This document provides an overview of the goals and priorities for Run-11 at .ANDY, including issues to resolve, progress made, and upcoming tasks. It also highlights the long-term goals of the project and the importance of establishing a measuring power for Drell-Yan production. The document concludes with a schematic of the detector for Run-11.

fbooker
Download Presentation

A N DY Status Commissioning with colliding beams (p  +p  at s=500 GeV)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ANDY StatusCommissioning with colliding beams (p+p at s=500 GeV) Reminder of goals and priorities for run-11 L.C.Bland, for AnDY 15 March 2011 Time Meeting, BNL

  2. Integrated Luminosity Estimate to Date • Presently, no accidentals correction (found to be large for ZDC). Singles rates from BBC are now scaled, following 20110302 access. • Requires calibration of effective cross section for BBC via vernier scan. • Jet analyzing power measurement sets goal of 10 / pb for run 11. • Establishing luminosity capability in run 11 is important for Drell Yan attempt in runs 12,13 (150 / pb in each run)

  3. Issues and Plans • Issues • Resolve a few remaining single-channel issues • We are in “production” with a jet trigger >250M jet events recorded. • In coming week… • Increase per bunch intensity for IP2 bump removal? • Remove beam crossing angle at IP2? IP2 DX training yesterday • Complete ECal gain matching Progress made offline in last week • Commission ZDC trigger for local polarimetry. Holes fixed in last week • Commission scaler system for local polarimetry.

  4. Reminder of GoalsLong-term and run-11 • Goals of ANDY project: • Establish that large-xF low-mass dileptons from the Drell-Yan process can be discriminated from background in s=500 GeV p+p collisions • Measure the analyzing power for Drell-Yan production with sufficient statistical precision to test the theoretical prediction of a sign change for DY in relation to semi-inclusive deep inelastic scattering • Establish if robust detection of Drell-Yan dileptons at large xF and low mass requires magnetic analysis  critical for future facilities at RHIC

  5. ANDY Prioritiesfor remainder of RHIC run-11 • Run-11 goals: • Establish the impact of a third IR on RHIC performance for p+p collisions at s=500 GeV - Demonstrate luminosity at IP2, as required for Drell-Yan sample in runs 12 (without magnet),13 (with magnet). Estimate that 150 / pb gives 104 large-rapidity di-electrons with M>4 GeV/c2 for p+p at s=500 GeV. Is this possible in a 10-week run? • Demonstrate calibration of HCal • Measure analyzing power for large xF jet production. Non-zero AN required for jets if Drell-Yan production has an analyzing power. Complete the measurement of the analyzing power for jet production. A non-zero AN for jets is a requirement for Drell-Yan to have non-zero analyzing power. Recent theoretical work establishes intrinsic interest in the jet analyzing power measurement.

  6. Run11 AN(Jet) arXiv:1103.1591 jet AN measurements are required to clarify signs of quark/gluon correlators related to Sivers functions. arXiv:1011.2692v1 s=200 GeV from p+pp “new” Sivers function “old” Sivers function 200GeV Non-zero jet analyzing power essentially a prerequisite before proceeding to Drell Yan • Siver’s effect only (no collin’s effect contribution) • Need AN(Jet) measurements before DY • With ~10/pb & P=50%, AnDY run11 can measure AN(Jet)

  7. Backup

  8. Schematic of detector for Run-11 • Equipment in place: • HCal is two existing 9x12 modules from E864 (NIM406,227) • ECal are two small lead-glass modules from BigCal at JLab • BBC (from PHOBOS) and ZDC • Preshower is newly constructed scintillator arrays • Goals: • Establish impact of 3IR operation on PHENIX/STAR luminosity • Calibrate HCal • relative gain via cosmic-ray m • absolute energy scale via r,L,KS… • Measure hadronic backgrounds to benchmark simulations • Measure jet analyzing power (Lint~10 / pb, P=50%)

  9. Trigger/DAQ electronics Left/right symmetric HCal Left/right symmetric ECal Blue-facing BBC Left/right symmetric preshower Beryllium vacuum pipe IP2 in January, 2011Run-11 Staging of ANDY See http://hena.lbl.gov/IP2/Business/status/<date> for pictures of progress