Southwood /Fargo Country Club Flood Risk Management Project. Neighborhood Meetings July 20, 2011. Southwood /Fargo Country Club HOW WE GOT HERE PETITION RECEIVED THIS PAST WINTER FROM NEIGHBORHOOD REQUESTING A LEVEE PROJECT IN REAR YARDS
E N D
Southwood/Fargo Country Club Flood Risk Management Project Neighborhood Meetings July 20, 2011
Southwood/Fargo Country Club • HOW WE GOT HERE • PETITION RECEIVED THIS PAST WINTER FROM NEIGHBORHOOD REQUESTING A LEVEE PROJECT IN REAR YARDS • EMERGENCY LEVEE CONSTRUCTED PRIOR TO THIS PAST SPRING’S FLOOD
Southwood/Fargo Country Club Emergency Levee – As Built BUILT TO AN ELEVATION OF 44-FEET
Southwood/Fargo Country Club – Across Course Levee • ALIGNMENT DESIGNED BY FARGO COUNTRY CLUB’S ARCHITECT • ONLY POSSIBLE ALIGNMENT ACROSS THE COURSE THAT WILL NOT RESULT IN SAFETY ISSUES FOR THE COURSE • PORTION OF SOUTHERN END WITHIN THE FLOODWAY
Southwood/Fargo Country Club – Across the Course Levee • GEOTECHNICAL STUDY COMPLETED • STUDY SHOWED THAT THE FACTOR OF SAFETY FOR THE LONG TERM STABILITY WOULD NOT BE MET • ANALYSIS DID NOT FACTOR IRRIGATION OF DRIVING RANGE INTO IT
Southwood/Fargo Country Club – Permanent Levee Option • CLOSELY FOLLOWS EMERGENCY LEVEE ALIGNMENT • ACTUAL ALIGNMENT WILL BE REVIEWED FURTHER • CENTERED ON PROPERTY LINES FROM 521 TO APPROXIMATELY 909 SOUTHWOOD DRIVE • BUILT TO AN ELEVATION OF 42.5-FEET PLUS 1-FOOT
Southwood/Fargo Country Club – Schedule • JULY 20, 2011 – PUBLIC MEETING • JULY 27, 2011 – BACKYARD WALKTHROUGH • AUGUST 22, 2011 – CALL FOR BIDS • SEPTEMBER 14, 2011 – OPEN BIDS • SEPTEMBER 19, 2011 – AWARD BIDS • OCTOBER 3, 2011 – CONTRACT AWARD, CONSTRUCTION BEGINS SHORTLY AFTER • SPRING 2012 – FINAL COMPLETION • FALL 2012 – PHASE 2 CONSTRUCTION • FUTURE NEIGHBORHOOD MEETINGS WILL BE HELD