An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Raytown C-2 schools 2013 PRELIMINARY BUDGET & Master timeline

  2. JUNE 2012 • Transportation Cuts • Route reduction and consolidation(Done) $250,000 • Reduce guaranteed minimum hours to 4 $150,000 • Food Service Cuts • Reduce the use of pre-packaged products $25,000 • Reduce usage of disposable trays and cutlery $50,000 • Custodial Audit Awarded • Interview TPAs for 403(b)/Section 125 • Proposal from EMS for Efficiency/Staffing Study • Proposal from Architects on RSECC/Admin. Bldg. Feasibility

  3. JULY 2012 • Advertise for and receive RFP from brokers/consultants for benefits • Approval for EMS Study • Approve Third Party Administrator for 403(b)/Section 125 • Approve proposal from architects on RSECC/Admin. Bldg.

  4. August 2012 • Herndon Career Center Restructure • Reduce Cosmetology Program by 1 Instructor $35,000 • Construction Technology Program Closed $23,000 • Revise Diesel Mechanics Fees for Work Done $25,000 • Automotive Technology Program Shift to Performance • Power Sports to Increase Enrollment Numbers $75,000 • Production of Bio-Diesel for use at HCC and District TBD

  5. October 2012 • Receive EMS Study • Recommend Benefits Broker/Consultant

  6. November 2012 • Recommendations from EMS Study

  7. January 2013 • Migrate to SISFIN financial software package ($100,000)

  8. February 2013 • 2013 Budget Update Presentation • Consider Additional Budget Cuts for FY 2014 (as needed) • Transport only children that live at least 1 mile from school $300,000 • Centralized food preparation TBD • Program Contraction at HCC TBD

  9. August 2013 • Move central administration to RSECC $100,000 • Implement School Within A School in all elementary schools TBD • Replace exiting students from Northwood with RSECC programs TBD • Migrate to SISK-12 software package $0

  10. Revenues

  11. Expenditures

  12. BUDGET OVERVIEW

  13. SHORT-RANGE PROJECTIONS