1 / 9

8.0m

Proposed Offset Mirror System. J. Arthur. SiC 1.5mrad. Be 13mrad. 24mm offset. SiC 1.5mrad. 8.0m. The Problem. Unfiltered LCLS beam contains significant background from spontaneous harmonics (Ec ~ 150 keV) and from Bremsstrahlung from scattered electrons (GeV).

ethelda
Download Presentation

8.0m

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Proposed Offset Mirror System J. Arthur SiC 1.5mrad Be 13mrad 24mm offset SiC 1.5mrad 8.0m

  2. The Problem Unfiltered LCLS beam contains significant background from spontaneous harmonics (Ec ~ 150 keV) and from Bremsstrahlung from scattered electrons (GeV) Much of this background lies directly on axis, and it is time-coincident with the FEL pulse This is a nuisance for radiological shielding, and a huge problem for data taking

  3. The Proposed Solution Use total-reflection mirrors to deflect FEL radiation (and 3rd harmonic, up to 24 keV). Use collimating apertures to eliminate non-reflected background

  4. Reflectivity vs energy for a flat SiC mirror at 1.5 mrad incidence angle R > 95% for E < 24 keV R < 10% for E > 28 keV From Berkeley CXRO calculator: <http://www.cxro.lbl.gov/optical_constants/mirror2.html>

  5. The mirror system will consist of two mirror pairs. One pair will be inserted at a time. The SiC pair gives a cutoff at 24 keV; the Be pair gives a cutoff at 2 keV. Interlocks can be used, if necessary, to assure that one of the mirror pairs is always inserted. SiC 1.5mrad Be 13mrad SiC 1.5mrad 24mm offset 8.0m

  6. Technical Issues Create new White Beam Optics Enclosure by moving shielding in FEE upstream 5mm apertures define FEL beam (plus core spontaneous) Alignment is critical Need high-quality mirrors Risk of damage to mirrors from intense FEL pulse

  7. Proposed layout of FEE 4 ft Fe 3 ft concrete 4 ft Fe SiC MIR Be MIR GAS ATTEN STOP ADJ SLIT COLLIM ADJ SLIT STOP SOLID ATTEN 15m 11.6m >2M SPACE FOR DIAGS ~0.6M SPACE FOR DIAGS

  8. 4 ft Fe 3 ft Concrete 4 ft Fe 3 ft Concrete 24mm offset 1m 0.65m 8.0m 3.78m 9.0m 1m 2.13m 11.65m 2.13m Pop-in camera location

  9. Status of Proposal Radiation Physics has examined shielding implications, presented preliminary report Discussion between XTOD and XES regarding real estate in FEE, commissioning plan, etc. Conventional Facilities implications are understood Final decision expected soon

More Related