1 / 8

Casting “DISA” Outsourcing Project

Casting “DISA” Outsourcing Project. South Milwaukee - 2008 Timing. Launch – Took 10 – 14 weeks for initial castings to flow 2-3 weeks to figure out plan – started from Ground Zero…. Had to learn about tooling – both cores and patterns Had to review supplier options and capabilities

eydie
Download Presentation

Casting “DISA” Outsourcing Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Casting “DISA” Outsourcing Project

  2. South Milwaukee - 2008 Timing • Launch – Took 10 – 14 weeks for initial castings to flow • 2-3 weeks to figure out plan – started from Ground Zero…. • Had to learn about tooling – both cores and patterns • Had to review supplier options and capabilities • 2-3 weeks to “build out” current orders • SM had to build out Cores and then close out production runs – in the middle of run prioritization Plants did not want any gaps in the top runners for fill rate issues • 1-2 week to ship tools and modify at suppliers • Most tools required modifications (pour cups, pattern mounting , core boxes, core masks etc) • 1-3 weeks for trial runs • Core run trials were first • Limited production run – supplier had to complete dimensional reviews and send to mfg plants • 5 days for quality inspection • Over-night samples to plants – then samples sent overnight to Rosemont for review • Worked through grinding, hardness, lettering and print issues • 2-4 weeks for regular production run at suppliers (core build, castings & anneal) • 1 week for shipment of product to plants

  3. Actions to speed up 2010 Outsourcing • Moved patterns immediately to previous outsourced suppliers • Immediately kicked off (3) 2013B core masks for 2110, OZ ½ plate and Appleton ½ plate tools for flexibility (finished first set last week) • Kept Core boxes at South Milwaukee • Added 3 additional suppliers to spread work around and cover all options • Worked up full tooling strategy to give two to three options across the entire supply base • Wave initial “full PPAP” for parts – allow suppliers to run parts, take initial pictures and send pictures to mfg plants and Rosemont

  4. Challenges with the 2010 Outsourcing • Tooling Strategy 570 patterns outsourced – much more complex mix of metals, patterns and cored jobs sent out • Action: EGS team reviewing each pattern and core mask receipt at each supplier to identify any shipping damage and misidentified tooling. Approximately 1,250separate tools have been shipped out. • Action: EGS team came up with a detailed plan for tooling flexibility across suppliers • Summer Shutdown for many suppliers • Action: Suppliers (Anvil and F & J) pulled production up just to allow for a full week of running ahead of extended – two week shutdowns • Manpower needed at Castwell – for Ductile Vertical work • A full shift is being added on 8/11 Had no other options short term option - Anvil on Shutdown / Urick is making tooling – tooling now set up to allow multiple suppliers to manufacture

  5. 2008 Outsourcing – Limited Supply Base

  6. 2010 Outsourcing – Final Tooling StrategyTooling to be completed by 8/13

  7. Final Results – Outsourcing TimingFull production across 7 suppliers after 7 wks

  8. Final Results – Outsourcing Timing • Why 18 tons behind now? • Anvil had said they were going to run 80T week of 7/24 (ahead of shutdown) – had meant to say 80K lbs.. 40 tons – Shipped 24 tons before annealing shutdown • Why should we be ahead by 110 tons by end of month? • Full normal production will be achieved by 8/16 • Tooling Complete • Summer Shutdowns over • Manpower hired • What if we have one supplier that doesn’t perform • We now have options to move and will make those decisions week by week • Prioritization – for the next 3 weeks • 5 suppliers need prioritization coming out of the summer shutdown gate / startup stage

More Related