrating peaking capability corresponding to installed capacity of the generating station through a successful trial run, after notice to the beneficiaries: hydro generating station with pondage : If insufficient reservoir or pond level -demonstrate peaking capability equivalent to installed capacity run-of-river hydro generating station - demonstrate peaking capability as and when sufficient inflow is available. c) element of the transmission system : first day of a calendar month

  24. Infirm power ‘Infirm power’ means electricity injected into the grid prior to the commercial operation of a unit or block of the generating station; 11. Sale of Infirm Power. Supply of infirm power shall be accounted as Unscheduled Interchange (UI) and paid for from the regional or State UI pool account at the applicable frequency-linked UI rate: Provided that any revenue earned by the generating company from sale of infirm power after accounting for the fuel expenses shall be applied for reduction in capital cost: Infirm Power can be Curtailed in case of Congestion

  25. Maintaining Fuel Stock 18 1(a) Coal-based/lignite-fired thermal generating stations (i) Cost of coal or lignite and limestone, if applicable, for 1½ months for pithead generating stations and two months for non-pit-head generating stations, for generation corresponding to the normative annual plant availability factor; Open-cycle Gas Turbine/Combined Cycle thermal generating stations Fuel cost for one monthcorresponding to the normative annual plant availability factor, duly taking into account mode of operation of the generating station on gas fuel and liquid fuel; Liquid fuel stock for ½ month corresponding to the normative annual plant availability factor, and in case of use of more than one liquid fuel, cost of main liquid fuel.

  26. Declared Capability in Fuel Shortage Conditions 21(4) In case of fuel shortage in a thermal generating station, the generating company may propose to deliver a higher MW during peak-load hours by saving fuel during off-peak hours. The concerned Load Despatch Centre may then specify a pragmatic day-ahead schedule for the generating station to optimally utilize its MW and energy capability, in consultation with the beneficiaries. DCi in such an event shall be taken to be equal to the maximum peak-hour expower plant MW schedule specified by the concerned Load Despatch Centre for that day.

  27. Declared Capability in Fuel Shortage Conditions Pk hours to be specified in RPC forum DC not to be revised during Pk hours DC can not be reduced Unless Unit trips If unit trips, maximum possible DC to be given in other units In such case max DC during pk hrs to be specified as DC for the day To Check Gaming by Generator DC can not be increased

  28. For Hydro Stations • DCi = Declared capacity (in ex-bus MW) for the ith day of the month which the station can deliver for at least three (3) hours, as certified by the nodal load dispatch centre after the day is over. • (8) The concerned Load Despatch Centre shall finalise the schedules for the hydro generating stations, in consultation with the beneficiaries, for optimal utilization of all the energy declared to be available, which shall be scheduled for all beneficiaries in proportion to their respective allocations in the generating station.

  29. Sharing of ISTS charges (1) Regional Tr. Ch of a Beneficiary =(Agreed Pooled Assets+ Associated Tr. System+ IR link) Total ISGS capacity X (Wt. Avg. Entitlement from all ISGS+LTA+ MTOA) (2) IR link sharing : SR-WR, NR-WR, ER-NER = 50:50 NR-ER by NR, SR-ER by SR, WR-ER by WR (3) ICT and Down Stream N/W charges by Respective Beneficiary (4) Unpooled ATS : by respective Beneficiaries

  30. Transmission charges in absence of a Beneficiary Regulation 33 (7) • A new clause is added with regard payment of Tr. Charges by the generator incase of non-identification of beneficiary for its capacity. • “Transmission charges corresponding to any plant capacity for which a beneficiary has not been identified and contracted shall be paid by the concerned generating company”.

  31. Effect of PoC Regualtions (Sharing of Inter state Transmission charges and losses) Salient features of PoC Regulations • Notified on 15.06.2010 and shall come into force from 01.01.2011 • Transmission charges for the Assets of POWERGRID shall continue to be determined by CERC • Existing methodology for Sharing of Transmission Charges is replaced (Regulation 33 of Terms & Conditions of Tariff, 2009 : Repealed ) • Sharing based on Point of Connection (PoC) Tariffs based on load flow analysis • PoC are identified against all the USERS of the ISTS network known as Designated ISTS Customers (DICs) Generating Stations SEBs/STUs Bulk consumer directly connected with ISTS Any designated entity representing aforementioned physically connected entity

  32. Proposed Changes in Fixed Charge Recovery For incentivising Peak Availability • Annual Fixed charge for the peak hours • Annual Fixed charge for the off-peak hours in (1): (2.4) ratio Different Norms for Fixed charges specified based on classification of • Peaking Stations • Other than Peaking Stations For Thermal, Hydro and CCGT • Norms for Pumped Storage Hydro Generating Stations introduced

  33. Tariff Policy 2006 • Provisions of “Tariff Policy” of Jan 2006 state: • “Even for the Public Sector Projects, tariff of all new generation and transmission projects should also be decided on the basis of competitive bidding after a period of five years or when Regulatory Commission is satisfied that the situation is ripe to introduce such competition.” • “Tariff of the projects to be developed by CTU/STU after the period of five years or when the Regulatory Commission is satisfied that the situation is right to introduce such competition would also be determined on the basis of Competitive Bidding.” Competitive Bidding in : • Power plant setup • Transmission system construction Empowered panel evaluates and awards

  34. Tariff Competitive Bidding • For Old projects, tariff will be continued to be fixed. • For New projects awarded under Competitive Bidding, Quoted Tariff as per final award will be used got payment of charges

  35. References : • Terms and Conditions for Renewable Energy • RLDC fee and Charges • Statement of Objects and Reasons for Terms and Conditions of Tariff regulations • Indian Electricity Grid Code 2010 • CERC order dt Benchmarking of Thermal projects • CERC order dt Benchmarking of Transmission projects • CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2009. • Tariff Notification for Generating Companies – Govt. of India