1 / 9

Supplier Improvement Program Update

Join the government systems meeting in Reno for an update on the Supplier Improvement Program (PIA) outlining background, approach, data analysis, 4-phase system, current status, and results. Learn about the joint effort to address paperwork issues and achieve systemic improvements.

fgina
Download Presentation

Supplier Improvement Program Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Supplier Improvement Program Update PIA Government Systems Meeting Reno, NV 11 February 2011

  2. Outline • Background • Approach • Data Analysis • 4 Phase approach • Current status • Results

  3. Background • Team origin started with MC-6 and T-11 Prime contractor’s • Originated out of PIA discussions • Driven by increased Government scrutiny during First Articles and First Production Lots • Evidence of common issues across supply base • Team Objectives • Enhance the performance of the Parachute Industry supply base • Leverage our shared resources to address systemic or critical shared supplier issues • Strengthen communication of supplier related issues across the Parachute Industry • Identify issues proactively and work on preventive actions

  4. Approach • Meet regularly via teleconference • Agree upon most significant supply chain issues facing the industry • Use data to guide decisions • Consider frequency, severity, and likelihood of detection • Establish prioritization (pareto principle) • Determine action plans for top one or two issues • Spread the actions across the team as much as possible • Document meeting with minutes and actions

  5. Data Analysis Results Data overwhelmingly revealed - Paperwork #1 issue 70% of rejections for paperwork 80% of rejections for paperwork

  6. Paperwork Improvement Phases Phase 4 Credit Withhold ($250) 4th Defect Each defective lot leads to the next step… Phase 3 Delivery Release 3rd Defect Phase 2 Corrective Actions 2nd Defect 5 consecutive acceptable lots Phase 1 Notification 1st Defect Starting point

  7. Current Status No suppliers in Phase 3 or 4 to date…

  8. Results Reductions in paperwork issues reported by every Prime

  9. Summary • Joint prime manufacturers team created to improve systemic supply base issues • Data identified Paperwork as largest supply chain issue by frequency • Team jointly implementing Paperwork Improvement Program that has 4 phases • Significant improvement seen to date across entire supply chain • Continued monitoring performance going forward Focused efforts resulting in systemic improvements

More Related