320 likes | 470 Views
2012 YEAR IN REVIEW. MAJ Alan Apple . Roadmap. Triumvirate Environmental, Inc. (GAO) “The key to keeping your balance is knowing when you've lost it.” –Unbalanced Pricing. ePlus Technology, Inc. v. Federal Communications Commission, (CBCA)
E N D
2012 YEAR IN REVIEW MAJ Alan Apple
Roadmap • Triumvirate Environmental, Inc. (GAO) • “The key to keeping your balance is knowing when you've lost it.” –Unbalanced Pricing. • ePlus Technology, Inc. v. Federal Communications Commission, (CBCA) • “Some people view litigation as an impasse.”- Claim imbedded in T4C Settlement. • D&M Grading, Inc., v. Department of Agriculture (CBCA) • “It’s hard to make bush hogging sound more sophisticated”- Differing Site Conditions. • Appeal of Laura K. McNew (PSBCA) • “Maybe momma was wrong: as long as everyone else breaks the rules, you can too. –Prevailing practice can excuse otherwise prohibited behavior and make it reasonable.
Triumvirate Environmental, Inc. (GAO) Lesson Learned: The key to keeping your balance is knowing when you've lost it.
Triumvirate Environmental, Inc. Protest challenging the VA’s price evaluation, technical evaluation, and trade-off decision • RFQ to establish a BPA for a General Services Admin. (GSA) Federal Supply Schedule (FSS) contract for hazardous waste removal services. • Non-price factors, when combined, “are significantly more important than price.” • Winning quote- $3.21 million. Triumvirate quote $2.18 million.
Triumvirate Environmental, Inc. Why the extra $1.3 million? • Pricing was “highly unrealistic with fifteen line items being impossibly low ($5.00) or left blank. • Used historical usage knowledge to give unbalanced pricing.
Triumvirate Environmental, Inc. Issue: Whether low quotations (multiple $5 line items) was an inherently high risk to the government supporting rejection of a quotation as unbalanced. Rule- • Unbalanced pricing exists when one or more contract line items is significantly over or understated. • Agencies cannot reject an offer solely because it is unbalanced. They must: consider the risks to the government associated with the unbalanced pricing, including the risk that unbalancing will result in unreasonably high prices for contract performance. Decision: CO’s must reasonably identify any risk to the government inherent in low/unbalanced quotations.
Triumvirate Environmental, Inc. (GAO) Lesson Learned: The key to keeping your balance is knowing when you've lost it.
ePlus Technology, Inc. v. Federal Communications Commission Lesson Learned: Some people view litigation as an impasse.
ePlus Technology, Inc. v. Federal Communications Commission Purchase order for commercially available, common-off-the-shelf “thin clients” for $351,900 on 15 Sept. 2010
ePlus Technology, Inc. v. FCC • 29 September 2010- Termination for Convenience • 4 March 2011- ePlus hand-delivered a letter “FOR SETTLEMENT PURPOSES ONLY” which, ironically, also requested that the letter be considered as a “claim, as a matter of right, for payment” • 29 September ePlus filed appeal of the governments lack of response (deemed denial)
ePlus Technology, Inc. vs. FCC • Govt. argues: lack of subject mater jurisdiction because appeal is not “ripe” for review. i.e. negotiations were not at an impasse. • Rule: • Contractor may submit a settlement proposal and claim together. • Once negotiations reach an impasse, it becomes a claim. • Whether an impasse has been reached may be determined by the parties actions and statements.
What could be an impasse: • When a contracting officer told a contractor that he would not consider the contractors proposal; • Where a contractor explicitly requested a final decision in conjunction with CO’s refusal to meet and negotiate; • Fruitless negotiations; • Written request to the CO that he “settle” the claims; • A “unilateral decision” by the contracting officer; and, of course; • No communications after 6 months and the contractor files an appeal of your deemed denial of his claim.
ePlus Technology, Inc. v. Federal Communications Commission Lesson Learned: Some people view litigation as an impasse.
D&M Grading, Inc. v. Department of Agriculture Lesson Learned: It’s hard to make bush hogging sound more sophisticated than it is.
D&M Grading v. Dept. of Agriculture An appeal of a Termination for Default on a roadway vegetation maintenance contract (i.e. brushing) contract.
D&M Grading v. Dept. of Agriculture • Contractor was to perform “brushing” over and along the roads. • Vegetation shall be removed to a max height of 6 inches above surface, trees larger than 6 inches are to remain, and all woody debris within the clearing limits shall be lopped and scattered outside clearing limits. • “Declined” to complete the contract: “never seen such neglected roads.” • Contractor claims site inaccessible due to snow-pack and differing site conditions.
D&M Grading v. Dept. of Agriculture Issue: Whether a contractors decision to forgo a site visit and later encountering neglected roads represents a Differing Site Condition and provides a basis to shift contractor risk to the agency. Type I DSC - actual conditions encountered differ materially from those represented within the contract. Type II DSC- actual conditions encountered differ materially from conditions ordinarily encountered and generally recognized to exist in the area Decision:“It is immaterial that the site was inaccessible at the time the contractor formulated its task order pricing; either on does not seek the award or one accounts for the unknown element in pricing.”
D&M Grading, Inc. v. Department of Agriculture Lesson Learned: It’s hard to make bush hogging sound more sophisticated than it is.
Appeal of Laura A. McNew Lesson Learned: Maybe momma was wrong: as long as everyone else breaks the rules, you can too.
Appeal of Laura K. McNew, Appeal of a Contracting Officer’s final decision to terminate for default a mail transportation and delivery contract • T4D because she was not reliable, trustworthy, and of good character. • Using a $10 True Value coupon from the undeliverable bulk business mail (UBBM) container. • There was an established practice in the Post Office to allow UBBM use of promotional pens and items of nominal value. Decision- Reasonable to for appellant to believe she could take and use coupon, therefore excusing her from “breach.”
Lessons Learned from the Post Office • A 2 inch knife is not a dangerous weapon (Appeal of Wayne L. Orr) • Threatening to jump through the phone and strangle a contract specialist in a profanity-laced diatribe doesn’t constitute an immediate threat of harm. (Lee Aron Van Dyke) • As long as everyone else is breaking the rules, maybe you can too. (Laura K. McNew)
Appeal of Laura A. McNew Lesson Learned: Maybe momma was wrong: as long as everyone else breaks the rules, you can too.
References • Triumvirate Environmental, Inc., Comp. Gen. B-406809 (September 5, 2012). • “The key to keeping your balance is knowing when you've lost it.” –Unbalanced Pricing. • ePlus Technology, Inc., v. Federal Communications Commission, CBCA 2573 (August 1, 2012). • “Some people view litigation as an impasse.”- Claim imbedded in T4C Settlement. • D&M Grading, Inc., v. Department of Agriculture, CBCA 2625 (April 24, 2012). • It’s hard to make bush hogging sound more sophisticated than it is. .”- Differing Site Conditions. • Appeal of Laura K. McNew, PBCA 6286 (April 23, 2012) • Maybe momma was wrong: as long as everyone else breaks the rules, you can too. Prevailing practice can excuse otherwise prohibited behavior and make it reasonable.
The Fiscal and Contracting Process& Commitment and Obligation