680 likes | 1.02k Views
2. WELCOME. 3. PSCo Planning Process. 4. Planning Process. CalendarMethodology / Criterion ReportingRegulatory InteractionColorado Rule 3206CPCN's with Colorado PUC. 5. Planning Calendar 2009. . . . . . . . . . . May. Jun. Jan. Feb. Mar. Apr. Aug. Sep. Jul. Oct. Nov. . 5 year capital budget stu
E N D
1. 1 FERC 890 1st Quarter Stakeholder Meeting for Transmission Planning Denver, CO
March 6, 2009
8:30 a.m. – 11:30 a.m.
2. 2 WELCOME
3. 3 PSCo Planning Process
4. 4 Planning Process Calendar
Methodology / Criterion
Reporting
Regulatory Interaction
Colorado Rule 3206
CPCN’s with Colorado PUC
5. 5 Planning Calendar 2009
6. 6 Transmission Map
7. 7 Planning Study Process Prepare Study Models
Utilize PSCo Base Case Preparation Process
Determine Appropriate WECC Base Cases as basis for Study
Verify Study Years, System Conditions, Demand Levels are appropriate Model projected transfers
Model appropriate regional loading
Include existing and planned facilities
Include Reactive Power resources as appropriate
Studies
Include effects of existing and planned protective systems as appropriate
Include effects of existing and planned control devices including load tap changers, switched shunt devices, and generation control as appropriate
Include planned or maintenance outages of equipment
Methodology
Assess performance to meet TPL-001 (N-1) and TPL-002 (N-1) requirements
Assess performance to meet TPL-003 (N-2) and TPL-004 (exploratory) as appropriate
Develop Recommendations for System Upgrades
8. 8 Methodology Analyses
Powerflow (Static)
Dynamic (Transient and Voltage Stability)
Software
GE PSLF
Siemens/PTI PSS/E
Conditions
System Intact (N-0)
Single Contingencies (N-1) of All Regional Elements
Select N-2 Contingencies
Loading
Recent Load Forecasts
Generally Peak Summer
Sensitivities with Peak Winter and Lighter Loading
9. 9 Methodology - Criteria
NERC Standards
Table 1
TPL-001, 002, 003, 004
TPL – (001 thru 004) – WECC – 1 – CR - System Performance Criteria
(Formerly NERC/WECC Criteria)
WECC Disturbance-Performance Table of Allowable Effects on Other Systems
Other
WECC planning criteria including voltage deviation criteria for system response after disturbances was used in the analysis. Specifically, WECC requires that for a single contingency, transient voltage dips cannot exceed 25% at load buses, or 30% at non-load buses, cannot exceed 20% for more than 20 cycles at any load bus, cannot have a post-transient voltage deviation exceed 5% at any bus, and the frequency cannot dip below 59.6 Hz for 6 cycles or more at a load bus. For multiple contingencies, transient voltage dips cannot exceed 30% at any bus and cannot exceed 20% for more than 40 cycles at any load bus, cannot have a post-transient voltage deviation exceed 10% at any bus, and frequency cannot dip below 59.0 Hz for 6 cycles or more at a load bus. The addition of any new generation cannot produce system performance that is out of compliance with the values stated above.
WECC planning criteria including voltage deviation criteria for system response after disturbances was used in the analysis. Specifically, WECC requires that for a single contingency, transient voltage dips cannot exceed 25% at load buses, or 30% at non-load buses, cannot exceed 20% for more than 20 cycles at any load bus, cannot have a post-transient voltage deviation exceed 5% at any bus, and the frequency cannot dip below 59.6 Hz for 6 cycles or more at a load bus. For multiple contingencies, transient voltage dips cannot exceed 30% at any bus and cannot exceed 20% for more than 40 cycles at any load bus, cannot have a post-transient voltage deviation exceed 10% at any bus, and frequency cannot dip below 59.0 Hz for 6 cycles or more at a load bus. The addition of any new generation cannot produce system performance that is out of compliance with the values stated above.
10. 10 Reporting – Annual 2009
11. 11 Reporting - Postings Tariff Studies
http://www.rmao.com/wtpp/PSCO_Studies.html
FERC 890 Information
http://www.oatioasis.com/psco/index.html
SB07-100
http://www.rmao.com/wtpp/SB100.html
High Plains Express
http://www.rmao.com/wtpp/HPX_Studies.html
WestConnect
http://www.westconnect.com/
12. 12 FERC 890 Attachment R Update
13. 13 2008 Filing Responded October 15, 2008
Full Filing: http://www.xcelenergy.com/SiteCollectionDocuments/docs/Xcel-Order890-Comp-Filing-Revision1.pdf
Other Information on OASIS:
http://www.oatioasis.com/psco/index.html, under FERC 890
Including:
Contacts:
http://www.oatioasis.com/PSCO/PSCOdocs/PSCo_Att_R_Points_of_Contact-10172008.pdf
Hyperlink List:
http://www.oatioasis.com/PSCO/PSCOdocs/PSCo_Att_R_Hyperlinks-10172008.pdf
Attachment R (K) only:
http://www.oatioasis.com/PSCO/PSCOdocs/PSCo_Attachment_R_101508.pdf
Meeting Notices and Materials
14. 14 PSCo 2008-2009 studies
15. 15 Transmission Planning Studies Near Term (Capital Budget) Studies
Tariff Studies
Senate Bill 07-100
High Plains Express
10-Year Plan
16. 16 Annual Capital Budget Assessment Conducted annually
Project recommendations developed from transmission reliability studies.
Generally divided into regions:
Denver/Boulder
Foothills
Western Colorado
Front Range (I-25 Corridor)
17. 17 Planned Project Status ( 5 year plan) Comanche - Daniels Park 345 kV Transmission Project
Chambers 230/115 kV Transmission intertie Project
Sandown - Leetsdale 115 kV Project
Midway - Waterton 345 kV Transmission Project
Niwot / Gunbarrel 230 kV Underground Line
18. 18 Comanche - Daniels Park 345 kV Transmission Project
19. 19 Comanche - Daniels Park 345 kV Project
20. 20 Chambers 230/115 kV Transmission Intertie Project
21. 21 Chambers 230/115 kV Transmission Intertie Project
22. 22 Sandown - Leetsdale 115 kV Transmission Project
23. 23 Sandown - Leetsdale 115 kV Transmission Project
24. 24 Midway - Waterton 345 kV Transmission Project
25. 25 Midway - Waterton 345 kV Transmission Project
26. 26 Niwot / Gunbarrel 230 kV Underground Line
27. 27 Niwot/Gunbarrel 230 kV Underground Line
28. 28 FERC Generation Interconnection Process
29. 29 Generation Interconnection Process FERC Orders 2003 and 2006
Order 2003 for Large Generators
Greater than 20MW
Large Generator Interconnection Process (LGIP)
Large Generator Interconnection Agent (LGIA)
Applies to all generation technologies
Order 2006 for Small Generators
Less than or equal to 20MW
Small Generator Interconnection Process (SGIP)
Small Generator Interconnection Agent (SGIA)
Applies to all generation technologies
30. 30 LGI Process Feasibility Study
$10,000 deposit
Preliminary determination of interconnection and delivery facilities
Study Cost based on actual costs
Feasibility schedule: 6-9 months
System Impact Study
$50,000 deposit
Proof of Site Control required
Transient stability of system is studied
Study Cost based on actual costs
SIS schedule: 9-12 months
Facilities Study
$100,000 deposit
Detailed engineering design and cost estimates
Study cost based on actual costs
Facilities Schedule: 2-4 months
Study results become the basis for the LGIA
31. 31 Generation Interconnection Process PSCo Interconnection Queue
Total Requests since 2003: 81
Total MW: 23,970
Requests by Generation Type:
Wind: 52
Solar 10
Coal: 6
Gas: 12
Biomass: 1
32. 32 Active FERC Generation Interconnection Studies (2006-2009)
Arapahoe – 587 MW
Boone – 500 MW Wind
Fort St. Vrain – 300 MW Wind; 256 MW Combined Cycle
Green Valley – 400 MW Wind
Hartsel – 100 MW Solar
Walsenburg – 300 MW Wind
Comanche – 700 MW Wind
Keensburg – 250 MW Wind
Ault – 1600 MW Wind
Jackson Fuller – 601 MW Wind
Missile Site – 800 MW Wind; 270 MW Gas
Lamar – 2686 MW Wind
San Luis Valley – 150 MW Wind; 1730 MW Solar
Pawnee – 1170 MW Combined Cycle; 2820 MW Wind
33. 33 Senate Bill 07–100 Projects
34. 34 Senate Bill 07-100 Upon recommendations by the 2006 Transmission Task Force on Reliable Electricity Infrastructure, the Sixty Sixth General Assembly passed Senate Bill 07-100. Under SB 07-100, PSCo must meet the following requirements:
Designate “Energy Resource Zones (ERZ)”
Develop plans for the construction or expansion of transmission facilities necessary to deliver electric power consistent with the timing of the development of beneficial energy resources located in or near such zones
Consider how transmission can be provided to encourage local ownership of renewable energy facilities
Submit proposed plans, designations, and applications for certificates of public convenience and necessity to the commission for simultaneous review
35. 35
36. 36
37. 37 Proposed SB07-100 Projects Pawnee – Smoky Hill 345 kV Transmission Project
San Luis – Calumet – Comanche 230/345 kV Line
Missile Site 345 kV Switching Station
Lamar – Front Range 345 kV Transmission Project
Pawnee – Daniels Park 345 kV Line
Ault – Cherokee 230 kV Line Addition
Lamar – Vilas 230/345 kV Line
38. 38 Pawnee - Smoky Hill 345 kV Transmission Project
39. 39 San Luis - Calumet - Comanche 230/345 kV Line
40. 40 Missile Site 345 kV Switching Station
41. 41 Lamar - Front Range 345 kV Transmission Project
42. 42 Pawnee - Daniels Park 345 kV Line
43. 43 Ault - Cherokee 230 kV Line Addition
44. 44 Lamar - Vilas 230/345 kV Line
45. 45 Senate Bill 07-100 Schedule 2008 – 2009 Process
March 4, 2008: Kickoff Meeting
April – July 2008: Transmission Study Groups
November 24, 2008: Submit Transmission Plans
December 2008: Commission Workshop
February 27, 2009. CPCN approved for Pawnee to Smoky 345 kV
2009 CPCN Applications
October 31, 2009: Submit Biennial plan
http://www.rmao.com/wtpp/SB100.html
46. 46 High Plains Express project
47. 47 High Plains Express Initiative
48. 48 HPX Status MOU for Stage 2 Executed
Organizational Structure Defined
Executive Committee
Work Groups: Commercial, Siting, Technical, Communication
Stage 2 Scheduled Completion in 2010
49. 49 10-Year Plan
50. 50 Stakeholder Opportunity for comment into study scope for 10 year assessment
51. 51 Regional (WECC) Update
52. 52 Regional (WECC) Planning Coordination Committee
Focus on Reliability
Technical Studies Subcommittee
System Review Work Group
Transmission Expansion Planning Policy Committee
Focus on Economic Assessments
53. 53
54. 54 Sub regional Update
55. 55 CCPG Forum for joint transmission planning
Recognized WECC Sub-Region
Three Open Meetings/Year
April, August, December (Joint with SWAT/Sierra)
Denver TSGT Offices
Multiple Subcommittee and Work Group meetings throughout the year
Open to All Interested Stakeholders
Meeting Notices/Materials Posted at: www.westconnect.com
56. 56 CCPG Activities Long Range (10-Year) Planning
NERC Compliance
Senate Bill 100
Sub-subregional Studies
WECC Data Coordination
Regional Project Participation
Charter
Purpose of the MOU is to finance 3rd party consultants t do studies
We are in the process of evaluating and acquiring a consultant
Study Scope is being fully defined
Want to adhere to FERC 890 and be as open and transparent as possible.
The MOU was written to allow additional participants – paying and non-paying. But, even if an entity does not sign the MOU, the Parties will still welcome input and comments from other Stakeholders
Intent is to have a web-site for posting materials, as well as a Q&A section.
Purpose of the MOU is to finance 3rd party consultants t do studies
We are in the process of evaluating and acquiring a consultant
Study Scope is being fully defined
Want to adhere to FERC 890 and be as open and transparent as possible.
The MOU was written to allow additional participants – paying and non-paying. But, even if an entity does not sign the MOU, the Parties will still welcome input and comments from other Stakeholders
Intent is to have a web-site for posting materials, as well as a Q&A section.
57. 57 Next Next CCPG meeting
April 23, 2009; Denver TSGT office
Notices/Materials Posted at: www.westconnect.com
Contacts
Thomas Green
303-571-7223
thomas.green@xcelenergy.com
Or
Jared Griffiths (Co-chair)
Phone 970-461-7603
Email jgriffit@wapa.gov Mention that this is the first phase
Subsequent phases will address:
economics
detailed routing
Participation
Purpose of MOU Mention that this is the first phase
Subsequent phases will address:
economics
detailed routing
Participation
Purpose of MOU
58. 58 CCPG Long Range Planning Group (CLRGPG) Assessment Purpose:
Develop 10 Year Transmission Plans (2018 Models)
Consider RPS & up to 30% Renewable
Re-evaluate the Eastern Plains Transmission Project Annual assessments include:
Assessment
Load Flow Analysis
Four Scenarios
59. 59 Long Range Scenarios Colorado resources suggested by Utility resource planners
Meets or exceeds Colorado’s Renewable Portfolio Standard
“Stressed” from South to North
Displace some northern CO resource with WY
Injected into CO via the proposed Wyoming-Colorado Intertie Project
Stressed North to South
Up To 5% of the capacity in Colorado’s Wind GDA’s
2000 MW from Colorado’s Central Solar Power GDA’s
60. 60 Scaled Scenario C (Total 2917 MW new)
61. 61 Scenario C – Topology Summary Lamar area to:
Comanche 345/500kV (SB100)
Big Sandy – Missile Site 345/500kV (SB100)
Burlington 345/500kV
Burlington - Wray 230kV
Pawnee - Smoky Hill – Daniels Park 345kV (SB100)
Ault – Cherokee 230kV (SB100)
62. 62 Subregional (WestConnect)
63. 63 Status of WestConnectSubregional Planning Process
2008 Planning Cycle posted on web site
2013 & 2018 Adequacy Assessments( Posted)
Coordinated with CCPG
10-Year Study Plan and Report (Posted)
Workshop in October
Report in January
Currently preparing 2009 scope of work
Website
http://www.westconnect.com/
64. 64 Transmission customers update loads, resources and demand responses
65. 65 Study Request Review
66. 66
67. 67 Stakeholder Questions & Comments
68. 68 4th Quarter meeting Dec 10, 2009
69. 69 Adjourn