250 likes | 416 Views
Elk Grove Water District Water Rate Update and Connection Fees Habib Isaac – Principal April 10, 2013. 2013 Water Rate Study. Water Rate Study Drivers. First Revenue adjustment pushed back to January 2014 Achieved based on updated reserve balances
E N D
Elk Grove Water District Water Rate Update and Connection Fees Habib Isaac – Principal April 10, 2013
Water Rate Study Drivers • First Revenue adjustment pushed back to January 2014 • Achieved based on updated reserve balances • Revenue adjustments scheduled for each January, if necessary • Revenue recovered - 65% fixed / 35% variable • FY 2012-13 consumption is baseline year for analysis • Projections based on average usage over last two calendar years • Meter conversions accounted for in projections • Consumption for metered accounts increases in first 2 years
FY 2012-13 Consumption Projection • Between July 2012 – December 2012 • Used 2 year average derived from 2011 and 2012 • Already accounts for non-metered conversions • Between January 2013 – June 2013 • Average based on 2011 and 2012 existing metered accounts • Non-metered accounts usage determined as follows: • Expected usage derived on a per month basis using 2011 and 2012 data • Conversion rate equals 125 meters per month • c
Variable Rates Schedule for January 2014 Residential Accounts • Tier 1 = $1.39 • Tier 2 = $2.76 • Non-Residential Accounts • $1.57 • Irrigation Accounts • $1.70 • Existing Structure • Tier 1 = $1.46 • Tier 2 = $1.80
Customer Impact – January 2014 6.36 1.02 1.86
Non-Metered Accounts 70.22 72.00 73.83 76.03 78.96 1" 94.36 96.86 99.44 102.54 106.67 1.5" 123.33 126.70 130.17 134.35 139.91 2" 190.92 196.32 201.88 208.57 217.48 3" Non-Metered; 5-Year Rate Schedule • Non-metered accounts are expected to only be charged 2014 rates • Lot sizes > 4,000 SqFt will still be charged a rate per SqFt • Multiple units will be charged the variable component = $11.00
Next Steps – Water Rate Study • Approval of rate study on April 24, 2013 • Prop. 218 notices mailed May 2, 2013 • Public workshop may be scheduled: May? • Public Hearing scheduled forJune 26, 2013 • New rates implemented on January 1, 2014
Existing Fee Methodology • Meter and Installation Charges • Recovers cost of new meter and installation • Capacity Charges • Applicable to Service Area 1 • Based on cost of CIP in 2003 • Total CIP cost allocated to existing and new equivalent dwelling units (EDU) • Cost per EDU converted into fee schedule based on meter size
Updates to Capacity Charge • Buildout projections refined based on District discussions with the City • Expected buildout reduced down from UWMP projections • Additional water well not necessary; removed from future CIP costs • New development represents approximately 6.1% of total water demand at buildout
What Does the Capacity Charge Cover? • Three components: • Plan-Based: Share of Future CIP • Buy-In: Share of 2003 CIP • Funded through existing bond issues • 2002A and B, 2003A, 2005A • Buy-In: Share of cost of issuance and interest paid
Component #1: Future CIP • A proportional share (6.1%) of four projects is allocated to new development • Railroad Corridor Water Line • Hampton Road WTP Refurbishment • VFDs - Booster Pumps Railroad Street WTF • Unforeseen Capital Projects • Total value of improvements allocated to new development: $74,300
Component #2: 2003 CIP • Improvements in the 2003 Capacity Fee were funded through debt service • Amount of CIP equals $20.5 million • Share of program costs is included in this fee update • Approximately $1.3 million of $20.5 million attributed to new development
Component #3: Share of Debt Service • Proportional share of the cost of issuance is allocated to new development • Additional costs incurred when issuing debt • Approximately $58,500 allocated to new development • Proportional share of interest paid to date is allocated to new development • Reimbursement to rate payers • Total debt paid through 2014 = $30.3 million • Approximately $668,600 allocated to new development • Based on share of 2003 CIP and COI
Next Steps – Connection Fee Study • Approval of Connection Fee Study on April 24, 2013 • 30-day notice prior to Public Hearing: May 26, 2013 • Public Hearing scheduled forJune 26, 2013 • New connection fees implemented on Sep. 1, 2013