1 / 11

GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7

Gamma-ray Large Area Space Telescope. GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7 Face-to-Face Nov 04 Mike Huffer/Gunther Haller mehsys@slac.stanford.edu haller@slac.stanford.edu. Test-Stand Summary. Finished TKR test-stands

ervinv
Download Presentation

GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Electronics, Data Acquisition & Flight Software W.B.S 4.1.7 Face-to-Face Nov 04 Mike Huffer/Gunther Haller mehsys@slac.stanford.edu haller@slac.stanford.edu

  2. Test-Stand Summary • Finished TKR test-stands • ACD was already finished • Remaining: • 1 TPS + 3 TEM’s. In conformal coating, expected back end of this week. To be shipped next week • 1 PDU to I&T

  3. Test-Stand Summary (continued) • ACD • DAQ/I&T team travelled to GSFC to update LCB including code on ACD test-stands • Status: seems to work • CAL • DAQ/I&T team travelled to NRL to update 3 CAL test-stands • Status: works • Additional LCB’s to update remaining ones in progress • TKR • Need to decide when to update

  4. ACTEL’s • Exchanged all 32-1 and 72-series MEC fab-line ACTELS with UMC-fab-line • Programmed 4 TEM sets • Are in lead-forming, expected back this week • To be assembled on TEM Qual, TwrA, TwrB TEM (one spare set of FPGA’s) • 72-1 series (used on LCB) not received yet, but not needed yet

  5. TEM/TPS Production Status • TEM/TPS Assembly (at General Technology) • Surface-mount assembled both sides of 3 TEMs and 3 TPS’s • No FPGA’s since GT pointed out some pin-misalignment • Sent back to SLAC, decided that they can be used • GT agreed but we will be sending UMC line devices • Does not delay schedule, since FPGA’s will be put on using METCAL rework station • 3 TEM’s were dropped from about 3 feet by accident • NCR’s created, damage being investigated • Probably ok but needs action • Boards were again inspected • Proceed with thru-hole components • In parallel decide how to repair damage if needed • Find out why it happened to prevent it from happening again • Wait till function/performance test to close NCR’s • Very slow progress. GT received parts kit 9/23. As of today only SMD components loaded (no thru-hole, etc) • Test-stands arrived at General Technology • 3 engineers will travel Monday after Thanksgiving to Board test (assuming assembly proceeds as planned) • Getting assembled boxes back before Christmas is a challenge • Released production of balance of PCB’s, expected in 20 days. • Can’t wait anymore until GT has first board assembled • Low risk since SLAC had already assembled one flight boards and tested over T • Plan still to wait for programming of balance of FPGA’s until board test results are available

  6. GASU & GASU-PS & PDU • PDU • Flight PCB fabrication: Received at SLAC • One board will be loaded in-house • Internal cable assembly • SOW released • RFP package being assembled in purchasing • Enclosure in fabrication, expected early December • Overall assembly • SOW released • Drawings released • RFP being assembled in purchasing • Issue with one part: Omnirel regulator which was recalled: Delivery not before end of February • Tester defined • GASU, GASU-Power Supply • Flight PCB fabrication awarded: Expected to be received early December • Rest identical status as PDU • Tester being designed and built • Test coverage for AEM and CRU, and EBM strong, GEM is weak

  7. SIU/EPU • Crate enclosures in fabrication, expected to be received in December • RFP package for internal harness being worked on in purchasing • Boards • Finished hole size will be 32 mil +/-3 on PCI boards including back-plane • Did not get feed-back by GSFC or PCB (but had sent email that we will proceed unless there are concerns) • Proceed with flight board fabrication • SIB, LCB, CPS, Backplane • PCB packages in release cycle • Backplanes, LCB out for RFP • ERNI cPCI connectors still not approved, not sure about the screening plan. Issue with Sn plating? • Did some tests at SLAC material lab, report in progress • Need closure from PCB & GSFC • Assembly SOW not written yet • EEPROM on RAD750 issue • See FSW. Decided to use 4 images and check-sum. No PROM

  8. LAT Harness (Box-to-Box) • RFP package of most cables being finalized in purchasing • Drawings released • There will be second RFP for remaining drawings • E.g. PDU to miscellaneous internal LAT sensors

  9. ASIC • All GTCC1, GCCC1 TEM ASIC’s screened • Qualification testing at GSFC has started • Test-setup assembled at GSFC and is working • GLTC ASIC’s (for GASU) • Thermal cycled GLTC’s • Screening hardware debugged, working • Test software in progress (Leonid has taken over for Oren who is not at SLAC anymore)

  10. Testbed • Hardware construction complete • Minor testing of EPU’s from a system level remains… • Waiting on availability of FSW EPU bootstrap • Physics-to-Physics demonstration • GLEAM to (LATTE) Single Event Display • > 20 KEvents/sec (for hours) • All 16 towers (+ readout of ACD) • Normal muons • 1 GEV gammas • Working on incorporating ACD simulation • Shown to work stand-alone

  11. 17th “tower” • Constructing… • Full tower • 4 AFEE production-line flight board copies • 36 production line MCMs • flight design cables • Partial tower • 4 AFEE production-line flight board copies • Limited number of EM MCMs • Burn-in cables • Keystone for much of our testing… • FSW Calibration software • GASU production • TEM validation • I & T software commissioning and practices validation • Calorimeter worked right out the box • Issues with tracker (being worked)

More Related