Loss of fill 2734

Loss of fill 2734. Global Post Mortem Event Event Timestamp: 15/06/12 15:54:55.343 Fill Number: 2733 Accelerator / beam mode: PROTON PHYSICS / STABLE BEAMS Energy : 3999960 [MeV] Intensity B1/B2: 15691 / 15005 [e^10 charges] Event Category / Classification: PROTECTION_DUMP /

fleta
Download Presentation

Loss of fill 2734

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Loss of fill 2734 • Global Post Mortem Event • Event Timestamp: 15/06/12 15:54:55.343 • Fill Number: 2733 • Accelerator / beam mode: PROTON PHYSICS / STABLE BEAMS • Energy: 3999960 [MeV] • Intensity B1/B2: 15691 / 15005 [e^10 charges] • Event Category / Classification: PROTECTION_DUMP / • MULTIPLE_SYSTEM_DUMP • First BIC input Triggered: First USR_PERMIT change: Ch11-BLM_MSK: A T -> F on CIB.SR7.S7.B1 R.Schmidt / I.Romera

  2. Loss of fill 2734 [ms] [ms] R.Schmidt / I.Romera

  3. From BIS logs BLM triggered Beam dump request PIC only sees the Powering problem after ~60ms

  4. From PIC R.Schmidt / I.Romera

  5. Loss of fill 2734 – change of orbit B1 R.Schmidt

  6. Loss of fill 2734 – change of orbit B2 R.Schmidt

  7. From FGC • Power converter only sends Powering Failure at 15:54:55.420 • -One can see strange jump in current some ms before…

  8. Beam losses beam 1 for fill 2734 R.Schmidt

  9. Beam losses beam 2 for fill 2734 R.Schmidt

  10. Comments • This has been one of the standard cases during the design of the MP system, and the reason for the diverse redundancy in the systems • We would not have dared to test such case with high intensity beams • MP worked as expected….. • EPC should investigate how to send out a Powering Failure event in such case • In order to no only rely on the BLMs, the Fast Beam Current Change Monitor is required … R.Schmidt / I.Romera