210 likes | 296 Views
ZANVAR ENGG. EXPORT PVT LTD. JAN 2012. TEAM MEMBER:-. Mr.PATIL NIVAS Mr. PATIL B.S Mr.LUGADE G.M. Mr.GAVALI A.R. Mr.GURAV N.B. COMPARATIVE PRODUCTION STATUS. PART NAME & NUMBER:- ALL 9 TYPE ESCORT BEARING CAPS. READY MATERIAL NOT LIFTED. ***. COMPARATIVE PRODUCTION STATUS.
E N D
ZANVAR ENGG. EXPORT PVT LTD. JAN 2012
TEAM MEMBER:- • Mr.PATIL NIVAS • Mr. PATIL B.S • Mr.LUGADE G.M. • Mr.GAVALI A.R. • Mr.GURAV N.B.
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- ALL 9 TYPE ESCORT BEARING CAPS READY MATERIAL NOT LIFTED ***
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- CONNECTING ROD BEML 10 Z 3100923 ***
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- (BEML) ROCKER ARM ***
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- TOWING HOOK ***
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- HITCH STABILIZER ***
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:-ALL TYPES Exhaust Manifold Export ***
COMPARATIVE PRODUCTION STATUS PART NAME & NUMBER:- 2 TYPE HOUSING 2500601&2500602
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- ALL 9 TYPE ESCORT BEARING CAPS M/c BEARING CHANGE Note:-
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- CONNECTING ROD BEML 10 Z 3100923 DISPATCH NOT LIFTED M/c BEARING CHANGE Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- (BEML) ROCKER ARM Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- ALL TYPES OF EX.MANIFOLD Note:- To calculate labor cost take 35% overhead on Basic+DA
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- 2 TYPES OF HOUSING Note:-
COST DETAILS(ITEMWISE) PART NAME & NUMBER:- HITCH STABILIZER & TOWING HOOK Note:- To calculate labor cost take 35% overhead on Basic+DA
REJECTION DETAILS(ITEMWISE IN %) Part Name:- ALL 9 TYPES ESCORT BEARING CAP CUSTOMER END REJ. 0 % ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- ALL 5 TYPES Exhaust Manifold Export ***ACTION ON MAJOR REJECTION CAUSES
REJECTION DETAILS(ITEMWISE IN %) Part Name:- 2 TYPE HOUSING 2500601&2500602 Ø267.746 UNDERSIZE ***ACTION ON MAJOR REJECTION CAUSES
OVERALL REJECTION (All Parts) ***ACTION ON MAJOR REJECTION CAUSES
LABOR EFFICIENCY LABOR EFFICIENCY= TOTAL SALRIES + OUTSIDE SUB.CONTRACTOR BILL TOTAL TURN OVER LABOR EFFICIENCY= 646550/1251398 LABOR EFFICIENCY= 0.51 REMARK:-EFFICIENCY :- 0.3 - OK MORE THAN 0.3 - IMPROVEMENT IS REQUIRED LESS THAN 0.3 - GOOD