1 / 10

Plans and schedule for QXF

Plans and schedule for QXF. G. Ambrosio and P. Ferracin. 2nd Joint HiLumi LHC/LARP Annual Meeting 14-16 November, 2012 Frascati.

Download Presentation

Plans and schedule for QXF

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Plans and schedule for QXF G. Ambrosio and P. Ferracin 2nd Joint HiLumi LHC/LARP Annual Meeting 14-16 November, 2012 Frascati The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404 Work supported by the US LHC Accelerator Research Program (LARP) through US Department of Energy contracts DE-AC02-07CH11359, DE-AC02-98CH10886, DE-AC02-05CH11231, and DE-AC02-76SF00515

  2. SQXF plan and schedule G. Ambrosio and P. Ferracin • Cable dimension finalized by 03/13 • Coil design and parts • 13 months (11/12 – 12/13) • Coil tooling design and fabrication • 1 year (02/13 – 02/14) • CERN: 1 Wind&Curing + 2 React&impreg • LARP: 1 Wind&Curing + 2 React&impreg • Beginning of coil winding at CERN and LBNL in 02/14 • First long coil wound in 05/14 • Feed-backs from SQXF to LQXF on coil fabrication

  3. SQXF plan and schedule G. Ambrosio and P. Ferracin • Number of coils • CERN • 1 Cu coil • 1 practice + 5 real RRP coils • 1 practice + 5 real PIT coils • LARP • 2 practice + 5 real RRP coils • Coil fabrication time • 100 days (5 months) per coil, 1 coil produced every month • Sequence: CERN will start with RRP coils • SQXF1 magnet will include the first available four RRP coils produced by the two “production lines”

  4. SQXF plan and schedule G. Ambrosio and P. Ferracin • Support structure • LARP/CERN design of the same structure • 1 short structure fabricated and assembled at CERN • 1 long structure fabricated and assembled by LARP • From conceptual design to assembly and qualification • More than 2 years (11/12 – 02/15) • Tests • First test (SQXF1) at CERN • Cool-down starts in 06/15 • First assembly of LQXF in 06/15 • Feed-backs from SQXF to LQXF on loading • Then SQXF1b (RRP), SQXF2 (PIT), SQXF2b (PIT)

  5. SQXF plan and schedule G. Ambrosio and P. Ferracin

  6. SQXF plan and schedule and LQXF milestones Winding first LQXF coil LQXF1 assembly G. Ambrosio and P. Ferracin

  7. LQXF Plans G. Ambrosio and P. Ferracin • Coil and tooling design performed with SQXF • Same coil parts, same tooling design, same process • Coil fabrication starts after feedback from first SQXF practice coil(s) • One lab for LQXF practice coils • Coil test in mirror structure • LQ-team for LQXF production coils • LQXF01 assembly starts after feedback from SQXF01

  8. LQXF Schedule SQXF coil feedback SQXF01 test feedback Practice Coils Coil test in mirror LQXF01 coils LQXF01 test LQXF02 coils G. Ambrosio and P. Ferracin Mostly based on LQ and LHQ actual times

  9. LQXF Schedule with reassembly options LQXF01 LQXF01b LQXF02 LQXF02b G. Ambrosio and P. Ferracin Can be used for addressing issues and fine-tune assembly & pre-loading

  10. LARP-CERN QXF Video-meetings G. Ambrosio and P. Ferracin • Nov 27 • Strand design and procurement • Dec 4 • Update on cable R&D • Dec 11 • Thermal analysis • Radiation resistance • Dec 18 • Magnetic analysis • Jan 8 • Mechanical analysis • WAMSDO week • Quench protection

More Related