CFC ANCOP ROTARY HOMES ANswering the Cry of the Poor
Progress Report July 18, 2012 First Cluster-Maynilad Funded Houses
FACTORS THAT CONSTRIBUTED TO THE DELAY • Condition of the site. • Difficulty in mobilization considering the simultaneous • work going on in the same area (house construction • and site development) • Lack of power supply. • Beneficiaries need to support the financial and material • requirements of their family. • Weather • Suitable site for forms fabrication. • Familiarization with the new technology.
WHAT PROGRESS HAVE WE ACCOMPLISHED AFTER JUNE 18? FIRST CLUSTER CONSISTING OF 14 HOUSES
PROGRESS IN THE CONSTRUCTION FROM JUNE 18, TO JULY 18, 2012: • Concrete slab for the model unit. • Completion of 2nd floor tie beam. • Additional Panel. • Completion of ground floor for the 14 units.
Program of works: • JULY • 3rd week-finish the wall partition for the 2nd floor of the first row. • 4th week-finish the walls of the 2nd row. • AUGUST • 1st week-put the c-parlenes and possibly the long span color roof. • 2nd week-fabrication and installation of doors and windows. • 3rd week-installing the kitchen zink and labatory and other finishing works. • Aug.24-BUILD DAY. (PAINTING)
DAYS WORK/UNIT MONTHACTIVITY NO. OF DAYS FEB - GROUNDBREAKING/CLP MARCH - CLP/EXCAVATION APRIL - CLP/EXCAVATION 15 MAY - FOOTING AND TIE BEAM 26 JUNE - CONSTRUCTION OF GROUND FLOOR 25 JULY - GROUND FLOOR, 2ND FLR BEAM AND WALL PARTITION 13 ___ TOTAL NO. OF DAYS WORK 79 === NO. OF DAYS SPEND PER UNIT TO THIS DATE: (79 DAYS DIVIDED BY 14 UNITS) 5.642857