PHILADELPHIA DISTRICT 2008 – 2012 DREDGING PROGRAM

PHILADELPHIA DISTRICT 2008 – 2012 DREDGING PROGRAM. Trenton. Philadelphia. Manasquan Inlet. PA. NJ. Baltimore. Dover. Delaware Bay. Delaware River, Phila to Trenton. Schuylkill River. Barnegat Inlet. Delaware River, Phila to the Sea. C&D Canal. Salem River. Absecon Inlet.

Download Presentation

PHILADELPHIA DISTRICT 2008 – 2012 DREDGING PROGRAM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PHILADELPHIA DISTRICT 2008 – 2012 DREDGING PROGRAM

  2. Trenton Philadelphia Manasquan Inlet PA NJ Baltimore Dover Delaware Bay Delaware River, Phila to Trenton Schuylkill River Barnegat Inlet Delaware River, Phila to the Sea C&D Canal Salem River Absecon Inlet Cohansey River Maurice River NJIWW Murderkill River Mispillion River Cold Springs Inlet (Cape may Inlet) L&R Canal Indian River Inlet NAP Navigation Projects

  3. FY08-FY12 Dredging Schedule Philadelphia District FY08 FY09 FY10 FY11 FY12 Dredge + Quantity (CY) Placement Site Maintenance Dredging 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr Hydraulicl 2M Upland Delaware River, Ph to Trenton Hydraulicl 1M Upland Wilmington Harbor Mechanical 500K Upland C&D Canal Proper Mechincal Hopper 300K Upland C&D Canal Approaches Hydraulic ~40K Upland C&D Canal Lower approach. Mechanical ~600K Site 92 open Hydraulic Schuylkill River Upland Hydraulicl ~250K Salem River Upland

  4. US Army Corps of Engineers Philadelphia District Delaware River, Phila. to SeaMaintenance Dredging - Hydraulic Cubic Yards – 2,000,000 Type of Material – Maintenance – Silt/Sand Type of Equipment – Pipeline Type of Disposal – Confined Upland Disposal Bid Opening Date – Spring Frequency - Annual Conditions: Issue work assignments for different ranges. First work assignment is normally issued by September.

  5. New Castle Range/ Killcohook Disposal Area Disposal Area – upland Delaware River – 5,246 acres C&D Canal - 7,623 acres NJIWW - 36 acres Wilmington Harbor - 277 acres

  6. US Army Corps of Engineers Philadelphia District Wilmington Harbor, DEMaintenance Cubic Yards – 650,000 Type of Material – Silt Type of Equipment – Pipeline Type of Disposal – Confined Upland Disposal Frequency - Annual Remarks – No dredging allowed between 1 April and 15 June

  7. US Army Corps of Engineers Philadelphia District IWW, Delaware River – Chesapeake BayLower Approach Maintenance Cubic Yards – 600,000 Type of Material – Silts Type of Equipment – Open water - Bucket and scows Type of Disposal – Open water Special Conditions – Placement of material in the disposal area Environmental Windows/ Constraints – Open Water placement Remarks – Site 92 closes after 2009

  8. IWW from Delaware River to Chesapeake Bay, DE & MD Delaware City Chesapeake City C&D Canal Delaware River Chesapeake Bay Baltimore Poole’s Island DE MD Site 92 Dover

  9. US Army Corps of Engineers Philadelphia District Schuylkill RiverMaintenance Cubic Yards – 500,000 Type of Material – Silt Type of Equipment – Pipeline Type of Disposal – Confined Upland Disposal Frequency Every other year Environmental Windows/ Constraints – None Remarks – Numerous pipeline crossings.

  10. Coastal Navigation Projects PA Manasquan Inlet Philadelphia NJ Barnegat Inlet NJIWW Baltimore Absecon Inlet Dover Delaware Bay MD Cape May Inlet Indian River Inlet DE

  11. FY08-FY12 Dredging Schedule Philadelphia District FY08 FY09 FY10 FY11 FY12 Dredge + Quantity (CY) Placement Site Maintenance Dredging 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr Hydraulic 300K NJIWW Upland Cold Spring Inlet Gov’t Plant 100K Open Beach Barnegat Inlet Gov’t Plant 95K Open Beach Manasquan Inlet Gov’t Plant 60K Open Beach

  12. US Army Corps of Engineers Philadelphia District New Jersey Intracoastal WaterWay Maintenance Cubic Yards – 350,000 Type of Material – Sand and silt Type of Equipment – Pipeline Type of Disposal – Confined Upland and Open Water Environmental Windows/ Constraints – N/A Remarks – Small Business set aside

  13. DE Shore Protection Projects Lewes – Roosevelt 2004 KEY Constructed projects (date) Rehoboth & Dewey Beaches 2005 1 Bethany – S. Bethany (initiated 2007) DE Fenwick Island 2005 MD Ocean City Updated October 2007

  14. Philadelphia District Coastal Storm Damage Reduction Projects KEY Constructed Project (Date Initiated) Authorized, not Constructed Not Yet Authorized Manasquan Inlet to Barnegat Inlet Barnegat Inlet to Little Egg Inlet (LBI)2005 Oakwood Beach Brigantine Is. – 2005 Absecon Is. - 2003 Reeds Beach Ocean City - 1992 Great Egg Inlet to Townsends Inlet Villas Avalon – Stone Harbor - 2002 Hereford Inlet to Cape May Cape May City - 1990 Lower Cape May Meadows Cape May Point - 2004 Updated: October 2007

  15. FY08-FY12 Dredging Schedule Philadelphia District FY08 FY09 FY10 FY11 FY12 Dredge + Quantity (CY) Placement Site Beach Fill Dredging -NJ 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr Mechanical 500K Beach Brigantine Island Hydraulic Hopperl 500K Beach Hydraulic- Hopperl 1.6M Absecon Island Beach Ocean City Beach fill Hydraulic- Hopper ~1.1M Beach 7 Mile Island Hydraulic- Hopper ~800K Beach Cape May City & CG Base Hydraulic- Hopper ~400K Beach Cape May Point Hydraulic- Hopper ~650K Beach

  16. FY08-FY12 Dredging Schedule Philadelphia District FY08 FY09 FY10 FY11 FY12 Dredge + Quantity (CY) Placement Site Beach Fill Dredging - DE 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr 1st Qtr 2nd Qtr 3rd Qtr 4th Qtr Hydraulic 132K Beach Rehoboth – Dewey Beach Hydraulic- Hopperl 360K Upland & HARS Fenwick Island Hydraulic – Hopperl 320K Upland Bethany – South Bethany Hydraulic ~Hopper 480K Upland