WELCOME Leona Heights Sulfur Mine & Creek Cleanup Lindsay Whalin, MS, PG Darin Ranelletti
Leona Heights Sulfur Mine & Creek Cleanup Project purpose & Design Lindsay Whalin, MS, PG San Francisco Bay Water Board
Presentation Outline 1. Lindsay 2. Phil 3. Darin • Purpose of Cleanup • Project Goals • Current Design • Construction Management • Project Duration • Construction days/hours • Road use/ Traffic • Noise control • Dust control • Access route • Staging areas • City Permits • Environmental Review • Timeline • Next Steps
Location McDonell Ave. Leona St. Mining Waste Piles N
Leona Heights Sulfur Mine & Creek Cleanup 5 The Problem
The Problem : Acid Mine Drainage
The Problem : It’s Toxic to Wildlife Leona Creek: Not just ugly… Mercury Cadmium Copper Lead Arsenic 10 to 10,000 x levels toxic to wildlife (no pathway to humans)
The Goals, Actions, & Actors Agencies Involved Project Goals • Cleanup mine site, eliminate acid mine drainage • Cleanup Leona Creek • Minimize impacts • Disturbance of neighbors (dust, noise, traffic) • Tree removal • Wildlife • Water Board • Required and oversees cleanup, design, stream habitat protection • City of Oakland • Permits & environmental review (CEQA) • US Army Corps Engineers • Stream protection • Ca Dept. Fish &Wildlife • Endangered species & stream protection
Leona Heights Sulfur Mine & Creek Cleanup 10 The Solution
Current Condition Mining Waste Natural Hillside
The Solution: Isolate Mining Waste Mining Waste Natural Hillside
The Results : Green, Stable Hillsides Present Future Run-on Prevention Channel Images courtesy of LSA Associates and Andrew McNichol
The Results: : Expanded Cul-de-sac on McDonell Present Future Run-on Prevention Channels Images courtesy of LSA Associates and Andrew McNichol
The Results: Green, Stable Hillsides Present Future Images courtesy of LSA Associates and Andrew McNichol
The Results :Clean, Stable Creek Present Future Skelly and Loy Inc.
Leona Heights Sulfur Mine & Creek Cleanup 17 Construction Management Phil Goalwin, PG E2C Remediation
Construction Management 18 • Staging Areas • Access Route • Logistics of Using McDonell Ave • Dust Control • Noise Control • Construction Days/Hours • Project Duration
Staging Areas • Primary Staging Area • McDonell Cul-De-Sac and Site Entrance • Materials Staging Area • Leona Lodge Overflow Parking Lot
Access Route • McDonell Ave. vs. Fire Road • Why not Fire Road? • Segments with Steep grades (up to 15%) • 180 degree Switchbacks • Appr0ximately 3.0 miles roundtrip • Shuts down trail for 5 months • Larger air emissions • Habitat for Alameda whip snake • Biological mitigation/Vernal Pools • Only emergency access • Need improvements to use • Still need to cross and use McDonell Ave
Access Route • McDonell Ave. vs. Fire Road • Why McDonell Ave? • Right at the primary staging area • Appr0ximately 0.6 miles from materials staging area • Paved road with gentle slope • Less air emissions • No biological mitigation • Do not need improvements to use • Reduced environmental impacts
McDonell Use Logistics • 5 Materials Staging Events • Each Event lasts 5 days (Monday~Friday) • Flagmen with radios to implement traffic control • Small Haul Trucks (with payload <10 tons) • Truck speeds to be kept under 10 mph • Residents will be given priority to truck traffic
Dust Control • Limited water spray to soils graded, excavated, truck loaded., etc. • Amount to control dust, but not cause runoff • Cover soil stockpiles with weighted plastic sheeting • Vehicles <5mph • Minimize material drop heights during unloading
Noise Control • Smaller Equipment • Noise Reduction Blankets on Perimeter Fence • Noise Reduction Blankets on Temporary Fence • No Construction Work at night, on weekends or holidays
Construction Days/Hours • Weekdays only (Monday-Friday) • Working Hours - In Accordance With City Of Oakland Conditions Of Approval • No Holidays
Project Duration • Construction Start • Early to Mid May 2014 • Construction Completion • September 30, 2014
Leona Heights Sulfur Mine & Creek Cleanup 29 Permitting Darin Ranelletti, Planner City of Oakland
City of Oakland Permits • Creek Permit • For clean-up work in creek • Tree Removal Permit • To remove and replace trees impacted by project • Grading Permit • To ensure stable slopes • Street Permit • For work in McDonall Avenue cul-de-sac
Environmental Review (CEQA) • Aesthetics • Air Quality • Biological • Cultural • Geology • Hydrology • Noise • Traffic Environmental analysis to include topics such as: CEQA document = Mitigate Negative Declaration • All impacts reduced to less-than-significant levels
Timeline • Nov 2013: Permit applications submitted to City • Feb 2014: Community meeting • Mar 2014: Public notices sent out • Starts official 30-day public review period • May 2014: Permits issued • May 2014: Project starts • Sept 2014: Project complete
Next Steps • Public notices sent out (March) • Environmental document available on City’s website and in City offices • 30-day public review period • Permits issued
Thank you Questions or comments?