Resource Asset Registration Form Version 5.0 / 5.1 Changes for WGRs
RARF Version 5.0 / 5.1 - WebEx • WebEx to discuss RARF Version 5.0 / 5.1 release • ERCOT will hold a WebEx on Thursday, July 12, 2012, from 14:00 to 16:00 CPT to help familiarize Resource Entities (REs) with the Resource Asset Registration Form (RARF) version 5.1Date: Thursday, July 12, 2012Time: 14:00 – 16:00 CPT (Chicago, GMT-05:00)WebEx URL: https://ercot.webex.com/ercot/j.php?ED=202253792&UID=0&PW=NNzgwYjhjZGU4&RT=MiM3 • Meeting Number: 655 194 994Meeting Password: Ercot123! • Dial-in Number: 1-877-668-4493 • Press # when prompted for pin number.
RARF Version 5 - two Phases • Phase I – March 21, 2012 – RARF Version 5.0 • Transposed the RARF form – resources are in rows • Phase I - Separated RARF into forms for Generation, Wind, Combined Cycle, Transmission, and Load Resources - separate forms to eventually allow partial submission (but not yet). • Added new fields (Business Rules for new fields were not active)
What Changed in RARF Version 5.0/5.1? • Phase II – June 26, 2012 – RARF Version 5.1 • Activated the business rules on new fields (non-binding until October 1, 2012.) • Added the AGR tab to the Gen_Form_Pivoted.xls for NPRR437 - Allow Aggregation of Multiple Generators Into A Single Resource For Market and Engineering Modeling • Separated out “General and Site Information”, “GEN Load Split - ESIID”, “Private Network – Site” tabs“ into General_Site_ESIID Information.xls”.
RARF Version 5.0 / 5.1 Phase Timing • Pre-populated, forms were sent to each Resource Entity on June 29, 2012. No immediate action is required. • RARF Version 5.1 validation rules on new fields became effective, but are non-binding until October 1, 2012. RARF Audit Reports reflect errors and warnings associated with all the new required data fields. • To the extent possible, existing RARF data was pre-populated (except PUN Load Data, One-Lines, Transformer Test Data, Stability Study Model, PSCAD Model, Dynamic Data, Collector System – WIND, Collector System-Wind Seg Data and new data fields that were completed in advance.) • REs are required to submit a completed RARF version 5.1 including all new data fields by October 1, 2012.
RARF Version 5.0/5.1 – Examples of New Fields – Wind_Form_Pivoted.xls Unit Info – Wind tab: • Non_Modeled Generator (Y or N) • Transmission Only Date (POI) [Optional, required for addition of the generation site transmission equipment on a earlier Network Operations Model MRD than the resource] • Standard Generation Interconnection Agreement (SGIA) Signature Date • Unit Start Date (Model Ready Date) [Optional, required for new resource to be added to the Network Operations Model] • POI – Sub-Station Code/Sub-Station Mnemonic • POI - Voltage Level • POI - PTI Bus Number • Governor Droop Setting • Governor Dead-band NATF
RARF Version 5.0/5.1 – Examples of New Fields – Wind_Form_Pivoted.xls Unit Info – Wind tab (continued): • Design Max Ambient Temperature • Design Min Ambient Temperature • Height of Meteorological Instrumentation - Wind Speed • Height of Meteorological Instrumentation - Wind Direction • Height of Meteorological Instrumentation - Barometric Pressure • Height of Meteorological Instrumentation – Temperature Ownership – Wind tab: • Ownership Start Date • Ownership Stop Date Parameters – Wind tab: • Unit De-rating Values (0 – 120 degrees F) NATF
RARF Version 5.0/5.1 – Examples of New Fields – Wind_Form_Pivoted.xls Reactive Capability – WIND tab (continued): • Reactive Capability Data Provided Below Is Gross Values? (Gross is required). • Reactive Capability Data Provided is from NDCRC Test Data? • If Reactive Capability Data Provided Is From NDCRC test Data Then Enter The Date On Which The Test Was Performed. Planning – Wind tab: • Positive Sequence Z (unsaturated) • Negative Sequence Z (unsaturated) • Zero Sequence Z (unsaturated) • Direct Axis Sub-transient Reactance, X"dv (saturated) • Direct Axis Transient Reactance, X'dv (saturated) • Zero Sequence Grounding Resistance For An Impedance Grounded Generator In P.U. (100 Mva Base) • Zero Sequence Grounding Reactance For An Impedance Grounded Generator In P.U. (100 Mva Base) NATF
RARF Version 5.0/5.1 – Examples of New Fields – Wind_Form_Pivoted.xls Planning – Wind tab (continued): • Average Amount Of Auxiliary Real Power (and characteristics) • Average Amount Of Auxiliary Reactive Power (and characteristics) • Auxiliary Load Power Factor • TURBINE STEP-UP TRANSFORMER DATA • High Side Voltage Level (nominal) • Low Side Voltage Level (nominal) • High Side Voltage Connection • Low Side Voltage Connection • Impedance Z • X/R Ratio • Zero Sequence Z • Zero Sequence X/R Ratio • Base Mva For Transformer Data NATF
RARF Version 5.0/5.1 – Examples of New Fields – Wind_Form_Pivoted.xls Collector System - WIND tab: • COLLECTION SYSTEM ONE LINE DIAGRAM (Embed a PDF One Line Diagram) • COLLECTION SYSTEM DETAILED MODEL (Embed a PSS/e Raw Data or Powerworld Model) • COLLECTION SYSTEM DETAILED MODEL • Cable Type • Voltage Level kV • POSITIVE SEQUENCE DATA • R/Kft • X/Kft • Charging Bc/Kft • ZERO SEQUENCE DATA • R0/Kft • X0/Kft NATF
RARF Version 5.0/5.1 – Examples of New Fields – Wind_Form_Pivoted.xls Collector System-Wind Seg Data tab: • Cable Type • WIND SEGMENT DETAILS • From • To • Circuit Number • Voltage Level • Cable Segment Length • Number of Turbines On Cable Segment Stability Study Model tab – embed any executable code models PSCAD Model (if applicable) tab Dynamic Data tab – embed any PDF diagrams, csv files and tabular data NATF
Questions QUESTIONS?