Evian 2011. Technical Stops:. what were the issues in 2011, minimizing impact and improving recovery. Acknowledgments: S.Claudet , K.Dahlerup , F.Duval , K.Foraz , M.Nonis , M.Poyer , H.Thiesen , J.Uythoven , W.Venturini. M.Solfaroli. Outline. General view Methodology

Download Presentation

what were the issues in 2011, minimizing impact and improving recovery

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Evian 2011 Technical Stops: what were the issues in 2011, minimizing impact and improving recovery Acknowledgments:S.Claudet, K.Dahlerup, F.Duval, K.Foraz, M.Nonis, M.Poyer, H.Thiesen, J.Uythoven, W.Venturini • M.Solfaroli

  2. Outline General view Methodology The 5 TSs one by one Pulling the numbers together Conclusions M.Solfaroli - Technical Stops

  3. General Overview Time allocated for recovery: 1 day 23 % of global time = TUNNEL INTERVENTIONS (including Xmas break) M.Solfaroli - Technical Stops

  4. Methodology • GOALS: • Spot out possible correlations between recovery time and TS interventions • Identify major problems • Investigate strategies for improvement • HOW IT HAS BEEN DONE: • All TS interventions screened and all recovery issues examined • Some beam checks need to be done repetitively (i.e. loss maps)...should they be considered as part of recovery time? YES! • What does represent the limit between recovery and operation (back in SB, back on program, first beam in,...)? M.Solfaroli - Technical Stops

  5. TS#1 28 – 31 March – 4 days + 1 recovery day 3243 keys given • WHERE WERE WE? • Slot of 1.38 TeV operation • Last 3.5 TeV physics fill (1645): • 200 b (24 bpinj) - (ready for 296 b) • ~1.22E11 p per bunch • Peak lumi: 2.5E32 cm-2 s-1 10% 30% 60% GOAL of the week Recovery from TS and start preparation for high intensity M.Solfaroli - Technical Stops

  6. TS#1 - Recovery Start of HWC Global CRYO start Inj region aperture measurements for higher intensity First pilot Dump @450GeV MKB.B2 CRYO Recovery Beam comm TS t Thu 31st 6.25pm Fri 1st 10.29am Fri 1st 9.59pm Sat 2nd 01.23am Sat 2nd ~2pm Mon 28th 7am 10% 24% 66% M.Solfaroli - Technical Stops

  7. TS#2 09 - 12 May – 4 days + 1 recovery day 2831 keys given • WHERE WERE WE? • Last 3.5 TeV physics fill (1755): • 768 b (72 bpinj) • ~1.25E11 p per bunch • Peak lumi: 9E32cm-2 s-1 16% 24% 60% • GOAL of the week • TS, re-establish physics conditions, alignment of RPs, VdMs • Quench propagation test on RB.A56 • FPA on RQD/F.A67 M.Solfaroli - Technical Stops

  8. TS#2 - Recovery Start of HWC Global CRYO start Lost P8 (communication) First pilot Pilots cycle Preparation for VdM scan CRYO CRYO TS Beam comm Recovery t Thu 12th 2.10pm Thu 12th 6.31pm Fri 13th 08.42am Fri 13th 11am Sat 14th 2.10pm Sat 14th 9pm Sun 14th 9am Mon 9th 7am ~27 h 8% 54% 38% M.Solfaroli - Technical Stops

  9. TS#3 - The longest one 04 - 08 July – 5 days + 1 recovery day 3062 keys given • WHERE WERE WE? • Last 3.5 TeV physics fill (1901): • 1380 b (144 bpinj) • ~1.16 E11 p per bunch • Peak lumi: 1.26E33cm-2 s-1 9% 26% 65% • GOAL of the week • Continue with the satellite collision scheme • (264b and higher) • Quench propagation test on RB.A56 • Test of DQQBS boards in S81 M.Solfaroli - Technical Stops

  10. TS#3 – Recovery Start of HWC Global CRYO start Power cut First pilot End of loss maps Injection CRYO CRYO TS Beam Beam comm Recovery Recovery t Mon 04th 7am Fri 8th 7.19pm Sat 9th 8.05am Sat 9th 5.27pm Sun 10th 11.11am Mon 11th 7.22pm Tue 12th 3.15pm Thu 14th 7am 14.5% 14.5% 71% When the power cut arrived, beam commissioning was almost completed (a TCDQ-TCSG cross check was ongoing) M.Solfaroli - Technical Stops

  11. TS#4 29 August - 02 September – 5 days + 1 recovery day 3645 keys given • WHERE WERE WE? • Last 3.5 TeV physics fill (2040): • 1380 b (144 bpinj) • ~1.29E11 p per bunch • Peak lumi: 2.1E33cm-2 s-1 7% 24% 69% • GOAL of the week • TS, recovery from TS, 1 m beta*, Alice polarity change • Quench propagation test on RQD/F.A56 M.Solfaroli - Technical Stops

  12. TS#4 - Recovery ~3 h without beam from injectors Global CRYO start Start of fill that reached beta* 1m Start of HWC First pilot First pilots ramp CRYO Recovery Beamcomm TS t Mon 29th 7am Fri 2nd 2.10pm Fri 2nd 5.14pm Fri 2nd 10.33pm Sat 3rd 1.41am Sat 3rd 10.59am 7% 7% 86% M.Solfaroli - Technical Stops

  13. TS#5 07 - 11 November – 5 days + 1 recovery day 3404 keys given • WHERE WERE WE? • Last 3.5 TeV physics fill (2267): • 1380 b (144 bpinj) • ~1.5E11 p per bunch • Peak lumi: 3.5E33cm-2 s-1 6% 24% 70% GOAL of the week TS, recovery, ions (stable beams) over the weekend • Quench propagation test on RQD/F.A56 M.Solfaroli - Technical Stops

  14. TS#5 - Recovery Pb commissioning included Global CRYO start Start of HWC First pilot Asynch BD @ 450 GeV Physics conditions SB CRYO Recovery Beam comm TS t Fri 11th 4.58pm Fri 11th 5.48pm Sat 12th 00.13am Sat 12th 00.32am Sat 12th 02.31am Sat 12th 06.40am Mon 7th 7am 5% 6% 89% M.Solfaroli - Technical Stops

  15. Some numbers… Tunnel activities vs TSs M.Solfaroli - Technical Stops

  16. …more… Pretty low statistics to have meaningful conclusions... ...in general HW issues require more time to be fixed M.Solfaroli - Technical Stops

  17. …and more! X = number of days allocated Allocated time for recovery = 24 h Recovery coefficient Recovery time vs TSs M.Solfaroli - Technical Stops

  18. Client requests • Cryo: no systematic maintenance anymore, it would be OK with 4 (or even 3) TSs provideda minimum of 5 days each (this year was good!) • QPS: minimum of 3 stops (ideally in May, August and October). Minimum duration 4 ½ days as in 2011. • EPC: not particular systematic intervention needed, but at least 1-2 days every 9 – 10 weeks • EL: TSs needed to repair/reset/maintain some systems that are not in good shape. Nevertheless, till the machines work… • CV: global time already at the limit. It would be difficult to keep for more than 8-9 weeks • Experiments? (CMS: “we would be ready to go to 4/5d every 10 weeks if needed”) • Injectors? M.Solfaroli - Technical Stops

  19. Conclusions • Need to improve fault details recording • Most of activities is maintenance, can it be reduced? • No systematic source of trouble over the 5 TSs !! • It seems clear that we are improving in recovery… 2012 • (“After TS, an increment in faults was observed. Effect is decreasing along the run” Walter @Chamonix 2011) • Need to apply a control for SW changes (through a meeting to coordinate and create a list?) which could: • Improve changes, by coordinating them • Increase operational efficiency, by making easier the identification of the source of problems • Reduce impact of changes on other systems • 4 TSs foreseen for 2012...can we push forward some maintenance and have 3 TSs of 5 days? M.Solfaroli - Technical Stops

  20. Back-up slides M.Solfaroli - Technical Stops

  21. TS#1 – Issues 1/2 M.Solfaroli - Technical Stops

  22. TS#1 – Issues 2/2 M.Solfaroli - Technical Stops

  23. TS#2 – Issues 1/2 M.Solfaroli - Technical Stops

  24. TS#2 – Issues 2/2 M.Solfaroli - Technical Stops

  25. TS#3 – Issues 1/2 M.Solfaroli - Technical Stops

  26. TS#3 – Issues 2/2 M.Solfaroli - Technical Stops

  27. TS#4 - Issues M.Solfaroli - Technical Stops

  28. TS#5 - Issues M.Solfaroli - Technical Stops

  29. TS#3 - Recovery 2 h SB with 2 bunches done meanwhile Start of HWC Global CRYO start Power cut First pilot End of loss maps Injection CRYO CRYO Beam Beam comm Recovery Recovery TS t Mon 04th Fri 8th 7.19pm Sat 9th 8.05am Sat 9th 5.27pm Sun 10th 11.11am Mon 11th 7.22pm Tue 12th 3.15pm Thu 14th 7am 16% 45% 39% When the power cut arrived, beam commissioning was almost completed (a TCDQ-TCSG cross check was ongoing) M.Solfaroli - Technical Stops

  30. General Overview Smaller emittance Increased n. bunches Increased bunch intensity Beta* = 1m 50 ns 75 ns MD, technical stop MD, technical stop, SQUEEZE MD, technical stop, scrubbing MD, technical stop 28 % of global time = TUNNEL INTERVENTIONS M.Solfaroli - Technical Stops