An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status Report #1 Autonomous GPS Vehicle Brendon Balouch Vernal Garcia Brian Gonzalez Kim Pham January 29, 2006 Purpose: To implement a fastest route algorithm in a GPS enabled vehicle

  2. Overall Need: • Project Milestones: • Establish communication between GPS and microprocessor • Build a steering control circuit • Build a drive train control circuit • Write our fastest route algorithm. • Integrate all pieces into a single package

  3. Task Completions • Communication established between GPS and microprocessor • RS-232 8N1 protocol successfully programmed for the ATMEL AT91 processor • GPS NMEA data sentences successfully decoded and converted to calculable integers.

  4. Task Completion Dates • PWM Motor Driver Schematic • February 9th, 2007 • H-Bridge Steering Controller Schematic • February 9th, 2007 • Preliminary Fastest Route Algorithm • February 23th, 2007 • Project Synergy • March 16th, 2007

  5. Projects Which Will Begin • PWM Motor Control Circuit • H-Bridge Steering Control Circuit • Fastest Route Algorithm • Programming of Processor to Support Peripheral Devices

  6. Recently Completed Tasks • Vehicle Purchased • December 29th, 2006 • Processor Obtained • October 10th, 2006 • GPS Purchased • November 18th, 2006