Flow Rate. 123. N 2. ~2x200L G.Catcher LS a day (Mixing and Filling) G.Catcher volume ~ 1400 L PPO, bis-MSB : x15 concent. GdR 3 : x10 concent. N 2. N 2. Mixing Tank. N 2 for purging. ( Ф 6). Inlet. ( Ф 12). Capacity : 200 L Material : P.E.

enrico
Download Presentation

123

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Flow Rate 123 N2 • ~2x200L G.Catcher LS a day • (Mixing and Filling) • G.Catcher volume ~ 1400 L • PPO, bis-MSB : x15 concent. • GdR3 : x10 concent. N2 N2

  2. Mixing Tank N2 for purging (Ф6) Inlet (Ф12) • Capacity : 200 L • Material : P.E. • N2 purging with Ф6 Teflon tubing (spiral shape) • Need 3 tanks for target, G.Catcher and Buffer. • All tubing for liquid transportation is Ф12 Teflon tubing. Outlet (Ф16)

  3. Flow Meters 유리관 면적식 유량계 + Ball Valve Accumulating Flow Meter Accumulating Flow Meter Measuring Accuracy : ±2% Accumulating Flow Meter Measuring Accuracy : ±0.5% Measuring Accuracy : ±3%

  4. Pump Magnet Pump with PP (Teflon pumps are too expensive. PP may be enough to be adapted to mockup.) We should use two types of pump according to flow rates. IWAKI magnet pumps are avaliable.

  5. Estimation

  6. Schedule It is possible to fill LS without Gd-loading to Target. (Gd can be loaded later.)