Taylor Road Resurfacing Project

Taylor Road Resurfacing Project. General Information:. Contractor: Perk Company, Inc. Awarded: July 28, 2011 Signed Contract: August 25, 2011 Project Bid Price: $3,600,000 Project Administration: ODOT District 12 Project Length 1.5 miles Project starts at Euclid Heights Blvd.

faunia
Download Presentation

Taylor Road Resurfacing Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Taylor Road Resurfacing Project

  2. General Information: • Contractor: Perk Company, Inc. • Awarded: July 28, 2011 • Signed Contract: August 25, 2011 • Project Bid Price: $3,600,000 • Project Administration: ODOT District 12 • Project Length 1.5 miles • Project starts at Euclid Heights Blvd. • Project ends at Bayreuth Road. • ODOT Project Engineer: Al Yost • ODOT Area Engineer: Patrick McCafferty

  3. Work Schedule Scheduled Start Date: April 2012 Scheduled Completion Date: September 30th 2012 Work will generally be from 7:00 am to 3:30 pm No night work Weekend work only if needed to keep the project on schedule

  4. Work Description • Repair the concrete base and resurface with asphalt from Euclid Hts Blvd to Bayreuth Rd. • All of the existing asphalt will be removed • Extensive concrete slab repairs and replacement from Euclid Hts Blvd to Mayfield Road • Additional concrete base repairs as needed from Mayfield Road to Bayreuth Road • Resurface with approximately 5 ½ “ of asphalt • Eastern most lane from Euclid Heights Blvd to Mayfield Road will be removed. • Road will be 5 lanes wide in this area when work is complete. • New curbs and drainage inlets will be installed

  5. Work Description • Replace damaged portions of curb throughout the project. • Approximately 40 driveway aprons will be replaced (at locations marked for curb replacement) • Upgrade curb ramps to ADA requirements. • Traffic signals at Severance Center Access and Hollister Road will be removed permanently

  6. Phase 1 • Shift all traffic to the East half of the road and make repairs to the West half • Maintain both Northbound and Southbound traffic • From Euclid Hts Blvd to Mayfield Road 1 Southbound lane 2 Northbound lanes • From Mayfield Road to Monticello Blvd 1 Southbound lane 1 Northbound lane 1 Center turn lane • From Monticello Blvd to Bayreuth Road 1 Southbound lane 1 Northbound lane

  7. Phase 1Intersections • Euclid Heights Blvd / Taylor Road • Left turn lane for Northbound traffic • Left turn lane for Southbound traffic • Mayfield Road / Taylor Road • Right turn lane for Northbound traffic • Left turn lane for Southbound traffic • Lanes on Mayfield Road not changed • Monticello Blvd. / Taylor Road • Left turn lane for Northbound traffic

  8. Phase 2 • Shift all traffic to the West half of the road and make repairs to the East half • Maintain both Northbound and Southbound traffic • From Euclid Hts Blvd to Mayfield Road • 1 Northbound lane • 1 Southbound lane • 1 Center turn lane • From Mayfield Road to Bayreuth Road • 1 Northbound lane • 1 Southbound lane

  9. Phase 2Intersections • Euclid Heights Blvd / Taylor Road • Right turn lane for Northbound traffic • Left turn lane for Southbound traffic • Mayfield Road / Taylor Road • Left turn lane for Northbound traffic • Lanes on Mayfield Road not changed

  10. Project Notes • Please watch for construction personnel and equipment while travelling through the work zones • ODOT and the City staff will work with you to mitigate any concerns which will arise during the reconstruction. • City of Cleveland Heights: (216) 291-3737 • ODOT Public Information Office: (216) 584-2006 • ODOT Construction Office: (216) 581-2100 • Al Yost • Pat McCafferty