1 / 0

Project Management, PMI Approach (PMP) Project Time and Schedule Management

Resources: Book: PMP in Depth by Dr. Paul Sanghera Book: The PMP Exam, How to Pass on Your First Try By Andy Crowe Project Management Lessons in Undergraduate Study Work Experience. Just E.T.C for Business, Education, Technology, and Entertainment Solutions.

etoile
Download Presentation

Project Management, PMI Approach (PMP) Project Time and Schedule Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Resources: Book: PMP in Depth by Dr. Paul Sanghera Book: The PMP Exam, How to Pass on Your First Try By Andy Crowe Project Management Lessons in Undergraduate Study Work Experience Just E.T.C for Business, Education, Technology, and Entertainment Solutions

    Project Management, PMI Approach (PMP)Project Time and Schedule Management

    sayed@justEtc.net, www.justEtc.net Sayed Ahmed BSc. Eng. in CSc. & Eng. (BUET, Bangladesh) MSc. in CSc. (University of Manitoba, Canada) http://sayed.JustEtc.net http://www.JustETC.net
  2. References & Resources Book: PMP in Depth by Dr. Paul Sanghera Read on 2007 Book: The PMP Exam, How to Pass on Your First Try by Andy Crowe Read on 2007 A Project Management lessons in undergraduate study Articles from the Internet Work Experience sayed@justEtc.net, www.justEtc.net
  3. Learning Objectives sayed@justEtc.net, www.justEtc.net
  4. Our Services sayed@justEtc.net, www.justEtc.net
  5. Project Time Management Process 1. Define Activities Required2. Sequence Activities3. Estimate Resources for the Activities4. Calculate Duration of the Activities5. Develop Schedule6. Control Schedule sayed@justEtc.net, www.justEtc.net
  6. Project Time Management Process Process: Define Activities Required List all the activities functionalities modules components That you want to develop When the project scope is defined use it to decompose the work into activity list Work breakdown structure will be useful at this stage List what modules, components the project will handle sayed@justEtc.net, www.justEtc.net
  7. Project Time Management Process Process: Define Activities Required List all the functionalities/activities that are required for each of the modules/components For each activity define properties assumptions quality requirements and output requirements Input: Define Activities Required Project scope statement Work breakdown structure Output: Define Activities Required Project activities [activity list] Activity attributes milestone list requested changes sayed@justEtc.net, www.justEtc.net
  8. Project Time Management Process Process: Define Activities Required Tools Decomposition Decompose work into smaller activities. Project team or the functional manager may be of good use here Templates The Company may have them other project may have them and some standards like IEEE may define some templates Rolling Wave Planning Many later aspects of the project may not be understood at the beginning Hence, initially decompose as much as possible and later with the progress, improve the decomposition Expert Judgment Take help of other experts in the field Project team or the functional manager may be of good use here sayed@justEtc.net, www.justEtc.net
  9. Project Time Management Process Process: Sequence Activities Find the order/sequence of the activities Some activities may be dependent on the completion of another activity – find them Some modules may be dependent on the completion of another module– find them Sometimes, it may be the case some activities/modules are not strictly dependent on another activity but may be preferable to start after another activity/module [Best Practice] Find them In this step, you need to find the sequence and then create a project network diagram Note module refers to a complete unit/component where each module may have many activities sayed@justEtc.net, www.justEtc.net
  10. Project Time Management Process Process: Sequence Activities Input Mostly from the first step Project scope statement Activity list Activity Attributes Milestone List Approved change requests sayed@justEtc.net, www.justEtc.net
  11. Project Time Management Process Process: Sequence Activities Tools Precedence Diagram Method (PDM) Activities are represented by the nodes where arrows represent the dependencies that exist between the activities Arrow Diagramming Method (ADM) Activities are represented using arrows where nodes represent the connection points We can create dummy activities with dotted arrows [not possible in PDM] sayed@justEtc.net, www.justEtc.net
  12. Project Time Management Process Process: Sequence Activities Tools Graphical Evaluative Review Technique (GERT): Like the PDM diagrams. Additionally, you can show dependencies among activities. Also, you can represent repeated processes. Network Templates: Sub networks of another project in the organization may be useful. Dependency Determination: like mandatory dependencies [you can not break the dependency] discretionary dependencies [best practices, the dependency is not strict], and external dependencies [out of the scope of the project]. Apply leads and lags: sayed@justEtc.net, www.justEtc.net
  13. Project Time Management Process Process: Sequence Activities Output Project schedule network diagram sayed@justEtc.net, www.justEtc.net
  14. Project Time Management Process Process: Estimate Resources for the Activities 3rd: Then you need to identify the resource requirements of each activity Process: Calculate Duration of the Activities 4th: Estimate duration for each activity It may be experience based practical examples based another completed project based mathematical analysis based Process: Develop Schedule 5th: Develop the schedule Project sequencing and time estimating will directly affect this Several projects may require the same resource Hence, the schedule should check when the resource is available and schedule accordingly Process: Control Schedule 6th: Monitor how the schedule is performing sayed@justEtc.net, www.justEtc.net
  15. Project Schedule Development In this phase, the following are determined Project duration Project finish date Schedules of the activities Input to the Phase Activity List Activity Attributes Project Schedule Network Diagrams Activity Duration Activity Resource Requirements Resource Calendars sayed@justEtc.net, www.justEtc.net
  16. Project Schedule Development Tools Critical Path Model (CPM) CPM is extensively used to determine the project duration CPM method also helps to identify how much individual activities can slip without affecting the total duration of the project Crashing and Fast tracking Crashing tries to add more resources into the project to ensure that the project will be finished on time or early. [Note: Fred's theory: adding resources to an already delayed project will/may increase the delay] Fast tracking tries to run multiple activities in parallel to ensure that the project will be finished on time or early Resource Leveling Apply the resource availability [and quantity] to the project duration It may increase the project duration when sufficient resource [in quantity or at the right time] is not available. sayed@justEtc.net, www.justEtc.net
  17. Project Schedule Development Critical Chain Method It is almost similar to the Critical Path Method Critical path method uses a concept called float CPM first calculates the total duration and then calculates float [how much it can slip] for each activity CPM ensures that no activity exceeds its float In Critical Chain Method latest possible start and latest possible finish dates are determined for each activity Afterwards, buffers are added between activities The goal is never try to exceed the buffer Company Calendar Company Calendars may be used to check the company holidays, or events that may affect the project duration/schedule Adjusting leads and lags sayed@justEtc.net, www.justEtc.net
  18. Steps in CPM Model Using CPM Model [steps] 1. CPM uses the arrow diagram method [activities and duration on arrows, nodes as connectors] to represent project activities and duration. 2. After building the diagram find the critical path [the path that takes the longest time from start to finish considering all alternatives] 3. Calculate float how much an activity can slip without affecting the critical path. 4. Calculate Early start The earliest date an activity can start considering the dependencies 5. Calculate Early finish Early start date + duration – 1 sayed@justEtc.net, www.justEtc.net
  19. Steps in CPM Model 6. Calculate Late Start: What is the last date an activity can start considering the dependencies 7. Calculate Late Finish: Late start date + duration – 1 8. Calculate Free Float: Amount of time an activity can be delayed without affecting the dependent activities' early start date 9. Calculate Negative Float: Occurs when an activity's start date occurs before a preceding activity's finish date When you have calculated all the values the values will help greatly in the schedule control sayed@justEtc.net, www.justEtc.net
More Related