An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CFSPPP-PLTU LAMPUNG (2 x 100 MW) PT. GAKA KARYA ENGINEERING RIGGING DEPARTMENT

  2. RIGGING DEPARTMENT ANALYZE AND PLANED ACTIVITY FOR LIFTING AND ERECTION WORK

  3. START • DATA MATERIAL • DIMENSION • WEIGHT REFERENCE 1. RIGGING BOOK 2. EQUIP. MANUAL 3. B30.24-2003 Safety Standard 4. B30.21-2005 manually lever operated hoist 5. Australian Standard, AS 3569--1989, Wire ropes 6. Australian Standard, AS 2759--1985, Wire ropes 7. NAVFAC P-307, Juni 2003 8. Construction Industry Crane Safety Summit, 2009 B NEED DUO CRANE Yes No MONO CRANE TAILING DESIGN A

  4. A B Risk JSA Safe RIGGING PLAN ACTION CONTROL REPORT STOP

  5. STEP-1 1.TAHAP PERTAMA, OBJECT YANG AKAN DI ANGKAT ADALAH GENERATOR UNIT 2 (BARAT) 2.INSTALL RAIL WAY FOR SLINDING. 3.MENURUNKAN GENARATOR DARI ATAS "GOLDEFER" 4.TAKE IT ON RAIL WAY. 5.READY TO SLIDING. 6.MOVE IT UNTIL 30.000MM OVER THAN BEFORE ON ELEVATION +500.

  6. STEP-2 1.TAHAP KEDUA, OBJECT YANG AKAN DI ANGKAT ADALAH GENERATOR UNIT 1 (TIMUR) 2.MENURUNKAN GENARATOR DARI ATAS "GOLDEFER" 3.TAKE IT ON RAIL WAY. 4.READY TO SLIDING. 5.MOVE IT UNTIL TO CENTERLINE OF GENERATOR ON ELEVATION +500.

  7. STEP-3 1.INSTALL RAIL WAY SEJAJAR DENGAN SUMBU GENERATOR. 2.MOVE IT UNTIL 7000MM OVER THAN BEFORE.

  8. STEP-4 1.INSTALL GANTRY CRANE FOR LIFTING GENERATOR UNIT 1 (TIMUR)

  9. STEP-5 1.CONNECTED ALL CONNECTOR, 2.LIFT OBJECT UNTIL ELEVATION 10.000 UP TO GROUND FLOOR, 3.MOVE OBJECT BY CRANE UNTIL POSITION (FROM BARAT TO TIMUR)

  10. STEP-6 1.INSTAL SKIDDING UNIT KETGA DAN KEEMPAT DI KAKI TENGAH. 2.LEPASKAN KAKI PANJANG.

  11. STEP-7 1.GESER OBJECT KE POSISI TARGET.

  12. STEP-8 1.TURUNKAN OBJECT KE POSISI TARGET.

  13. STEP-9 1.SLIDING GENERATOR UNIT 2 (BARAT) TO CENTER LINE ON GROUND FLOOR.

  14. STEP-10 1.PREPARATION ACTIVITIES FOR GENERATOR UNIT 2 (BARAT)

  15. STEP-11 1.CONNECTED ALL CONNECTOR, 2.LIFT OBJECT UNTIL ELEVATION 10.000 UP TO GROUND FLOOR, 3.MOVE OBJECT BY CRANE UNTIL POSITION (FROM TIMUR TO BARAT)

  16. STEP-12 1.INSTAL SKIDDING UNIT KETGA DAN KEEMPAT DI KAKI TENGAH. 2.LEPASKAN KAKI PANJANG.

  17. STEP-13 1.GESER OBJECT KE POSISI TARGET.

  18. STEP-14 1.TURUNKAN OBJECT KE POSISI TARGET.

  19. RIGGING DEPARTMENT LOGO LIFT SWING MOVE DOWN In safety corridor THINK SAFE DO SAFELY SAFETY FIRST

  20. CFSPPP-PLTU LAMPUNG (2 x 100 MW) PT. GAKA KARYA ENGINEERING RIGGING DEPARTMENT