STEREO Organization. Project Manager Nick Chrissotimos Deputy Project Manager Jim Adams Deputy Project Manager/Instruments Mike Delmont Deputy Project Manager/Resources Pietro Campanella. GSFC Procurement Office Rex Elliot Contracting Officer / Julie Janus. STP Program Support Office
E N D
STEREO Organization Project Manager Nick Chrissotimos Deputy Project Manager Jim Adams Deputy Project Manager/Instruments Mike Delmont Deputy Project Manager/Resources Pietro Campanella GSFC Procurement Office Rex Elliot Contracting Officer / Julie Janus STP Program Support Office Configuration Management / D. Dusterwald-CSC, L. Hepler-CSC Planning / T. Parr-CSC, K. Milligan-CSC, D. Wicks-CSC, J. Rogers-CSC Business Support/ Mandy Tatum-SERV, Bobbie Power-SGT Business Support Financial Manager Elaine Blazosky Resource Analyst Tracy Felton, Linnette Morales, Beverly Thomas Mission Systems Engineering Systems Engineer/ Shane Hynes – Swales Instrument Systems Engineer/ Lisa Bartusek, Steve Wasserzug-Swales Systems Engineering / Joe Cerullo-ASRC S/W Systems Engineering / Jerry Hengemihle-MTEL General Business Support Jack Arrison-OSC Project Support Manager Leslie Cusick-SGT Project Scientist Michael Kaiser AETD Engineering Support Deputy Proj. Scientist Terry Kucera STEREO Science Center Bill Thompson-EITI System Assurance Systems Assurance Mgr. / Michael Haynes Quality Engineer / Pam Hopkins-HTSI, Larry Gibb-SRSTE Observatory Management Observatory Manager/ Larry Christensen Mark Jarosz Instrument Management IMPACT/ UCB Instrument Mgr. / Lil Reichenthal, Renan Borelli JHU/APL Ted Mueller, Project Mgr. Parts Assurance Antonio Reyes-OSC Safety Richard Bolt SWAVES/ UMN Instrument Mgr./ Paul Buchanan Reliability Matt Samuel-MUNIZ SECCHI/ NRL Instrument Mgr./ Bernie Klein Software Quality Assurance Mike Garner-HTSI PLASTIC/ UNH Instrument Mgr./ Art Jacques-OSC 25 November 03
STEREO Status • STEREO re-plan officially approved by Headquarters • Feb 11-24, 2006 launch (mostly due to thruster valve problem) • Increased price cap (about 10-11% including launch slip) all contained within STP probe line item (includes ‘missing’ SSC space weather funding) • No descopes • Instrument delivery target dates have been adjusted based on Feb 2006 launch date. Additional time may be granted on case-by-case basis • Launch vehicle prep time now acceptable (27 months) • Terry Kucera (DPS) heading up EPO effort • First EPO telecon March 17: nominally monthly • STEREO now top priority with Goddard Visualization group • CCMC may offer to collect and run STEREO models (steering committee studying this now) • Post-launch organization/operations now being actively pursued • Mission Director to be named (for post launch) • Mission Operation Manager (‘MOM’) to help organize pre-launch
Science Teams STEREO Phase E Management Structure Mission Director Project Scientist SSC Project Manager APL DSN Contractual DSN Technical Engineering Support Mission Operations FDF MLK 3/3/04