NAMC March 2011. Project Scope, Budget and Schedule. Capital Building Program. 15 distinct projects spread over three DMC campuses $500 million dollars total project cost Project budgets range from $2.3 million dollars to $126 million dollars (construction cost)

everley
Download Presentation

NAMC March 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NAMC March 2011

  2. Project Scope, Budget and Schedule

  3. Capital Building Program • 15 distinct projects spread over three DMC campuses • $500 million dollars total project cost • Project budgets range from $2.3 million dollars to $126 million dollars (construction cost) • Complex projects built in an operating hospital environment requiring a high degree of skill and experience

  4. Central Campus Harper University Hospital

  5. Harper/ Hutzel Unified Lobby • Project Specifics: • Renovation and New Construction • $8.5 million construction • 18 month project duration • Summer 2011 start date

  6. Pre & Post Operative Care Lockers Nuclear Medicine Surgery Recept & Waiting OR Storage & Support Nuclear Medicine KCC Labs OR Storage & Support Operating Rooms Labs Lockers Surgical Services Renovation • Project Specifics: • Phased renovation • $16.9 million construction • 28 month project duration • Fall 2011 start date

  7. HUH Webber Memorial Hospital Ground Floor N Ground Floor Masterplan Project • Project Specifics: • Phased renovation • $9.8 million construction • 26 month project duration • Spring 2013 start date Support CT Scan Interventional Radiology Central Prep/ Recovery Radiology Ultrasound Reception & Check-In

  8. HUH Unit Renovations • Project Specifics: • Phased renovation • $4.3 million construction • 15 month project duration • Summer 2011 start date

  9. Harper ED Expansion • Project Specifics: • Phased renovation and new construction • $2.3 million construction • 12 month project duration • Start Date TBD

  10. Central Campus Children’s Hospital of Michigan

  11. CHM Patient Tower & Carls MOB • Project Specifics: • New construction and renovation • $126 million construction • 58 month project duration • Start Date TBD

  12. CHM Pediatric Specialty Center • Project Specifics: • New construction • $24.6 million construction • 16 month project duration • Fall ‘10 start date

  13. Central Campus Detroit Receiving Hospital

  14. DRH Inpatient Renovations • Project Specifics: • Phased renovation • $13.9 million construction • 48 month project duration • Summer 2012 start date

  15. DRH New OR & Pre/Post-Op • Project Specifics: • New construction and phased renovation • $4.4 million construction • 12 month project duration • Fall 2011 start date

  16. Central Campus Rehabilitation Institute of Michigan

  17. RIM 6th Floor Renovation • Project Specifics: • Renovation project • $3.15 million construction • 12 month project duration • Spring 2012 start date

  18. Central Campus Cardiovascular Institute and HUH Multispecialty Building

  19. Cardiovascular Institute & Multispecialty Building • Project Specifics: • New construction • $58 million construction • 34 month project duration • Fall 2011 start date

  20. Central Campus New Parking Structure

  21. New Parking Structure • Project Specifics: • New construction • $30.6 million construction • 20 month project duration • Winter 2012 start date

  22. NorthWest Detroit Campus Sinai Grace Hospital

  23. SGH ED, ICU & Radiology • Project Specifics: • New construction and Phased Renovation • $52.6 million construction • 36 month project duration • Fall 2011start date

  24. Commerce Township Campus Huron Valley Sinai Hospital

  25. Renovations to Private Rooms • Project Specifics: • Phased Renovation • $4.6 million construction • 11 month project duration • Early 2011 start date

  26. HVSH Additional ICU Beds • Project Specifics: • Phased Renovation • $2.3 million construction • 10 month project duration • Early 2012 start date

  27. Project Teams and Awards • Projects with A/E award and currently in design: • SGH ED, ICU, Radiology & Unified Lobby Project- SmithGroup/Hamilton Anderson/Scales • DRH New OR and Pre-Op/ Post-Op Project- Stucky Vitale/T2 • Design/Wade Trim • Harper/ Hutzel Unified Lobby Project- Neumann Smith/BEI./TYJT • HUH Surgical Services Renovations- HKS Inc./Hamilton Anderson/Desai Nasr • HUH Patient Unit Renovations- Stucky Vitale/T2 Design/Wade Trim • CVI & HUH Multispecialty Bldg & Parking Structure- Harley Ellis Devereaux Metco,BEI, DPRA, Centric Design

  28. Projects with CM award and currently in construction: • Children’s Hospital Pediatric Specialty Center Brinker, LLC • HVSH Inpatient Rooms MIG/Auch • Projects recently Awarded for CM Services: • DRH New OR and Pre-Op/ Post-Op Project DeMaria/C.S Farmer • Harper/ Hutzel Unified Lobby Project Walbridge/DIG • Projects currently out to bid for CM services: • SGH ED, ICU, Radiology & Unified Lobby Project 3/25 award • HUH Surgical Services Renovations 4/11 award • CVI & HUH Multispecialty Building & Parking Structure 4/11 award

  29. Projects awaiting release: • RIM 6th floor Renovation 12/2011 start • HVSH Additional ICU Beds 08/2011 start • DRH Patient Care Unit Renovations 05/2011 start • CHM Tower Project TBD • HUH Ground Floor Masterplan 05/2013 start • HUH Patient Unit Renovations construction 05/2011 start

  30. Project Labor Agreement(PLA)

  31. A Project Labor Agreement will be entered into between The Detroit Medical Center and the Greater Detroit Building and Construction Trades Council, (GDBTC), acting on its own behalf and on behalf of its respective affiliates, and signatory unions. • The purpose of this agreement will be to assure that all construction work shall proceed economically, efficiently, safely, continuously, without interruption and with due consideration for the protection of labor standards, wages and working conditions. • The GDBTC shall work with its respective signatory unions to promote hiring practices that promote DMC’s commitment to inclusion.

  32. Owner Controlled Insurance Program(OCIP)

  33. The Detroit Medical Center will enter into an agreement to provide and administer an Owner Controlled Insurance Program (OCIP). This will be a multi-site and multi-year program. This program will apply to all contractors and subcontractors providing services for these projects.

  34. Community Commitment

  35. The DMC has made a commitment to the Community by setting significant goals for inclusion: • 30% of all construction dollars will be awarded to minority-owned (MBE), women-owned (WBE) and Detroit based businesses (DHB, DBB) • A minimum of 25% of all hours worked on construction projects will be by a Minority • 25% of all hours worked on construction projects will be by City of Detroit Residents • 50% of all hours worked on construction projects will be by Wayne County Residents • A minimum of 25% of hours worked by apprentices on construction projects will be by Minorities

  36. Tracking & Reporting Progress The Detroit Medical Center has engaged the services of the MMSDC to oversee the collection and compilation of data supplied by all contracted firms relative to MBE, WBE, DBB/ DHB and residency requirements. This information will be supplied by each contracted firm on an on-line application and submitted monthly to the MMSDC for verification, compilation and the reporting of progress toward committed goals.

  37. Contractor Prequalification Requirements

  38. General Bidder PreQualification • As a prerequisite to working at the Detroit Medical Center, all firms must complete a BIDDER PREQUALIFICATION FORM and must be pre-approved. • Go to DMC.ORG and Click on the Construction Update Icon. • Prequalification helps to insure streamlined access to opportunities to participate in the Capital Building Program. • Companies who are prequalified will be posted on the DMC and Schooner Consulting Websites. • Prequalification is not a guarantee of work. It is a tool to help develop a pool of qualified contractors/ vendors.

  39. Non Capital Building Program Construction • The DMC posts all requests for proposals on the DMC Website . • Go to DMC.ORG and click on the Vendors Link at the bottom of the page. • At the Material Resource Management page click on view RFPs on the right side of the page.

  40. Questions