1 / 17

GRID+ Project : WP3 - MONITOR

GRID+ Project : WP3 - MONITOR. Progress Report December 2011. Bruxelles , December 2011. Outline. Summary Labeling – Deliverable D3.1 KPI – Deliverable D3.4 Finance – Deliverable D3.6. Bruxelles , October 2011. Summary of Milestones and Open Issues.

eris
Download Presentation

GRID+ Project : WP3 - MONITOR

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GRID+ Project : WP3 - MONITOR Progress Report December 2011 Bruxelles, December 2011

  2. Outline Summary Labeling – Deliverable D3.1 KPI – Deliverable D3.4 Finance – Deliverable D3.6 Bruxelles, October 2011

  3. SummaryofMilestones and Open Issues [Labeling] EEGI LabelingProcess and LabelingTemplatedefined and sent topartnersforreview [KPI] First contactbetweenT&DEurope and JRC performedforsharingofdeveloped KPI work. Explicittimelinefor KPI defined. [Finance] Technoficonfirmspreparationofrawdraft on financingschemestobepreparedby end ofJanuary 2012. [Labeling] RequireconfirmationfromEuropeanCommissionregardingExpertsperforming EEGI Labeling [Labeling] Define EEGI Labelingexperts [Labeling] Defineprojectsundergoing EEGI LabelingProcess [Labeling] Validate EEGI LabelingProcess and EEGI LabelingTemplate [KPI] ???? (T&DEuropetogive feedback on this) [Finance] ???? (Technofitogive feedback on this) ACCOMPLISHED MILESTONES OPEN ISSUES (requireURGENTresolution)

  4. SummaryLabelling, KPI, Finance Tasks URGENT ACTION required CAUTION OK

  5. Outline Summary Labeling – Deliverable D3.1 KPI – Deliverable D3.4 Finance – Deliverable D3.6 Bruxelles, October 2011

  6. WP3 Deliverables

  7. LabelingSubArea – Deliverable 3.1 New Timeline Oct-2011 Nov-2011 Dec-2011 Jan-2012 Feb-2012 Mar-2012 WP3 Labeling Tasks KEY T3.3 DEFINITION & VALIDATION Labeling Process and Labeling Template Project MilestoneMS302 • SubTask Completed • SubTask to be completed (urgently) • Define Process & Template T3.3.1 • DELAY (Tobecompletedbefore Christmas holidays) T3.3.2 SubTask to be completed (on schedule) Validate EVALUATIONproposal list of projects qualifying for EEGI Label T3.4 T3.4.1 (Tobecompletedbefore Christmas holidays) D3.1 T3.4.2 (Tobecompletedbefore Christmas holidays) • Select Projects for Labeling & Gather Information Define Experts • Perform Labeling Process T3.4.3 T3.4.4 • Get Missing Project Info T3.4.5 • Finalize Labeling Process T3.4.6 • Validate • Buffer

  8. LabelingSubArea – Deliverable 3.1 Yr1 DraftTimeline Oct-2011 Nov-2011 Dec-2011 Jan-2012 Feb-2012 Mar-2012 Sep-2011 Official D3.1 Milestones and Deliverables Dec 20 2011 (InternalDelay) Mar 15 2012 MS302 – EEGI Process and EEGiLabelingValidated D3.1 – First proposallistofprojectsthatqualifyfor EEGI Labelreadyforpresentationto EEGI Team Internal Meetings / Milestones Mar 15 2012 Oct 20 2011 Dec 20 2011 • WP3 Update Meeting • -ApproveLabelingProcess & Template • DefineProjectsforlabeling • Defineexperts WP3 Kick-off Meeting Management Boardapprovalofproposallistthatqualifyfor EEGI Label

  9. Outline Summary Labeling – Deliverable D3.1 KPI – Deliverable D3.4 Finance – Deliverable D3.6 Bruxelles, October 2011

  10. WP3 Deliverables

  11. KPI SubArea – Year 1 activities (initialTimeline) Oct-2011 Dec 2011 Feb 2012 Apr 2012 Jun 2012 Aug 2012 Oct 2012 WP3 KPI Tasks ASSESSMENT existing KPIs T3.1 Analyze existing work JRC within framework EEGI T3.1a Research & Map other relevant existing KPIs relevant to EEGI Objectives Mar 30 2013 T3.1b D3.4 – EEGI Project & ProgramAssessment Report based on definedKPIs T3.1c Select Project MilestoneMS301 DEFINITION EEGI Program / ProjectKPIs T3.2 EVALUATION T3.5

  12. KPI SubArea – MS301 New Timeline (untilApril 2012) Oct-2011 Nov-2011 Dec-2011 Jan-2012 Feb-2012 Mar-2012 Apr-2012 ASSESSMENT existing KPIs T3.1 KEY • SubTask Completed • Contact JRC & Get all KPI Documentation T3.1.1 • SubTask to be completed (urgently) • DELAY SubTask to be completed (on schedule) • Analysis KPI methodologies T3.1.2 • WP3 Internal Discussion on best KPIs T3.1.3 Report & Presentationon best KPIs T3.1.4 MS301 T3.2 - DEFINITION EEGI Program / ProjectKPIs

  13. KPI SubArea – Deliverable 3.4 Yr1 DraftTimeline Oct-2011 Dec 2011 Feb 2012 Apr 2012 Jun 2012 Aug 2012 Oct 2012 Official D3.4 Milestones and Deliverables Mar 15 2013 Jun 15 2012 MS301 – EEGI Project and ProgramKPIsvalidated D3.4 – EEGI Project & ProgramAssessment Report based on definedKPIs Internal Meetings / Milestones Oct 20 2011 Feb 15 2012 Jun 15 2012 T&Dpresentationof “most-promising” KPIs, withmappingto EEGI objectives (Program & Project) Management Boardvalidationofthis KPI mapping WP3 Kick-off Meeting Management Boardvalidationof EEGI Project & ProgramKPIs

  14. Outline Summary Labeling – Deliverable D3.1 KPI – Deliverable D3.4 Finance – Deliverable D3.6 Bruxelles, October 2011

  15. WP3 Deliverables

  16. Finance SubArea – Year 1 activities Oct-2011 Dec 2011 Feb 2012 Apr 2012 Jun 2012 Aug 2012 Oct 2012 WP3 Finance Tasks CREATION PORTFOLIO financing schemes T3.6 Analyze Financial Schemes & Preliminary Assessment Report D3.6 – Portfolio ofpossiblefinancingscheme T3.6.1 PreliminaryAssessment Report Validation Preliminary Report T3.6.2 • Create Portfolio of Financing Schemes T3.6.3 Validation Management Board T3.6.4 • Buffer

  17. FinancingSubArea – Deliverable 3.6 DraftTimeline Oct-2011 Dec 2011 Feb 2012 Apr 2012 Jun 2012 Aug 2012 Oct 2012 Official D3.6 Milestones and Deliverables Sep 15 2012 D3.6 – Portfolio ofpossiblefinancingschemes Internal Meetings / Milestones Sep 15 2012 Oct 20 2011 Jan 30 2012 Mar 15 2012 Management Boardapprovalof portfolio offinancingschemes WP3 Kick-off Meeting Technofipreliminaryassessment report on existingFinancingSchemes, presentedto Management Board TechnofirawdraftpresentationofinitialfindingsofFinancingmechanisms

More Related